| 1 | Lighting of public spaces Street Lighting — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - ₹3,657,000 against a ₹174,214 median for Street Lighting works in HARDOI (1999% above, 82 peer works)
- 164 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹36.57 L | HIGH 74
cost 25delay 23duplication 20 | |
| 2 | Lighting of public spaces Street Lighting — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - ₹696,856 against a ₹174,214 median for Street Lighting works in HARDOI (300% above, 82 peer works)
- 164 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹6.97 L | HIGH 74
cost 25delay 23duplication 20 | |
| 3 | Construction of Class Rooms Education — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - ₹950,000 against a ₹580,000 median for Education works in HARDOI (64% above, 14 peer works)
- 548 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹9.50 L | MEDIUM 67
delay 25duplication 20cost 16 | |
| 4 | Construction of class rooms Education — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - ₹950,000 against a ₹580,000 median for Education works in HARDOI (64% above, 14 peer works)
- 548 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹9.50 L | MEDIUM 67
delay 25duplication 20cost 16 | |
| 5 | ?? ?? ?? ?? ?? ? Other — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 760 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹6.00 L | MEDIUM 65
delay 25duplication 20cost 14 | |
| 6 | Interlocking and Naali work Roads & Paving — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - ₹1,554,600 against a ₹1,045,500 median for Roads & Paving works in HARDOI (49% above, 10 peer works)
- 292 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹15.55 L | MEDIUM 64
delay 25duplication 20cost 13 | |
| 7 | WS/MP792/2023-2024/9089-Construction of rooms and halls in s Education — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 760 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹6.00 L | MEDIUM 64
delay 25duplication 20cost 14 | |
| 8 | WS/MP792/2023-2024/9093-Construction of rooms and halls in s Education — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 760 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹6.00 L | MEDIUM 64
delay 25duplication 20cost 14 | |
| 9 | ?? ?? ?? ?? ?? ? Other — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 760 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹3.25 L | MEDIUM 63
delay 25duplication 20cost 12 | |
| 10 | ?? ?? ?? ?? ?? ? Other — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 760 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹3.25 L | MEDIUM 63
delay 25duplication 20cost 12 | |
| 11 | ?? ?? ?? ?? ? Other — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 760 days beyond expected completion
Read more (2 more)Show less- 97% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹10.01 L | MEDIUM 58
delay 25cost 16duplication 11 | |
| 12 | 60 watt street light Street Lighting — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - ₹927,180 against a ₹174,214 median for Street Lighting works in HARDOI (432% above, 82 peer works)
- 548 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹9.27 L | MEDIUM 56 | |
| 13 | 38 No High mast light Street Lighting — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - ₹8,757,826 against a ₹174,214 median for Street Lighting works in HARDOI (4927% above, 82 peer works)
- 548 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹87.58 L | MEDIUM 56 | |
| 14 | 2 No Street Light Street Lighting — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - ₹465,770 against a ₹174,214 median for Street Lighting works in HARDOI (167% above, 82 peer works)
- 548 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹4.66 L | MEDIUM 56 | |
| 15 | Solar Street Light Street Lighting — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - ₹5,597,655 against a ₹174,214 median for Street Lighting works in HARDOI (3113% above, 82 peer works)
- 567 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹55.98 L | MEDIUM 56 | |
| 16 | Street Light high Mast Street Lighting — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - ₹3,750,000 against a ₹174,214 median for Street Lighting works in HARDOI (2053% above, 82 peer works)
- 567 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹37.50 L | MEDIUM 56 | |
| 17 | 79 No Semi high mast light Street Lighting — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - ₹9,375,000 against a ₹174,214 median for Street Lighting works in HARDOI (5281% above, 82 peer works)
- 589 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹93.75 L | MEDIUM 56 | |
| 18 | 360 N0 Solar light Street Lighting — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - ₹6,163,710 against a ₹174,214 median for Street Lighting works in HARDOI (3438% above, 82 peer works)
- 589 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹61.64 L | MEDIUM 56 | |
| 19 | 242 No solar Light Street Lighting — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - ₹4,696,160 against a ₹174,214 median for Street Lighting works in HARDOI (2596% above, 82 peer works)
- 589 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹46.96 L | MEDIUM 56 | |
| 20 | 385 No Solar Light Street Lighting — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - ₹7,484,505 against a ₹174,214 median for Street Lighting works in HARDOI (4196% above, 82 peer works)
- 589 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹74.85 L | MEDIUM 56 | |
| 21 | 63 N0 Solar Light Street Lighting — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - ₹1,215,970 against a ₹174,214 median for Street Lighting works in HARDOI (598% above, 82 peer works)
- 589 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹12.16 L | MEDIUM 56 | |
| 22 | INTERLOCKING AND NALI Roads & Paving — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - ₹2,300,000 against a ₹1,045,500 median for Roads & Paving works in HARDOI (120% above, 10 peer works)
- 204 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹23.00 L | MEDIUM 56 | |
| 23 | 50 NO 200 WATT LIGHT Street Lighting — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - ₹8,594,232 against a ₹174,214 median for Street Lighting works in HARDOI (4833% above, 82 peer works)
- 204 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹85.94 L | MEDIUM 56 | |
| 24 | 12 NO 200 WATT LIGHT Street Lighting — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - ₹2,194,000 against a ₹174,214 median for Street Lighting works in HARDOI (1159% above, 82 peer works)
- 204 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹21.94 L | MEDIUM 56 | |
| 25 | 26 ?? 170-200 06 ?? ?? Other — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - ₹5,580,000 against a ₹2,480,022 median for Other works in HARDOI (125% above, 10 peer works)
- 385 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹55.80 L | MEDIUM 56 | |