102 works across 1 implementing agency, recommended by 5 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) | 102 | 8 | ₹7.17 Cr | 18 | 24.5 | CASHUTEC Nirmithi Kendra 32% of spend · 18 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| G Kumar Naik RAICHUR | 86 | ₹5.89 Cr | 6 |
| K Rajashekar Basavaraj Hitnal KOPPAL | 8 | ₹40.50 L | 6 |
| Syed Naseer Hussain Sitting Rajya Sabha | 6 | ₹30.00 L | 4 |
| Nirmala Sitharaman Sitting Rajya Sabha | 1 | ₹47.86 L | 1 |
| Narayanasa K. Bhandage Sitting Rajya Sabha | 1 | ₹10.00 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 34 | ₹1.95 Cr | 3 |
| Street Lighting | 24 | ₹1.20 Cr | 0 |
| Community Buildings | 20 | ₹2.02 Cr | 5 |
| Education | 9 | ₹69.00 L | 4 |
| Equipment & Vehicles | 4 | ₹49.00 L | 1 |
| Water | 3 | ₹14.99 L | 0 |
| Sports | 3 | ₹17.50 L | 1 |
| Drainage & Sanitation | 2 | ₹30.00 L | 2 |
| Religious & Cultural | 2 | ₹15.00 L | 1 |
| Other | 1 | ₹5.00 L | 1 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
Round figures are normal and similar works legitimately cost the same. One figure covering nearly every work is what this looks for, and it means the costing is worth seeing, not that it is wrong.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction CC Road 331 days beyond expected completion | RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) | Recommended | ₹5.00 L | 331 d | +0% | 63.7 | MEDIUM |
| Construction of CC Drain and CD 331 days beyond expected completion | RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) | Recommended | ₹5.00 L | 331 d | 0% | 63.7 | MEDIUM |
| Construction of CC Road 331 days beyond expected completion | RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) | Recommended | ₹5.00 L | 331 d | +0% | 63.7 | MEDIUM |
| Construction of continued milaf shadi mahal community hall i ₹1,000,000 against a ₹400,000 median for Community Buildings works in RAICHUR (150% above, 78 peer works) | RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) | Recommended | ₹10.00 L | 178 d | +150% | 59.9 | MEDIUM |
| Construction of Road from Suresh Patil's Farm to Hampayyaswa ₹1,000,000 against a ₹498,005 median for Roads & Paving works in RAICHUR (101% above, 75 peer works) | RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) | Recommended | ₹10.00 L | — | +101% | 55.2 | MEDIUM |
| Construction of Community Hall at Hussain Nagar Camp Kallur ₹1,000,000 against a ₹400,000 median for Community Buildings works in RAICHUR (150% above, 78 peer works) | RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) | Recommended | ₹10.00 L | — | +150% | 55.2 | MEDIUM |
| Setting up of Farmers training center and common facility ce ₹4,786,000 against a ₹400,000 median for Community Buildings works in RAICHUR (1096% above, 78 peer works) | RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) | Completed | ₹47.86 L | — | +1097% | 55.2 | MEDIUM |
| Construction of samskruthika bhava or agas in Raghunathanaha ₹1,000,000 against a ₹500,000 median for Religious & Cultural works in RAICHUR (100% above, 14 peer works) | RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) | Recommended | ₹10.00 L | 132 d | +100% | 53.5 | MEDIUM |
| Construction of one additional rooms to Sri Maharshi Valmik ₹1,000,000 against a ₹500,000 median for Education works in RAICHUR (100% above, 15 peer works) | RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) | Recommended | ₹10.00 L | 132 d | +100% | 53.5 | MEDIUM |
| Renovation work Furniture,CC camera fittings to PWD building ₹1,000,000 against a ₹400,000 median for Equipment & Vehicles works in RAICHUR (150% above, 8 peer works) | RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) | Recommended | ₹10.00 L | 132 d | +150% | 53.5 | MEDIUM |
| Construction work of Sri Maharana prathapa education trust(R ₹1,000,000 against a ₹500,000 median for Education works in RAICHUR (100% above, 15 peer works) | RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) | Recommended | ₹10.00 L | 132 d | +100% | 53.5 | MEDIUM |
| Construction of HIghtech toilets at musthafa madarasa premis Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) | Recommended | ₹25.00 L | 132 d | 0% | 42.6 | MEDIUM |
| Construction of Continued community hall (Beeralingeshwar Sa 192 days beyond expected completion | RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) | Recommended | ₹4.00 L | 192 d | 0% | 42.0 | MEDIUM |
| Construction of class room of veerasangameshwar shivacharya 192 days beyond expected completion | RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) | Recommended | ₹4.00 L | 192 d | -20% | 42.0 | MEDIUM |
| Development of Garden work in Sangolli Rayanna Murthy premi 194 days beyond expected completion | RAICHUR(DEPUTY COMMISSIONER RAICHUR_IDA) | Recommended | ₹5.00 L | 194 d | 0% | 42.0 | MEDIUM |