| 1 | Street Light - Installation of High Mast Light at Belagavadi Street Lighting — Bengaluru South(DEPUTY COMMISSIONER RAMANAGARA_IDA) - ₹500,000 against a ₹249,923 median for Street Lighting works in BENGALURU SOUTH (100% above, 14 peer works)
- 211 days beyond expected completion
Read more (1 more)Show less- 63% of this agency's ₹47,782,352 spend went to one vendor (PROJECT MANAGER NIRMITHI KENDRA RAMANAGARA), across 27 vendors and 167 transactions
| BENGALURU SOUTH | ₹5.00 L | MEDIUM 59 | |
| 2 | Street Light - High Mast Light at Aralikattedoddi, Mathikere Street Lighting — Bengaluru South(DEPUTY COMMISSIONER RAMANAGARA_IDA) - ₹500,000 against a ₹249,923 median for Street Lighting works in BENGALURU SOUTH (100% above, 14 peer works)
- 211 days beyond expected completion
Read more (1 more)Show less- 63% of this agency's ₹47,782,352 spend went to one vendor (PROJECT MANAGER NIRMITHI KENDRA RAMANAGARA), across 27 vendors and 167 transactions
| BENGALURU SOUTH | ₹5.00 L | MEDIUM 59 | |
| 3 | Construction of community centers and community halls at Sul Community Buildings — Bengaluru South(DEPUTY COMMISSIONER RAMANAGARA_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in BENGALURU SOUTH (100% above, 133 peer works)
- 351 days beyond expected completion
Read more (1 more)Show less- 63% of this agency's ₹47,782,352 spend went to one vendor (PROJECT MANAGER NIRMITHI KENDRA RAMANAGARA), across 27 vendors and 167 transactions
| BENGALURU SOUTH | ₹10.00 L | MEDIUM 59 | |
| 4 | Construction of community hall by Hassan District Vokkaligar Community Buildings — HASSAN(DEPUTY COMMISSIONER HASSAN_IDA) - ₹1,000,000 against a ₹300,000 median for Community Buildings works in HASSAN (233% above, 293 peer works)
- 329 days beyond expected completion
| HASSAN | ₹10.00 L | MEDIUM 55 | |
| 5 | Construction of community Hall at Bolamaranahalli Village, A Community Buildings — MANDYA(DEPUTY COMMISSIONER MANDYA_IDA) - 84 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 90% of this agency's ₹44,437,263 spend went to one vendor (PROJECT MANAGER NIRMITHI KENDRA MANDYA), across 4 vendors and 119 transactions
| MANDYA | ₹4.90 L | MEDIUM 52
duplication 20agency 15delay 12 | |
| 6 | Installing tube-wells and borewells- Digging of Drinking wat Water — Bengaluru South(DEPUTY COMMISSIONER RAMANAGARA_IDA) - 164 days beyond expected completion
- 98% similarity with another nearby work
Read more (1 more)Show less- 63% of this agency's ₹47,782,352 spend went to one vendor (PROJECT MANAGER NIRMITHI KENDRA RAMANAGARA), across 27 vendors and 167 transactions
| BENGALURU SOUTH | ₹2.00 L | MEDIUM 51
delay 23duplication 13agency 9 | |
| 7 | Installing tube-wells and borewells- Digging of Drinking wat Water — Bengaluru South(DEPUTY COMMISSIONER RAMANAGARA_IDA) - 164 days beyond expected completion
- 98% similarity with another nearby work
Read more (1 more)Show less- 63% of this agency's ₹47,782,352 spend went to one vendor (PROJECT MANAGER NIRMITHI KENDRA RAMANAGARA), across 27 vendors and 167 transactions
| BENGALURU SOUTH | ₹2.00 L | MEDIUM 51
delay 23duplication 13agency 9 | |
| 8 | Purchase of necessary equipments and Computers for The Rural Education — Bengaluru South(DEPUTY COMMISSIONER RAMANAGARA_IDA) - ₹5,000,000 against a ₹500,000 median for Education works in BENGALURU SOUTH (900% above, 9 peer works)
- 115 days beyond expected completion
Read more (1 more)Show less- 63% of this agency's ₹47,782,352 spend went to one vendor (PROJECT MANAGER NIRMITHI KENDRA RAMANAGARA), across 27 vendors and 167 transactions
| BENGALURU SOUTH | ₹50.00 L | MEDIUM 50 | |
| 9 | Installing borewell at Shanubhoganahalli Village and Grama P Water — Bengaluru South(DEPUTY COMMISSIONER RAMANAGARA_IDA) - 195 days beyond expected completion
- 63% of this agency's ₹47,782,352 spend went to one vendor (PROJECT MANAGER NIRMITHI KENDRA RAMANAGARA), across 27 vendors and 167 transactions
| BENGALURU SOUTH | ₹1.50 L | MEDIUM 49
delay 25agency 9duplication 7 | |
