| 1 | construction of library Education — LAKHIMPUR(DEPUTY COMMISSIONER LAKHIMPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 777 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| LAKHIMPUR | ₹1.25 L | MEDIUM 67
delay 25duplication 20cost 13 | |
| 2 | construction of library Education — LAKHIMPUR(DEPUTY COMMISSIONER LAKHIMPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 777 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| LAKHIMPUR | ₹1.25 L | MEDIUM 67
delay 25duplication 20cost 13 | |
| 3 | Const. of building at Cinatolia TE, Cinatoli, Lakhimpur dist Community Buildings — LAKHIMPUR(DEPUTY COMMISSIONER LAKHIMPUR_IDA) - ₹1,000,000 against a ₹300,000 median for Community Buildings works in LAKHIMPUR (233% above, 71 peer works)
- 591 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| LAKHIMPUR | ₹10.00 L | MEDIUM 59 | |
| 4 | Repair/Rennovation of Bahgora Deori Gaon Kundimama Gosani Sh Community Buildings — LAKHIMPUR(DEPUTY COMMISSIONER LAKHIMPUR_IDA) - ₹1,000,000 against a ₹300,000 median for Community Buildings works in LAKHIMPUR (233% above, 71 peer works)
- 677 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| LAKHIMPUR | ₹10.00 L | MEDIUM 59 | |
| 5 | Const. of Stage and Green Room at Ghilamara North Bank Colle Education — LAKHIMPUR(DEPUTY COMMISSIONER LAKHIMPUR_IDA) - ₹1,000,000 against a ₹500,000 median for Education works in LAKHIMPUR (100% above, 24 peer works)
- 729 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| LAKHIMPUR | ₹10.00 L | MEDIUM 59 | |
| 6 | community hall Community Buildings — LAKHIMPUR(DEPUTY COMMISSIONER LAKHIMPUR_IDA) - ₹600,000 against a ₹300,000 median for Community Buildings works in LAKHIMPUR (100% above, 71 peer works)
- 777 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| LAKHIMPUR | ₹6.00 L | MEDIUM 59 | |
| 7 | Infrastructure Development of North Lakhimpur Press Club, La Community Buildings — LAKHIMPUR(DEPUTY COMMISSIONER LAKHIMPUR_IDA) - ₹600,000 against a ₹300,000 median for Community Buildings works in LAKHIMPUR (100% above, 71 peer works)
- 181 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| LAKHIMPUR | ₹6.00 L | MEDIUM 59 | |
| 8 | Const. of builing at Panigaon Pragati Sangha under MPLADS, f Community Buildings — LAKHIMPUR(DEPUTY COMMISSIONER LAKHIMPUR_IDA) - ₹1,000,000 against a ₹300,000 median for Community Buildings works in LAKHIMPUR (233% above, 71 peer works)
- 254 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| LAKHIMPUR | ₹10.00 L | MEDIUM 59 | |
| 9 | Dirgha Anchalik Rangamancha Religious & Cultural — LAKHIMPUR(DEPUTY COMMISSIONER LAKHIMPUR_IDA) - ₹1,000,000 against a ₹500,000 median for Religious & Cultural works in LAKHIMPUR (100% above, 31 peer works)
- 335 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| LAKHIMPUR | ₹10.00 L | MEDIUM 59 | |
| 10 | Const. of Community Hall at Tanganapara Nepali Gaon near Har Community Buildings — DHEMAJI(DEPUTY COMMISSIONER DHEMAJI_IDA) - ₹600,000 against a ₹300,000 median for Community Buildings works in DHEMAJI (100% above, 87 peer works)
- 728 days beyond expected completion
| DHEMAJI | ₹6.00 L | MEDIUM 55 | |
| 11 | Construction of Community hall near Simen Anchalik Brahma Dh Community Buildings — DHEMAJI(DEPUTY COMMISSIONER DHEMAJI_IDA) - ₹1,000,000 against a ₹300,000 median for Community Buildings works in DHEMAJI (233% above, 87 peer works)
- 254 days beyond expected completion
| DHEMAJI | ₹10.00 L | MEDIUM 55 | |
| 12 | Const. of community hall of Puhor (CLF), Jonai LAC under MPL Community Buildings — DHEMAJI(DEPUTY COMMISSIONER DHEMAJI_IDA) - ₹1,000,000 against a ₹300,000 median for Community Buildings works in DHEMAJI (233% above, 87 peer works)
- 327 days beyond expected completion
| DHEMAJI | ₹10.00 L | MEDIUM 55 | |
