| 1 | Construction of shelters for animal Other — SHIVAMOGGA(DEPUTY COMMISSIONER SHIMOGA_IDA) - ₹1,500,000 against a ₹325,000 median for Other works in SHIVAMOGGA (362% above, 16 peer works)
- 219 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 53% of this agency's ₹76,492,740 spend went to one vendor (Nirmithi Kendra Shivamogga), across 11 vendors and 333 transactions
| SHIVAMOGGA | ₹15.00 L | HIGH 78
cost 25delay 25duplication 20 | |
| 2 | Construction of shelters for animal Other — SHIVAMOGGA(DEPUTY COMMISSIONER SHIMOGA_IDA) - ₹1,500,000 against a ₹325,000 median for Other works in SHIVAMOGGA (362% above, 16 peer works)
- 219 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 51% of this agency's ₹64,252,561 spend went to one vendor (Nirmithi Kendra Shivamogga), across 9 vendors and 274 transactions
| SHIVAMOGGA | ₹15.00 L | HIGH 78
cost 25delay 25duplication 20 | |
| 3 | Construction work of Kannada Sahitya Bhavan Community Buildings — HAVERI(DEPUTY COMMISSIONER HAVERI_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in HAVERI (100% above, 155 peer works)
- 373 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 56% of this agency's ₹59,687,756 spend went to one vendor (Bommai Zilla Nirmithi Kendra), across 23 vendors and 185 transactions
| HAVERI | ₹10.00 L | HIGH 78
cost 25delay 25duplication 20 | |
| 4 | Construction of Dining Hall Community Buildings — Dangs(DISTRICT COLLECTOR DANG_IDA) - ₹1,000,000 against a ₹250,000 median for Community Buildings works in DANGS (300% above, 18 peer works)
- 609 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 49% delay rate across its projects
| DANGS | ₹10.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 5 | Construction of Dining Hall Community Buildings — Dangs(DISTRICT COLLECTOR DANG_IDA) - ₹1,000,000 against a ₹250,000 median for Community Buildings works in DANGS (300% above, 18 peer works)
- 609 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 49% delay rate across its projects
| DANGS | ₹10.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 6 | Construction of Community Hall Community Buildings — BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) - ₹1,500,000 against a ₹500,000 median for Community Buildings works in BELAGAVI (200% above, 447 peer works)
- 609 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 49% delay rate across its projects
| BELAGAVI | ₹15.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 7 | Construction of Community Hall Community Buildings — BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) - ₹1,500,000 against a ₹500,000 median for Community Buildings works in BELAGAVI (200% above, 447 peer works)
- 609 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 49% delay rate across its projects
| BELAGAVI | ₹15.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 8 | Construction work of Kannada Sahitya Bhavan Community Buildings — HAVERI(DEPUTY COMMISSIONER HAVERI_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in HAVERI (100% above, 155 peer works)
- 373 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| HAVERI | ₹10.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 9 | Construction of New building for Chatnalli Milk Producers Co Community Buildings — BIDAR(DEPUTY COMMISSIONER BIDAR_IDA) - ₹1,000,000 against a ₹400,000 median for Community Buildings works in BIDAR (150% above, 186 peer works)
- 590 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BIDAR | ₹10.00 L | HIGH 73
cost 25delay 25duplication 20 | |
| 10 | Construction of New building for Marakhal Milk Producers Coo Community Buildings — BIDAR(DEPUTY COMMISSIONER BIDAR_IDA) - ₹1,000,000 against a ₹400,000 median for Community Buildings works in BIDAR (150% above, 186 peer works)
- 590 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BIDAR | ₹10.00 L | HIGH 73
cost 25delay 25duplication 20 | |
| 11 | Construction of New building for Bannalli Milk Producers Coo Community Buildings — BIDAR(DEPUTY COMMISSIONER BIDAR_IDA) - ₹1,000,000 against a ₹400,000 median for Community Buildings works in BIDAR (150% above, 186 peer works)
- 590 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BIDAR | ₹10.00 L | HIGH 73
cost 25delay 25duplication 20 | |
| 12 | Construction of New building for Sastapur Milk Producers Coo Community Buildings — BIDAR(DEPUTY COMMISSIONER BIDAR_IDA) - ₹1,000,000 against a ₹400,000 median for Community Buildings works in BIDAR (150% above, 186 peer works)
- 590 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BIDAR | ₹10.00 L | HIGH 73
cost 25delay 25duplication 20 | |
