| 1 | Commissioning of 20watt Semi Integrated Solar Lights, 30AH L Street Lighting — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,865,000 against a ₹165,000 median for Street Lighting works in KHORDHA (1030% above, 25 peer works)
- 869 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹18.65 L | HIGH 76
cost 25delay 25duplication 20 | |
| 2 | Commissioning of 20watt Semi Integrated Solar Lights, 30AH L Street Lighting — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,790,000 against a ₹165,000 median for Street Lighting works in KHORDHA (985% above, 25 peer works)
- 869 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹17.90 L | HIGH 76
cost 25delay 25duplication 20 | |
| 3 | Commissioning of 20watt Semi Integrated Solar Lights, 30AH L Street Lighting — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,352,000 against a ₹165,000 median for Street Lighting works in KHORDHA (719% above, 25 peer works)
- 869 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹13.52 L | HIGH 76
cost 25delay 25duplication 20 | |
| 4 | Commissioning of 20watt Semi Integrated Solar Lights, 30AH L Street Lighting — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,716,000 against a ₹165,000 median for Street Lighting works in KHORDHA (940% above, 25 peer works)
- 869 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹17.16 L | HIGH 76
cost 25delay 25duplication 20 | |
| 5 | Construction of Library Hall in Balipatna Block Education — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,000,000 against a ₹500,000 median for Education works in KHORDHA (100% above, 131 peer works)
- 152 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹10.00 L | MEDIUM 60
cost 25delay 21duplication 8 | |
| 6 | Construction of Library Hall in Balianta Block Education — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,000,000 against a ₹500,000 median for Education works in KHORDHA (100% above, 131 peer works)
- 152 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹10.00 L | MEDIUM 60
cost 25delay 21duplication 8 | |
| 7 | Bhubaneswar Block, Ward No. 61, Installation of Drinking Wat Water — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 823 days beyond expected completion
Read more (2 more)Show less- 98% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹1.00 L | MEDIUM 58
delay 25cost 14duplication 12 | |
| 8 | Bhubaneswar Block, Ward No. 57, Installation of Drinking Wat Water — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 823 days beyond expected completion
Read more (2 more)Show less- 98% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹1.00 L | MEDIUM 58
delay 25cost 14duplication 12 | |
| 9 | Construction of changing room near Balunkeswar pond of Taman Water — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹200,000 against a ₹100,000 median for Water works in KHORDHA (100% above, 382 peer works)
- 823 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹2.00 L | MEDIUM 56 | |
| 10 | Block-Bhubaneswar, Installation of Cold Drinking Water at Sh Water — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - 263 days beyond expected completion
- 98% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹1.00 L | MEDIUM 54
delay 25duplication 14cost 9 | |
| 11 | Block-Bhubaneswar, Installation of Cold Drinking Water at Sh Water — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - 263 days beyond expected completion
- 98% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹1.00 L | MEDIUM 54
delay 25duplication 14cost 9 | |
| 12 | Ward No. 13 of Khordha, Construction of Cultural Centre at W Religious & Cultural — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 824 days beyond expected completion
Read more (2 more)Show less- 97% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹2.00 L | MEDIUM 54
delay 25cost 13duplication 9 | |
| 13 | Construction of Library Hall in Tangi Block Education — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,000,000 against a ₹500,000 median for Education works in KHORDHA (100% above, 131 peer works)
- 152 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹10.00 L | MEDIUM 52 | |
| 14 | Construction of Library Hall in Khordha Block Education — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,000,000 against a ₹500,000 median for Education works in KHORDHA (100% above, 131 peer works)
- 152 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹10.00 L | MEDIUM 52 | |
| 15 | Construction of Library Hall in Bhubaneswar Block Education — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,000,000 against a ₹500,000 median for Education works in KHORDHA (100% above, 131 peer works)
- 152 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹10.00 L | MEDIUM 52 | |
| 16 | Construction of Library Hall in Jatni Block Education — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,000,000 against a ₹500,000 median for Education works in KHORDHA (100% above, 131 peer works)
- 152 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹10.00 L | MEDIUM 52 | |
| 17 | Construction Reading Room in Balianta Block Community Buildings — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in KHORDHA (100% above, 144 peer works)
- 120 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹10.00 L | MEDIUM 52 | |
| 18 | Construction Reading Room in Balipatna Block Community Buildings — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in KHORDHA (100% above, 144 peer works)
- 120 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹10.00 L | MEDIUM 52 | |
| 19 | Ward No. 62 of Bhubaneswar Block, Cold Drinking Water Machin Water — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 869 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹1.00 L | MEDIUM 51 | |
| 20 | Ward No. 62 of Bhubaneswar Block, Cold Drinking Water Machin Water — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 869 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹1.00 L | MEDIUM 51 | |
| 21 | Bhubaneswar Block, Ward No. 38, Installation of Drinking Wat Water — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 823 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹1.00 L | MEDIUM 50 | |
| 22 | Construction of Vending Pindis for Vegetable Market (Part-3 Roads & Paving — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,000,000 against a ₹400,000 median for Roads & Paving works in KHORDHA (150% above, 165 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹10.00 L | MEDIUM 50
cost 25duplication 18agency 6 | |
| 23 | Construction of Vending Pindis for Vegetable Market (Part-3 Roads & Paving — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,000,000 against a ₹400,000 median for Roads & Paving works in KHORDHA (150% above, 165 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹10.00 L | MEDIUM 50
cost 25duplication 18agency 6 | |
| 24 | Block-Khordha, Installation of Cold Drinking Water at Gethes Water — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - 263 days beyond expected completion
- 96% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹1.00 L | MEDIUM 48
delay 25cost 9duplication 8 | |
| 25 | Block-Khordha, Installation of Cold Drinking Water at Balunk Water — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - 263 days beyond expected completion
- 96% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹1.00 L | MEDIUM 48
delay 25cost 9duplication 8 | |