| 1 | Construction of public libraries and reading rooms At City S Community Buildings — PUNE(DISTRICT COLLECTOR PUNE_IDA) - ₹6,000,000 against a ₹1,000,000 median for Community Buildings works in PUNE (500% above, 255 peer works)
- 596 days beyond expected completion
| PUNE | ₹60.00 L | MEDIUM 55 | |
| 2 | installation of High Mast Lighting at 4 different public pla Street Lighting — PUNE(DISTRICT COLLECTOR PUNE_IDA) - ₹1,000,000 against a ₹500,000 median for Street Lighting works in PUNE (100% above, 57 peer works)
- 331 days beyond expected completion
| PUNE | ₹10.00 L | MEDIUM 55 | |
| 3 | Installation of Smart Solar Bus Stop featuring solar power, Street Lighting — PUNE(DISTRICT COLLECTOR PUNE_IDA) - ₹1,000,000 against a ₹500,000 median for Street Lighting works in PUNE (100% above, 57 peer works)
- 168 days beyond expected completion
| PUNE | ₹10.00 L | MEDIUM 53 | |
| 4 | Installation of Smart Solar Bus Stop featuring solar power, Street Lighting — PUNE(DISTRICT COLLECTOR PUNE_IDA) - ₹1,000,000 against a ₹500,000 median for Street Lighting works in PUNE (100% above, 57 peer works)
- 168 days beyond expected completion
| PUNE | ₹10.00 L | MEDIUM 53 | |
| 5 | Installation of Smart Solar Bus Stop featuring solar power, Street Lighting — PUNE(DISTRICT COLLECTOR PUNE_IDA) - ₹1,000,000 against a ₹500,000 median for Street Lighting works in PUNE (100% above, 57 peer works)
- 168 days beyond expected completion
| PUNE | ₹10.00 L | MEDIUM 53 | |
| 6 | Installation of Smart Solar Bus Stop featuring solar power, Street Lighting — PUNE(DISTRICT COLLECTOR PUNE_IDA) - ₹1,000,000 against a ₹500,000 median for Street Lighting works in PUNE (100% above, 57 peer works)
- 168 days beyond expected completion
| PUNE | ₹10.00 L | MEDIUM 53 | |
| 7 | Installation of Smart Solar Bus Stop featuring solar power, Street Lighting — PUNE(DISTRICT COLLECTOR PUNE_IDA) - ₹1,000,000 against a ₹500,000 median for Street Lighting works in PUNE (100% above, 57 peer works)
- 168 days beyond expected completion
| PUNE | ₹10.00 L | MEDIUM 53 | |
| 8 | Installation of Smart Solar Bus Stop featuring solar power, Street Lighting — PUNE(DISTRICT COLLECTOR PUNE_IDA) - ₹1,000,000 against a ₹500,000 median for Street Lighting works in PUNE (100% above, 57 peer works)
- 168 days beyond expected completion
| PUNE | ₹10.00 L | MEDIUM 53 | |
| 9 | Installation of Smart Solar Bus Stop featuring solar power, Street Lighting — PUNE(DISTRICT COLLECTOR PUNE_IDA) - ₹1,000,000 against a ₹500,000 median for Street Lighting works in PUNE (100% above, 57 peer works)
- 168 days beyond expected completion
| PUNE | ₹10.00 L | MEDIUM 53 | |
| 10 | Installation of Smart Solar Bus Stop featuring solar power, Street Lighting — PUNE(DISTRICT COLLECTOR PUNE_IDA) - ₹1,000,000 against a ₹500,000 median for Street Lighting works in PUNE (100% above, 57 peer works)
- 168 days beyond expected completion
| PUNE | ₹10.00 L | MEDIUM 53 | |
| 11 | Crematoriums or structures on burial/ cremation ground for p Religious & Cultural — PUNE(DISTRICT COLLECTOR PUNE_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 645 days beyond expected completion
| PUNE | ₹10.00 L | MEDIUM 50
delay 25cost 13duplication 7 | |
| 12 | Crematoriums or structures on burial/ cremation ground for p Religious & Cultural — PUNE(DISTRICT COLLECTOR PUNE_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 596 days beyond expected completion
| PUNE | ₹10.00 L | MEDIUM 49
delay 25cost 12duplication 7 | |
| 13 | Construction of Social Hall in Dalit Settlement at Gram Panc Community Buildings — PUNE(DISTRICT COLLECTOR PUNE_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 946 days beyond expected completion
| PUNE | ₹10.00 L | MEDIUM 47 | |
| 14 | Providing electric bicycles to 23 differently abled persons Equipment & Vehicles — PUNE(DISTRICT COLLECTOR PUNE_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 839 days beyond expected completion
| PUNE | ₹9.89 L | MEDIUM 46 | |
| 15 | Installation of Smart Solar Hut (Gazebo) with solar power sy Sports — PUNE(DISTRICT COLLECTOR PUNE_IDA) - 168 days beyond expected completion
- 97% similarity with another nearby work
| PUNE | ₹10.00 L | MEDIUM 46
delay 23cost 9duplication 9 | |
| 16 | Installation of Smart Solar Hut (Gazebo) with solar power sy Sports — PUNE(DISTRICT COLLECTOR PUNE_IDA) - 168 days beyond expected completion
- 97% similarity with another nearby work
| PUNE | ₹10.00 L | MEDIUM 46
delay 23cost 9duplication 9 | |
| 17 | Construction of Patra Social Hall at Mauje Gram Panchayat Ni Community Buildings — PUNE(DISTRICT COLLECTOR PUNE_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 946 days beyond expected completion
| PUNE | ₹6.00 L | MEDIUM 46 | |
| 18 | Installation of RO water plant of 500 L. capacity at Ozar Di Water — PUNE(DISTRICT COLLECTOR PUNE_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 912 days beyond expected completion
| PUNE | ₹5.00 L | MEDIUM 45 | |
| 19 | Bus stop at Village Panchayat Nhawara Main Chowk in Shirur T Community Buildings — PUNE(DISTRICT COLLECTOR PUNE_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 912 days beyond expected completion
| PUNE | ₹5.00 L | MEDIUM 45 | |
| 20 | Bus stop at Pabal Phata in Shirur town of Shirur Haveli talu Community Buildings — PUNE(DISTRICT COLLECTOR PUNE_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 912 days beyond expected completion
| PUNE | ₹5.00 L | MEDIUM 45 | |
| 21 | Bus stop at Chowk at Kasari Phata on Pune-Nagar Road in Shir Roads & Paving — PUNE(DISTRICT COLLECTOR PUNE_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 912 days beyond expected completion
| PUNE | ₹5.00 L | MEDIUM 45 | |
| 22 | Construction of Social Hall at Gram Panchayat Pimparkhed in Community Buildings — PUNE(DISTRICT COLLECTOR PUNE_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 946 days beyond expected completion
| PUNE | ₹5.00 L | MEDIUM 45 | |
| 23 | Installation of formaldehyde scrubber with chemisorption and Health — MUMBAI(DISTRICT COLLECTOR MUMBAI CITY_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 377 days beyond expected completion
| MUMBAI | ₹15.00 L | MEDIUM 44 | |
| 24 | Gram Panchayat Bhiwade Bu. Construction of a social hall in Community Buildings — PUNE(DISTRICT COLLECTOR PUNE_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 696 days beyond expected completion
| PUNE | ₹9.99 L | MEDIUM 44 | |
| 25 | Construction of assembly hall at the foot of Bhamchandra hil Community Buildings — PUNE(DISTRICT COLLECTOR PUNE_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 696 days beyond expected completion
| PUNE | ₹10.00 L | MEDIUM 44 | |