| 1 | 1. GRAM MULHETA MEIN BRIJPAL KE MAKAN SE KABRISTAN KI TARAF Roads & Paving — SAMBHAL(DISTRICT MAGISTRAE BHIMNAGAR SAMBHAL_IDA) - ₹2,488,000 against a ₹1,141,000 median for Roads & Paving works in SAMBHAL (118% above, 71 peer works)
- 370 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SAMBHAL | ₹24.88 L | HIGH 74
cost 25delay 25duplication 20 | |
| 2 | Construction of Class room
Sompal Singh Memorial Public Scho Education — SAMBHAL(DISTRICT MAGISTRAE BHIMNAGAR SAMBHAL_IDA) - ₹1,000,000 against a ₹499,000 median for Education works in SAMBHAL (100% above, 15 peer works)
- 820 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SAMBHAL | ₹10.00 L | HIGH 74
cost 25delay 25duplication 20 | |
| 3 | Construction of Class room and Hall
Sainik Veer Abdul Hamid Education — SAMBHAL(DISTRICT MAGISTRAE BHIMNAGAR SAMBHAL_IDA) - ₹1,000,000 against a ₹499,000 median for Education works in SAMBHAL (100% above, 15 peer works)
- 820 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SAMBHAL | ₹10.00 L | HIGH 74
cost 25delay 25duplication 20 | |
| 4 | PRABHUNATH SINGH KRISHNA UCHCHATR MADHYAMIK VIDYALAY ARAZI Education — AZAMGARH(DISTRICT MAGISTRATE AZAMGARH_IDA) - ₹1,000,000 against a ₹516,000 median for Education works in AZAMGARH (94% above, 63 peer works)
- 366 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| AZAMGARH | ₹10.00 L | HIGH 74
delay 25cost 23duplication 20 | |
| 5 | PRABHUNATH SINGH KRISHNA UCHCHATR MADHYAMIK VIDYALAY ARAZI Education — AZAMGARH(DISTRICT MAGISTRATE AZAMGARH_IDA) - ₹1,000,000 against a ₹516,000 median for Education works in AZAMGARH (94% above, 63 peer works)
- 366 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| AZAMGARH | ₹10.00 L | HIGH 74
delay 25cost 23duplication 20 | |
| 6 | 1. GRAM MULHETA MEIN BRIJPAL KE MAKAN SE KABRISTAN KI TARAF Roads & Paving — SAMBHAL(DISTRICT MAGISTRAE BHIMNAGAR SAMBHAL_IDA) - ₹2,488,000 against a ₹1,141,000 median for Roads & Paving works in SAMBHAL (118% above, 71 peer works)
- 370 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SAMBHAL | ₹24.88 L | HIGH 73
cost 25delay 25duplication 20 | |
| 7 | Construction of Class room
Sompal Singh Memorial Public Scho Education — SAMBHAL(DISTRICT MAGISTRAE BHIMNAGAR SAMBHAL_IDA) - ₹1,000,000 against a ₹499,000 median for Education works in SAMBHAL (100% above, 15 peer works)
- 820 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SAMBHAL | ₹10.00 L | HIGH 73
cost 25delay 25duplication 20 | |
| 8 | Construction of Class room and Hall
Sainik Veer Abdul Hamid Education — SAMBHAL(DISTRICT MAGISTRAE BHIMNAGAR SAMBHAL_IDA) - ₹1,000,000 against a ₹499,000 median for Education works in SAMBHAL (100% above, 15 peer works)
- 820 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SAMBHAL | ₹10.00 L | HIGH 73
cost 25delay 25duplication 20 | |
| 9 | INTERLOCKING ROAD FROM GHARI DAWAR ROAD TO NANGLA SALIM FARM Roads & Paving — FIROZABAD(DISTRICT MAGISTRATE FIROZABAD_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 763 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| FIROZABAD | ₹28.28 L | MEDIUM 69
delay 25duplication 20cost 20 | |
| 10 | INTERLOCKING ROAD FROM GHARI DAWAR ROAD TO NANGLA SALIM FARM Roads & Paving — FIROZABAD(DISTRICT MAGISTRATE FIROZABAD_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 763 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| FIROZABAD | ₹28.28 L | MEDIUM 69
delay 25duplication 20cost 20 | |
| 11 | CONSTRUCTION OF INTERLOCKING ROAD FROM MATSAINA DABAR RAOD T Roads & Paving — FIROZABAD(DISTRICT MAGISTRATE FIROZABAD_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 763 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| FIROZABAD | ₹23.54 L | MEDIUM 68
delay 25duplication 20cost 19 | |
| 12 | CONSTRUCTION OF INTERLOCKING ROAD FROM MATSAINA DABAR RAOD T Roads & Paving — FIROZABAD(DISTRICT MAGISTRATE FIROZABAD_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 763 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| FIROZABAD | ₹23.54 L | MEDIUM 68
delay 25duplication 20cost 19 | |
| 13 | Construction of interlocking tiles to Eidgah via Qabristan, Roads & Paving — Siddharthnagar(DISTRICT MAGISTRATE SIDDHARTH NAGAR_IDA) - ₹1,500,000 against a ₹875,000 median for Roads & Paving works in SIDDHARTHNAGAR (71% above, 136 peer works)