| 13 | Const. of community hall of Doksiri (CLF), Jonai LAC under M Community Buildings — DHEMAJI(DEPUTY COMMISSIONER DHEMAJI_IDA) - ₹1,000,000 against a ₹300,000 median for Community Buildings works in DHEMAJI (233% above, 87 peer works)
- 327 days beyond expected completion
| DHEMAJI | ₹10.00 L | MEDIUM 55 | |
| 14 | Const. of office building of Jonai Bar Association, Jonai LA Community Buildings — DHEMAJI(DEPUTY COMMISSIONER DHEMAJI_IDA) - ₹1,000,000 against a ₹300,000 median for Community Buildings works in DHEMAJI (233% above, 87 peer works)
- 327 days beyond expected completion
| DHEMAJI | ₹10.00 L | MEDIUM 55 | |
| 15 | Construction of Community Hall near Simen Chapori Anchalik B Community Buildings — DHEMAJI(DEPUTY COMMISSIONER DHEMAJI_IDA) - ₹1,000,000 against a ₹300,000 median for Community Buildings works in DHEMAJI (233% above, 87 peer works)
- 164 days beyond expected completion
| DHEMAJI | ₹10.00 L | MEDIUM 52 | |
| 16 | Const. of Lechai Gaon Community Hall (near Namghar) under MP Community Buildings — LAKHIMPUR(DEPUTY COMMISSIONER LAKHIMPUR_IDA) - ₹500,000 against a ₹300,000 median for Community Buildings works in LAKHIMPUR (67% above, 71 peer works)
- 705 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| LAKHIMPUR | ₹5.00 L | MEDIUM 51 | |
| 17 | Const. of Nowboicha Baptist Sabha Office Building, Nowboicha Community Buildings — LAKHIMPUR(DEPUTY COMMISSIONER LAKHIMPUR_IDA) - ₹500,000 against a ₹300,000 median for Community Buildings works in LAKHIMPUR (67% above, 71 peer works)
- 718 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| LAKHIMPUR | ₹5.00 L | MEDIUM 51 | |
| 18 | Kaoimari Gorkha Kriisti Bhawan, No.1 Kaoimari, PO- Badhakora Community Buildings — LAKHIMPUR(DEPUTY COMMISSIONER LAKHIMPUR_IDA) - ₹500,000 against a ₹300,000 median for Community Buildings works in LAKHIMPUR (67% above, 71 peer works)
- 335 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| LAKHIMPUR | ₹5.00 L | MEDIUM 51 | |
| 19 | Lachit Sangha Community Buildings — LAKHIMPUR(DEPUTY COMMISSIONER LAKHIMPUR_IDA) - ₹500,000 against a ₹300,000 median for Community Buildings works in LAKHIMPUR (67% above, 71 peer works)
- 335 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| LAKHIMPUR | ₹5.00 L | MEDIUM 51 | |
| 20 | Na- Ali Community Hall Community Buildings — LAKHIMPUR(DEPUTY COMMISSIONER LAKHIMPUR_IDA) - ₹500,000 against a ₹300,000 median for Community Buildings works in LAKHIMPUR (67% above, 71 peer works)
- 335 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| LAKHIMPUR | ₹5.00 L | MEDIUM 51 | |
| 21 | Construction of New Conference Hall at DDR College Campus, C Education — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 665 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹10.00 L | MEDIUM 50 | |
| 22 | Const. of Dirak Sumoni Sluice Gate in Na Dihing River Embank Boundary & Protection — TINSUKIA(DC Tinsukia) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 718 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 71% delay rate across its projects
| TINSUKIA | ₹10.00 L | MEDIUM 50 | |
| 23 | Ward No.6, North Lakhimpur, Lakhimpur (Assam) Other — LAKHIMPUR(DEPUTY COMMISSIONER LAKHIMPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 729 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| LAKHIMPUR | ₹10.00 L | MEDIUM 49 | |
| 24 | Construction of Temporary Iron Bridge at Kemi River under MP Roads & Paving — DHEMAJI(DEPUTY COMMISSIONER DHEMAJI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 369 days beyond expected completion
| DHEMAJI | ₹36.00 L | MEDIUM 49 | |
| 25 | puja mandap Religious & Cultural — LAKHIMPUR(DEPUTY COMMISSIONER LAKHIMPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 777 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| LAKHIMPUR | ₹6.00 L | MEDIUM 48 | |