| 1 | Const. of CC Building at Ward No.15 Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 775 days beyond expected completion
Read more (2 more)Show less- 98% similarity with another nearby work
- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹2.00 L | MEDIUM 60
delay 25duplication 14cost 13 | |
| 2 | Const. of CC at Dumal Samaj Maheswari Bhaban at Janmura Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - ₹500,000 against a ₹200,000 median for Community Buildings works in SUBARNAPUR (150% above, 139 peer works)
- 692 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹5.00 L | MEDIUM 59 | |
| 3 | Const. of CC at Kaibarta Samaj at Sonepur Municipality Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - ₹500,000 against a ₹200,000 median for Community Buildings works in SUBARNAPUR (150% above, 139 peer works)
- 692 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹5.00 L | MEDIUM 59 | |
| 4 | Const. of Community Centre near Durga Mandap at Agalpur, Aga Community Buildings — BALANGIR(DISTRICT COLLECTOR BOLANGIR_IDA) - ₹500,000 against a ₹200,000 median for Community Buildings works in BALANGIR (150% above, 405 peer works)
- 545 days beyond expected completion
| BALANGIR | ₹5.00 L | MEDIUM 54 | |
| 5 | Const. Of room (1st Floor) at Marwari Seva Sadan at Balangir Community Buildings — BALANGIR(DISTRICT COLLECTOR BOLANGIR_IDA) - ₹1,000,000 against a ₹200,000 median for Community Buildings works in BALANGIR (400% above, 405 peer works)
- 775 days beyond expected completion
| BALANGIR | ₹10.00 L | MEDIUM 54 | |
| 6 | Const. of Mini Stadium near Dwarsani Mandir at Ichgaon, Para Religious & Cultural — BALANGIR(DISTRICT COLLECTOR BOLANGIR_IDA) - ₹1,000,000 against a ₹300,000 median for Religious & Cultural works in BALANGIR (233% above, 83 peer works)
- 775 days beyond expected completion
| BALANGIR | ₹10.00 L | MEDIUM 54 | |
| 7 | Const. of Community Centre at Nagaon-B, Nagaon-B GP Community Buildings — BALANGIR(DISTRICT COLLECTOR BOLANGIR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 730 days beyond expected completion
Read more (1 more)Show less- 98% similarity with another nearby work
| BALANGIR | ₹2.00 L | MEDIUM 52
delay 25duplication 12cost 11 | |
| 8 | Construction of Meeting Hall at Saraswasti Shishu Vidya Mand Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - ₹1,000,000 against a ₹200,000 median for Community Buildings works in SUBARNAPUR (400% above, 139 peer works)
- 101 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹10.00 L | MEDIUM 48 | |
| 9 | Construction of Additional Classroom in Saraswati Shishu Vid Education — Subarnapur(District Collector Subarnapur_IDA) - ₹500,000 against a ₹300,000 median for Education works in SUBARNAPUR (67% above, 20 peer works)
- 101 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹5.00 L | MEDIUM 48 | |
| 10 | Const. of CC Building near Hanuman Mandir at Bagbar Religious & Cultural — Subarnapur(District Collector Subarnapur_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 775 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹1.00 L | MEDIUM 47 | |
| 11 | Const. of CC Building near Maheshwari Mandir at Phulmuthi, C Religious & Cultural — Subarnapur(District Collector Subarnapur_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 775 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹2.00 L | MEDIUM 47 | |
| 12 | Const. of CC building near Purnamsi Sankrutika Sansad at Kar Religious & Cultural — Subarnapur(District Collector Subarnapur_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 775 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹2.00 L | MEDIUM 47 | |
| 13 | Const. of CC Building at Andhradera near Metakani Mandir at Religious & Cultural — Subarnapur(District Collector Subarnapur_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 775 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹2.00 L | MEDIUM 47 | |
| 14 | Const. of CC Building at Kuhibahal Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 775 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹2.00 L | MEDIUM 47 | |
| 15 | Const. of CC Building at Tulundapali, Seledi GP Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 775 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹2.00 L | MEDIUM 47 | |
| 16 | Const. of CC Building at Kaudiamunda, Sankara GP Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 775 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹2.00 L | MEDIUM 47 | |
| 17 | Const. of CC Building at Khemaloi Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 775 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹2.00 L | MEDIUM 47 | |
| 18 | Const. of CC Building at Kumarkeli,GP-Mahada Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 775 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹2.00 L | MEDIUM 47 | |
| 19 | Const. of CC Building at Kadodar Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 775 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹2.00 L | MEDIUM 47 | |
| 20 | Const. of Mandap at Jharbahali, Chadeipank GP Religious & Cultural — Subarnapur(District Collector Subarnapur_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 775 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹2.00 L | MEDIUM 47 | |
| 21 | Const. of CC Building at Jambahalipada, GP-Kalapathar Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 775 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹2.00 L | MEDIUM 47 | |
| 22 | Const. of CC Building at Keshalpura, Jaloi GP Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 775 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹2.00 L | MEDIUM 47 | |
| 23 | Const. of CC Building at Harinipali, Kotsamlai GP Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 775 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹2.00 L | MEDIUM 47 | |
| 24 | Const. of CC Building at Baghapali, Kotsamalai GP Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 775 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹2.00 L | MEDIUM 47 | |
| 25 | Const. of CC Building at Raksa Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 775 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹2.00 L | MEDIUM 47 | |