| 1 | Construction of Community centre near Sri kaginele Mahasamst Roads & Paving — RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) - ₹1,000,000 against a ₹498,005 median for Roads & Paving works in RAICHUR (101% above, 75 peer works)
- 545 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 68% delay rate across its projects
| RAICHUR | ₹10.00 L | MEDIUM 60 | |
| 2 | Construction of Samudaya bhavana near Jilla kanaka bhavana Roads & Paving — RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) - ₹1,500,000 against a ₹498,005 median for Roads & Paving works in RAICHUR (201% above, 75 peer works)
- 545 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 68% delay rate across its projects
| RAICHUR | ₹15.00 L | MEDIUM 60 | |
| 3 | 2)Continuatin work of Samudaya bhavan beside Nageshwara temp Community Buildings — RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) - ₹1,000,000 against a ₹400,000 median for Community Buildings works in RAICHUR (150% above, 78 peer works)
- 575 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 68% delay rate across its projects
| RAICHUR | ₹10.00 L | MEDIUM 60 | |
| 4 | 19)Installation of Highmask light at B.Ganekal village in D Street Lighting — RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 749 days beyond expected completion
Read more (2 more)Show less- 97% similarity with another nearby work
- Implementing agency has a 68% delay rate across its projects
| RAICHUR | ₹5.00 L | MEDIUM 58
delay 25cost 12duplication 11 | |
| 5 | 36) Installation of Highmask light at Mustoor village in De Street Lighting — RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 749 days beyond expected completion
Read more (2 more)Show less- 97% similarity with another nearby work
- Implementing agency has a 68% delay rate across its projects
| RAICHUR | ₹5.00 L | MEDIUM 58
delay 25cost 12duplication 11 | |
| 6 | 30)Installation of Highmask light at Karadigudda village in Street Lighting — RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 749 days beyond expected completion
Read more (2 more)Show less- 97% similarity with another nearby work
- Implementing agency has a 68% delay rate across its projects
| RAICHUR | ₹5.00 L | MEDIUM 57 | |
| 7 | 16)Installation of Highmask light at Alkod village in Devadu Street Lighting — RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) - 659 days beyond expected completion
- 97% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 68% delay rate across its projects
| RAICHUR | ₹5.00 L | MEDIUM 55
delay 25duplication 11agency 10 | |
| 8 | 21)Installation of Highmask light at Chinhodi village in De Street Lighting — RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 749 days beyond expected completion
Read more (2 more)Show less- 96% similarity with another nearby work
- Implementing agency has a 68% delay rate across its projects
| RAICHUR | ₹5.00 L | MEDIUM 55 | |
| 9 | 23)Installation of Highmask light near Chennamma Katte of G Street Lighting — RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 749 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 68% delay rate across its projects
| RAICHUR | ₹5.00 L | MEDIUM 55 | |
| 10 | 32)Installation of Highmask light at Kyadigera village in D Street Lighting — RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 749 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 68% delay rate across its projects
| RAICHUR | ₹5.00 L | MEDIUM 54 | |
| 11 | 33)Installation of Highmask light at Maladkal village in De Street Lighting — RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 749 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 68% delay rate across its projects
| RAICHUR | ₹5.00 L | MEDIUM 54 | |
| 12 | 26) Installation of Highmask light near Valimiki Circle of H Street Lighting — RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) - 659 days beyond expected completion
- Implementing agency has a 68% delay rate across its projects
| RAICHUR | ₹5.00 L | MEDIUM 52 | |
| 13 | 35)Installation of Highmask light near Valmiki circle at Nag Street Lighting — RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) - 659 days beyond expected completion
- Implementing agency has a 68% delay rate across its projects
| RAICHUR | ₹5.00 L | MEDIUM 52 | |
| 14 | 20)Installation of Highmask light at Mallapur village in Dev Street Lighting — RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) - 659 days beyond expected completion
- Implementing agency has a 68% delay rate across its projects
| RAICHUR | ₹5.00 L | MEDIUM 51 | |
| 15 | 31)Installation of Highmask light at Kothadoddi village in D Street Lighting — RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) - 659 days beyond expected completion
- Implementing agency has a 68% delay rate across its projects
| RAICHUR | ₹5.00 L | MEDIUM 51 | |
| 16 | 38) Installation of Highmask light at Shavantgera village i Street Lighting — RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 749 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 68% delay rate across its projects
| RAICHUR | ₹5.00 L | MEDIUM 50 | |
| 17 | Construction of Metal road from Mallikarkjun land to Gopala Roads & Paving — RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) - 560 days beyond expected completion
- Implementing agency has a 68% delay rate across its projects
| RAICHUR | ₹50,000 | MEDIUM 50 | |
| 18 | Construction of Metal road from Gopalappa land to Khajappa l Roads & Paving — RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) - 560 days beyond expected completion
- Implementing agency has a 68% delay rate across its projects
| RAICHUR | ₹50,000 | MEDIUM 50 | |
| 19 | 17) Installation of Highmask light near Amarapura Cross at A Street Lighting — RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 749 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 68% delay rate across its projects
| RAICHUR | ₹5.00 L | MEDIUM 48 | |
| 20 | 5)Installation of Highmask light at Julagudda village in Lin Street Lighting — RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) - 658 days beyond expected completion
- Implementing agency has a 68% delay rate across its projects
| RAICHUR | ₹5.00 L | MEDIUM 48 | |
| 21 | 14)Installation of Highmask light at Narkaldinni village in Street Lighting — RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) - 659 days beyond expected completion
- Implementing agency has a 68% delay rate across its projects
| RAICHUR | ₹5.00 L | MEDIUM 48 | |
| 22 | 12) Installation of Highmask light near Amareshwara temple a Religious & Cultural — RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 749 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 68% delay rate across its projects
| RAICHUR | ₹5.00 L | MEDIUM 48 | |
| 23 | 9) Installation of Highmask light near sangameshwar temple a Religious & Cultural — RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 749 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 68% delay rate across its projects
| RAICHUR | ₹5.00 L | MEDIUM 48 | |
| 24 | 4)Installation of Highmask light at Gejjalagatta village in Street Lighting — RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) - 658 days beyond expected completion
- Implementing agency has a 68% delay rate across its projects
| RAICHUR | ₹5.00 L | MEDIUM 47 | |
| 25 | 40) Installation of Highmask light at Madagiri village in S Street Lighting — RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 749 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 68% delay rate across its projects
| RAICHUR | ₹5.00 L | MEDIUM 47 | |