- 749 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SIDDHARTHNAGAR | ₹15.00 L | MEDIUM 67
delay 25duplication 20cost 18 | |
| 14 | Construction of interlocking tiles to Eidgah via Qabristan, Roads & Paving — Siddharthnagar(DISTRICT MAGISTRATE SIDDHARTH NAGAR_IDA) - ₹1,500,000 against a ₹875,000 median for Roads & Paving works in SIDDHARTHNAGAR (71% above, 136 peer works)
- 749 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SIDDHARTHNAGAR | ₹15.00 L | MEDIUM 67
delay 25duplication 20cost 18 | |
| 15 | 1. GRAM MIRZAPUR NASRULLAHPUR MEIN GHASI SHEIKH KE MAKAN SE Roads & Paving — SAMBHAL(DISTRICT MAGISTRAE BHIMNAGAR SAMBHAL_IDA) - ₹1,960,000 against a ₹1,141,000 median for Roads & Paving works in SAMBHAL (72% above, 71 peer works)
- 370 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SAMBHAL | ₹19.60 L | MEDIUM 67
delay 25duplication 20cost 18 | |
| 16 | INERLOCKING ROAD FROM MUSLIM BASTI TO SATAAR ALI HOUSE TOWAR Roads & Paving — FIROZABAD(DISTRICT MAGISTRATE FIROZABAD_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 763 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| FIROZABAD | ₹13.59 L | MEDIUM 66
delay 25duplication 20cost 17 | |
| 17 | INERLOCKING ROAD FROM MUSLIM BASTI TO SATAAR ALI HOUSE TOWAR Roads & Paving — FIROZABAD(DISTRICT MAGISTRATE FIROZABAD_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 763 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| FIROZABAD | ₹13.59 L | MEDIUM 66
delay 25duplication 20cost 17 | |
| 18 | 1. GRAM MIRZAPUR NASRULLAHPUR MEIN GHASI SHEIKH KE MAKAN SE Roads & Paving — SAMBHAL(DISTRICT MAGISTRAE BHIMNAGAR SAMBHAL_IDA) - ₹1,960,000 against a ₹1,141,000 median for Roads & Paving works in SAMBHAL (72% above, 71 peer works)
- 370 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SAMBHAL | ₹19.60 L | MEDIUM 66
delay 25duplication 20cost 18 | |
| 19 | Construction interlocking tiles from the house Shri Puran to Roads & Paving — SAMBHAL(DISTRICT MAGISTRAE BHIMNAGAR SAMBHAL_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 747 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SAMBHAL | ₹13.00 L | MEDIUM 66
delay 25duplication 20cost 17 | |
| 20 | Construction of interlocking tiles from the house of Shri Ma Roads & Paving — SAMBHAL(DISTRICT MAGISTRAE BHIMNAGAR SAMBHAL_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 747 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SAMBHAL | ₹10.00 L | MEDIUM 65
delay 25duplication 20cost 15 | |
| 21 | GRAM DUDHAPUR MEIN AJAY PAL KE MAKAN SE MANDIR KI TARAF CC T Roads & Paving — SAMBHAL(DISTRICT MAGISTRAE BHIMNAGAR SAMBHAL_IDA) - ₹1,806,000 against a ₹1,141,000 median for Roads & Paving works in SAMBHAL (58% above, 71 peer works)
- 370 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SAMBHAL | ₹18.06 L | MEDIUM 65
delay 25duplication 20cost 15 | |
| 22 | GRAM FAZALPUR NIKAT HINDOLI MEIN AMBEDKAR PARK KI BOUNDRYWAL Sports — SAMBHAL(DISTRICT MAGISTRAE BHIMNAGAR SAMBHAL_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 370 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SAMBHAL | ₹17.20 L | MEDIUM 65
delay 25duplication 20cost 15 | |
| 23 | Construction interlocking tiles from the house Shri Puran to Roads & Paving — SAMBHAL(DISTRICT MAGISTRAE BHIMNAGAR SAMBHAL_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 747 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SAMBHAL | ₹13.00 L | MEDIUM 65
delay 25duplication 20cost 17 | |
| 24 | GRAM AKBARPUR MEIN TALIB KE MAKAN SE AFTAB KE MAKAN KI TARAF Roads & Paving — SAMBHAL(DISTRICT MAGISTRAE BHIMNAGAR SAMBHAL_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 370 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SAMBHAL | ₹15.93 L | MEDIUM 64
delay 25duplication 20cost 15 | |
| 25 | 1. GRAM ENCHOLI MEIN RAUF ALI KE MAKAN SE TALAB KI TARAF CC Roads & Paving — SAMBHAL(DISTRICT MAGISTRAE BHIMNAGAR SAMBHAL_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 370 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SAMBHAL | ₹15.65 L | MEDIUM 64
delay 25duplication 20cost 14 | |