| 10 | Installing borewell at Doddanahalli Village, Neelasandra Gra Water — Bengaluru South(DEPUTY COMMISSIONER RAMANAGARA_IDA) - 195 days beyond expected completion
- 63% of this agency's ₹47,782,352 spend went to one vendor (PROJECT MANAGER NIRMITHI KENDRA RAMANAGARA), across 27 vendors and 167 transactions
| BENGALURU SOUTH | ₹2.00 L | MEDIUM 48
delay 25agency 9duplication 7 | |
| 11 | Construction of New Milk Producers Co-Operative Society Buil Community Buildings — Bengaluru South(DEPUTY COMMISSIONER RAMANAGARA_IDA) - 206 days beyond expected completion
- 63% of this agency's ₹47,782,352 spend went to one vendor (PROJECT MANAGER NIRMITHI KENDRA RAMANAGARA), across 27 vendors and 167 transactions
| BENGALURU SOUTH | ₹3.00 L | MEDIUM 46 | |
| 12 | Installing borewell at Dasarahalli Village, Hunasanahalli Gr Water — Bengaluru South(DEPUTY COMMISSIONER RAMANAGARA_IDA) - 195 days beyond expected completion
- 63% of this agency's ₹47,782,352 spend went to one vendor (PROJECT MANAGER NIRMITHI KENDRA RAMANAGARA), across 27 vendors and 167 transactions
| BENGALURU SOUTH | ₹2.00 L | MEDIUM 45 | |
| 13 | Setting up of Early Warning Systems for effective disaster m Other — Bengaluru South(DEPUTY COMMISSIONER RAMANAGARA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 238 days beyond expected completion
Read more (1 more)Show less- 63% of this agency's ₹47,782,352 spend went to one vendor (PROJECT MANAGER NIRMITHI KENDRA RAMANAGARA), across 27 vendors and 167 transactions
| BENGALURU SOUTH | ₹10.00 L | MEDIUM 44 | |
| 14 | Construction of bus-sheds or bus-stops at Harohalli Village, Community Buildings — Bengaluru South(DEPUTY COMMISSIONER RAMANAGARA_IDA) - 341 days beyond expected completion
- 63% of this agency's ₹47,782,352 spend went to one vendor (PROJECT MANAGER NIRMITHI KENDRA RAMANAGARA), across 27 vendors and 167 transactions
| BENGALURU SOUTH | ₹5.00 L | MEDIUM 44 | |
| 15 | Construction of bus-sheds or bus-stops at Jakkasandra Villag Community Buildings — Bengaluru South(DEPUTY COMMISSIONER RAMANAGARA_IDA) - 341 days beyond expected completion
- 63% of this agency's ₹47,782,352 spend went to one vendor (PROJECT MANAGER NIRMITHI KENDRA RAMANAGARA), across 27 vendors and 167 transactions
| BENGALURU SOUTH | ₹5.00 L | MEDIUM 44 | |
| 16 | Construction of building Kala Prathistan Ranga Mandira at To Religious & Cultural — TUMAKURU(DEPUTY COMMISSIONER TUMKUR_IDA) - ₹1,000,000 against a ₹490,000 median for Religious & Cultural works in TUMAKURU (104% above, 19 peer works)
- 97 days beyond expected completion
| TUMAKURU | ₹10.00 L | MEDIUM 44 | |
| 17 | Installing tube-wells and borewells- Digging of Drinking wat Water — Bengaluru South(DEPUTY COMMISSIONER RAMANAGARA_IDA) - 164 days beyond expected completion
- 63% of this agency's ₹47,782,352 spend went to one vendor (PROJECT MANAGER NIRMITHI KENDRA RAMANAGARA), across 27 vendors and 167 transactions
| BENGALURU SOUTH | ₹2.00 L | MEDIUM 43 | |
| 18 | Construction of community centre at Bheemasandradoddi Villag Community Buildings — Bengaluru South(DEPUTY COMMISSIONER RAMANAGARA_IDA) - 365 days beyond expected completion
- 63% of this agency's ₹47,782,352 spend went to one vendor (PROJECT MANAGER NIRMITHI KENDRA RAMANAGARA), across 27 vendors and 167 transactions
| BENGALURU SOUTH | ₹4.00 L | MEDIUM 43 | |
| 19 | Construction of bus-sheds or bus-stops at Sri Pataladamma Te Community Buildings — Bengaluru South(DEPUTY COMMISSIONER RAMANAGARA_IDA) - 341 days beyond expected completion
- 63% of this agency's ₹47,782,352 spend went to one vendor (PROJECT MANAGER NIRMITHI KENDRA RAMANAGARA), across 27 vendors and 167 transactions
| BENGALURU SOUTH | ₹5.00 L | MEDIUM 43 | |
| 20 | Construction of bus-sheds or bus-stops at Sri Anjaneya Swamy Community Buildings — Bengaluru South(DEPUTY COMMISSIONER RAMANAGARA_IDA) - 341 days beyond expected completion
- 63% of this agency's ₹47,782,352 spend went to one vendor (PROJECT MANAGER NIRMITHI KENDRA RAMANAGARA), across 27 vendors and 167 transactions
| BENGALURU SOUTH | ