| 1 | Construction of Panchayat Ghar Community Buildings — BATHINDA(DEPUTY COMMISSIONER BHATINDA_IDA) - ₹1,000,000 against a ₹298,400 median for Community Buildings works in BATHINDA (235% above, 34 peer works)
- 185 days beyond expected completion
| BATHINDA | ₹10.00 L | MEDIUM 61
cost 25delay 25duplication 6 | |
| 2 | Construction of Stadium Sports — SRI MUKTSAR SAHIB(DEPUTY COMMISSIONER SRI MUKTSAR SAHIB_IDA) - ₹990,000 against a ₹400,000 median for Sports works in SRI MUKTSAR SAHIB (148% above, 11 peer works)
- 85 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SRI MUKTSAR SAHIB | ₹9.90 L | MEDIUM 59
cost 25duplication 20delay 12 | |
| 3 | Construction of Shed in Shamshanghat Community Buildings — SRI MUKTSAR SAHIB(DEPUTY COMMISSIONER SRI MUKTSAR SAHIB_IDA) - ₹700,000 against a ₹320,000 median for Community Buildings works in SRI MUKTSAR SAHIB (119% above, 22 peer works)
- 85 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SRI MUKTSAR SAHIB | ₹7.00 L | MEDIUM 59
cost 25duplication 20delay 12 | |
| 4 | Construction of B/W of Kabristan Religious & Cultural — MANSA(DEPUTY COMMISSIONER MANSA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 727 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MANSA | ₹1.50 L | MEDIUM 58
delay 25duplication 20cost 11 | |
| 5 | Purchase of Gym Equipment Sports — MANSA(DEPUTY COMMISSIONER MANSA_IDA) - 353 days beyond expected completion
- 100% similarity with another nearby work
| MANSA | ₹1.50 L | MEDIUM 56
delay 25duplication 20cost 9 | |
| 6 | Purchase of Gym Equipment Sports — MANSA(DEPUTY COMMISSIONER MANSA_IDA) - 353 days beyond expected completion
- 100% similarity with another nearby work
| MANSA | ₹2.50 L | MEDIUM 55
delay 25duplication 20cost 8 | |
| 7 | Purchase of Mobile water Tank Water — MANSA(DEPUTY COMMISSIONER MANSA_IDA) - ₹188,000 against a ₹99,987 median for Water works in MANSA (88% above, 64 peer works)
- 78 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MANSA | ₹1.88 L | MEDIUM 55
cost 22duplication 20delay 11 | |
| 8 | Purchase of Gym Equipment Sports — MANSA(DEPUTY COMMISSIONER MANSA_IDA) - 161 days beyond expected completion
- 100% similarity with another nearby work
| MANSA | ₹3.25 L | MEDIUM 54
delay 22duplication 20cost 9 | |
| 9 | Providing and Laying Pipe Line from Thakatposh to Mall Ke Ko Water — MANSA(DEPUTY COMMISSIONER MANSA_IDA) - ₹353,000 against a ₹99,987 median for Water works in MANSA (253% above, 64 peer works)
- 626 days beyond expected completion
| MANSA | ₹3.53 L | MEDIUM 53 | |
| 10 | Construction of Library Room Education — SRI MUKTSAR SAHIB(DEPUTY COMMISSIONER SRI MUKTSAR SAHIB_IDA) - ₹500,000 against a ₹232,826 median for Education works in SRI MUKTSAR SAHIB (115% above, 18 peer works)
- 646 days beyond expected completion
| SRI MUKTSAR SAHIB | ₹5.00 L | MEDIUM 52 | |
| 11 | Construction of Interlock tiles in Govt. Palace Roads & Paving — SRI MUKTSAR SAHIB(DEPUTY COMMISSIONER SRI MUKTSAR SAHIB_IDA) - ₹1,200,000 against a ₹600,000 median for Roads & Paving works in SRI MUKTSAR SAHIB (100% above, 31 peer works)
- 661 days beyond expected completion
| SRI MUKTSAR SAHIB | ₹12.00 L | MEDIUM 52 | |
| 12 | Estimate for Repair of existing Structure at water supply sc Water — SRI MUKTSAR SAHIB(DEPUTY COMMISSIONER SRI MUKTSAR SAHIB_IDA) - ₹635,000 against a ₹243,000 median for Water works in SRI MUKTSAR SAHIB (161% above, 101 peer works)
- 727 days beyond expected completion
| SRI MUKTSAR SAHIB | ₹6.35 L | MEDIUM 52 | |
| 13 | Construction of Interlock tiles & Shed in Cremation Ground Community Buildings — SRI MUKTSAR SAHIB(DEPUTY COMMISSIONER SRI MUKTSAR SAHIB_IDA) - Completed work has no photographic documentation on record
- ₹700,000 against a ₹320,000 median for Community Buildings works in SRI MUKTSAR SAHIB (119% above, 22 peer works)
Read more (1 more)Show less- 100% similarity with another nearby work
| SRI MUKTSAR SAHIB | ₹7.00 L | MEDIUM 52
cost 25duplication 20compliance 5 | |
| 14 | Construction of Interlock Tiles & Shed in Cremation Ground Community Buildings — SRI MUKTSAR SAHIB(DEPUTY COMMISSIONER SRI MUKTSAR SAHIB_IDA) - Completed work has no photographic documentation on record
- ₹1,000,000 against a ₹320,000 median for Community Buildings works in SRI MUKTSAR SAHIB (212% above, 22 peer works)
Read more (1 more)Show less- 100% similarity with another nearby work
| SRI MUKTSAR SAHIB | ₹10.00 L | MEDIUM 52
cost 25duplication 20compliance 5 | |
| 15 | Construction of Shed in Panchayat Ghar Community Buildings — SRI MUKTSAR SAHIB(DEPUTY COMMISSIONER SRI MUKTSAR SAHIB_IDA) - Completed work has no photographic documentation on record
- ₹683,906 against a ₹320,000 median for Community Buildings works in SRI MUKTSAR SAHIB (114% above, 22 peer works)
Read more (1 more)Show less- 100% similarity with another nearby work
| SRI MUKTSAR SAHIB | ₹6.84 L | MEDIUM 52
cost 25duplication 20compliance 5 | |
| 16 | Construction of Public Shed in Ward no.9 Bhikhi Community Buildings — MANSA(DEPUTY COMMISSIONER MANSA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 784 days beyond expected completion
Read more (1 more)Show less- 97% similarity with another nearby work
| MANSA | ₹2.00 L | MEDIUM 51
delay 25cost 13duplication 11 | |
| 17 | Construction of Stadium Sports — BATHINDA(DEPUTY COMMISSIONER BHATINDA_IDA) - ₹699,800 against a ₹264,023 median for Sports works in BATHINDA (165% above, 36 peer works)
- 100% similarity with another nearby work
| BATHINDA | ₹7.00 L | MEDIUM 50
cost 25duplication 20agency 5 | |
| 18 | Mobile Water Tank Water — BATHINDA(DEPUTY COMMISSIONER BHATINDA_IDA) - 135 days beyond expected completion
- 100% similarity with another nearby work
| BATHINDA | ₹1.50 L | MEDIUM 50
duplication 20delay 19cost 6 | |
| 19 | Mobile Water Tank Water — BATHINDA(DEPUTY COMMISSIONER BHATINDA_IDA) - 135 days beyond expected completion
- 100% similarity with another nearby work
| BATHINDA | ₹4.00 L | MEDIUM 49
duplication 20delay 19cost 6 | |
| 20 | Construction of Interlock Tile House from Kamal Singh to Nac Roads & Paving — MANSA(DEPUTY COMMISSIONER MANSA_IDA) - ₹1,000,000 against a ₹180,422 median for Roads & Paving works in MANSA (454% above, 65 peer works)
- 157 days beyond expected completion
| MANSA | ₹10.00 L | MEDIUM 49 | |
| 21 | Construction of Floor in Gen Dharamshala Community Buildings — MANSA(DEPUTY COMMISSIONER MANSA_IDA) - ₹437,000 against a ₹200,000 median for Community Buildings works in MANSA (118% above, 44 peer works)
- 157 days beyond expected completion
| MANSA | ₹4.37 L | MEDIUM 49 | |
| 22 | Construction of Ramdasia Sikh Dharamshala Religious & Cultural — MANSA(DEPUTY COMMISSIONER MANSA_IDA) - ₹500,000 against a ₹183,718 median for Religious & Cultural works in MANSA (172% above, 15 peer works)
- 157 days beyond expected completion
| MANSA | ₹5.00 L | MEDIUM 49 | |
| 23 | Construction of Outfall Drain From Darshan Singh to Teja Sin Drainage & Sanitation — BATHINDA(DEPUTY COMMISSIONER BHATINDA_IDA) - ₹500,000 against a ₹87,500 median for Drainage & Sanitation works in BATHINDA (471% above, 14 peer works)
- 135 days beyond expected completion
| BATHINDA | ₹5.00 L | MEDIUM 49 | |
| 24 | Street lights (Solar) Street Lighting — BATHINDA(DEPUTY COMMISSIONER BHATINDA_IDA) - 107 days beyond expected completion
- 100% similarity with another nearby work
| BATHINDA | ₹5.91 L | MEDIUM 48
duplication 20delay 15cost 8 | |
| 25 | Construction of Pipleline from Sua to Water Works Water — MANSA(DEPUTY COMMISSIONER MANSA_IDA) - ₹2,000,000 against a ₹99,987 median for Water works in MANSA (1900% above, 64 peer works)
- 147 days beyond expected completion
| MANSA | ₹20.00 L | MEDIUM 47 | |