| 13 | Construction of New building for Bagadoori Milk Producers Co Community Buildings — BIDAR(DEPUTY COMMISSIONER BIDAR_IDA) - ₹1,000,000 against a ₹400,000 median for Community Buildings works in BIDAR (150% above, 186 peer works)
- 590 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BIDAR | ₹10.00 L | HIGH 73
cost 25delay 25duplication 20 | |
| 14 | Construction of New building for Chandoori Milk Producers Co Community Buildings — BIDAR(DEPUTY COMMISSIONER BIDAR_IDA) - ₹1,000,000 against a ₹400,000 median for Community Buildings works in BIDAR (150% above, 186 peer works)
- 590 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BIDAR | ₹10.00 L | HIGH 73
cost 25delay 25duplication 20 | |
| 15 | Construction of New building for
Maroor Milk Producers Coop Community Buildings — BIDAR(DEPUTY COMMISSIONER BIDAR_IDA) - ₹1,000,000 against a ₹400,000 median for Community Buildings works in BIDAR (150% above, 186 peer works)
- 590 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BIDAR | ₹10.00 L | HIGH 73
cost 25delay 25duplication 20 | |
| 16 | Construction of New building for Chatnalli Milk Producers Co Community Buildings — BIDAR(DEPUTY COMMISSIONER BIDAR_IDA) - ₹1,000,000 against a ₹400,000 median for Community Buildings works in BIDAR (150% above, 186 peer works)
- 590 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BIDAR | ₹10.00 L | HIGH 73
cost 25delay 25duplication 20 | |
| 17 | Construction of New building for Marakhal Milk Producers Coo Community Buildings — BIDAR(DEPUTY COMMISSIONER BIDAR_IDA) - ₹1,000,000 against a ₹400,000 median for Community Buildings works in BIDAR (150% above, 186 peer works)
- 590 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BIDAR | ₹10.00 L | HIGH 73
cost 25delay 25duplication 20 | |
| 18 | Construction of New building for Bannalli Milk Producers Coo Community Buildings — BIDAR(DEPUTY COMMISSIONER BIDAR_IDA) - ₹1,000,000 against a ₹400,000 median for Community Buildings works in BIDAR (150% above, 186 peer works)
- 590 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BIDAR | ₹10.00 L | HIGH 73
cost 25delay 25duplication 20 | |
| 19 | Construction of New building for Sastapur Milk Producers Coo Community Buildings — BIDAR(DEPUTY COMMISSIONER BIDAR_IDA) - ₹1,000,000 against a ₹400,000 median for Community Buildings works in BIDAR (150% above, 186 peer works)
- 590 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BIDAR | ₹10.00 L | HIGH 73
cost 25delay 25duplication 20 | |
| 20 | Construction of New building for Bagadoori Milk Producers Co Community Buildings — BIDAR(DEPUTY COMMISSIONER BIDAR_IDA) - ₹1,000,000 against a ₹400,000 median for Community Buildings works in BIDAR (150% above, 186 peer works)
- 590 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BIDAR | ₹10.00 L | HIGH 73
cost 25delay 25duplication 20 | |
| 21 | Construction of New building for Chandoori Milk Producers Co Community Buildings — BIDAR(DEPUTY COMMISSIONER BIDAR_IDA) - ₹1,000,000 against a ₹400,000 median for Community Buildings works in BIDAR (150% above, 186 peer works)
- 590 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BIDAR | ₹10.00 L | HIGH 73
cost 25delay 25duplication 20 | |
| 22 | Construction of New building for
Maroor Milk Producers Coop Community Buildings — BIDAR(DEPUTY COMMISSIONER BIDAR_IDA) - ₹1,000,000 against a ₹400,000 median for Community Buildings works in BIDAR (150% above, 186 peer works)
- 590 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BIDAR | ₹10.00 L | HIGH 73
cost 25delay 25duplication 20 | |
| 23 | Road construction work Roads & Paving — BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) - ₹1,500,000 against a ₹500,000 median for Roads & Paving works in BELAGAVI (200% above, 59 peer works)
- 146 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 49% delay rate across its projects
| BELAGAVI | ₹15.00 L | HIGH 73
cost 25delay 20duplication 20 | |
| 24 | Road construction work Roads & Paving — BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) - ₹1,500,000 against a ₹500,000 median for Roads & Paving works in BELAGAVI (200% above, 59 peer works)
- 146 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 49% delay rate across its projects
| BELAGAVI | ₹15.00 L | HIGH 73
cost 25delay 20duplication 20 | |
| 25 | Construction of 8 classrooms with a total area of 7,200 sq. Education — VIJAYAPURA(DEPUTY COMMISSIONER BIJAPUR_IDA) - ₹2,500,000 against a ₹250,000 median for Education works in VIJAYAPURA (900% above, 146 peer works)
- 73 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 74% of this agency's ₹91,833,067 spend went to one vendor (Nirmithi kendra vijayapur), across 40 vendors and 130 transactions
| VIJAYAPURA | ₹25.00 L | MEDIUM 69
cost 25duplication 20agency 13 | |