Open this link on a larger screen to see the verification queue.
55 works across 1 implementing agency, recommended by 4 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) 2 high risk | 55 | 3 | ₹10.32 Cr | 18 | 36.2 | BALAJI ENTERPRISES 29% of spend · 24 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Baburam Nishad Sitting Rajya Sabha | 29 | ₹50.52 L | 0 |
| Jai Prakash HARDOI | 23 | ₹9.60 Cr | 16 |
| Laxmi Kant Bajpai Sitting Rajya Sabha | 2 | ₹11.32 L | 2 |
| Ashok Kumar Rawat MISRIKH | 1 | ₹9.50 L | 0 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Street Lighting | 39 | ₹6.36 Cr | 10 |
| Other | 5 | ₹2.86 Cr | 4 |
| Roads & Paving | 5 | ₹72.32 L | 2 |
| Education | 4 | ₹26.54 L | 2 |
| Community Buildings | 1 | ₹9.50 L | 0 |
| Equipment & Vehicles | 1 | ₹1.50 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
Round figures are normal and similar works legitimately cost the same. One figure covering nearly every work is what this looks for, and it means the costing is worth seeing, not that it is wrong.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Lighting of public spaces ₹3,657,000 against a ₹174,214 median for Street Lighting works in HARDOI (1999% above, 82 peer works) | HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) | Recommended | ₹36.57 L | 164 d | +1999% | 74.0 | HIGH |
| Lighting of public spaces ₹696,856 against a ₹174,214 median for Street Lighting works in HARDOI (300% above, 82 peer works) | HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) | Recommended | ₹6.97 L | 164 d | +300% | 74.0 | HIGH |
| Interlocking and Naali work ₹1,554,600 against a ₹1,045,500 median for Roads & Paving works in HARDOI (49% above, 10 peer works) | HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) | Recommended | ₹15.55 L | 292 d | +49% | 64.5 | MEDIUM |
| INTERLOCKING AND NALI ₹2,300,000 against a ₹1,045,500 median for Roads & Paving works in HARDOI (120% above, 10 peer works) | HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) | Recommended | ₹23.00 L | 204 d | +120% | 56.2 | MEDIUM |
| 50 NO 200 WATT LIGHT ₹8,594,232 against a ₹174,214 median for Street Lighting works in HARDOI (4833% above, 82 peer works) | HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) | Recommended | ₹85.94 L | 204 d | +4833% | 56.2 | MEDIUM |
| 12 NO 200 WATT LIGHT ₹2,194,000 against a ₹174,214 median for Street Lighting works in HARDOI (1159% above, 82 peer works) | HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) | Recommended | ₹21.94 L | 204 d | +1159% | 56.2 | MEDIUM |
| 26 ?? 170-200 06 ?? ?? ₹5,580,000 against a ₹2,480,022 median for Other works in HARDOI (125% above, 10 peer works) | HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) | Recommended | ₹55.80 L | 385 d | +125% | 56.2 | MEDIUM |
| 31 ?? 06 ?? 170-200 ?? ₹6,520,794 against a ₹2,480,022 median for Other works in HARDOI (163% above, 10 peer works) | HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) | Recommended | ₹65.21 L | 385 d | +163% | 56.2 | MEDIUM |
| Lighting of public spaces ₹6,968,560 against a ₹174,214 median for Street Lighting works in HARDOI (3900% above, 82 peer works) | HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) | Recommended | ₹69.69 L | 34 d | +3900% | 56.0 | MEDIUM |
| Lighting of public spaces ₹6,097,477 against a ₹174,214 median for Street Lighting works in HARDOI (3400% above, 82 peer works) | HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) | Recommended | ₹60.97 L | 34 d | +3400% | 56.0 | MEDIUM |
| Lighting of public spaces ₹9,581,750 against a ₹174,214 median for Street Lighting works in HARDOI (5400% above, 82 peer works) | HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) | Recommended | ₹95.82 L | 34 d | +5400% | 56.0 | MEDIUM |
| Lighting of public spaces ₹2,787,424 against a ₹174,214 median for Street Lighting works in HARDOI (1500% above, 82 peer works) | HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) | Recommended | ₹27.87 L | 34 d | +1500% | 56.0 | MEDIUM |
| Lighting of public spaces ₹8,710,700 against a ₹174,214 median for Street Lighting works in HARDOI (4900% above, 82 peer works) | HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) | Recommended | ₹87.11 L | 34 d | +4900% | 56.0 | MEDIUM |
| Lighting of public spaces ₹9,227,740 against a ₹174,214 median for Street Lighting works in HARDOI (5197% above, 82 peer works) | HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) | Completed | ₹92.28 L | — | +5197% | 51.2 | MEDIUM |
| 30 ?? 6?? 170 ?? 200 ₹4,022,832 against a ₹2,480,022 median for Other works in HARDOI (62% above, 10 peer works) | HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) | Recommended | ₹40.23 L | 365 d | +62% | 50.6 | MEDIUM |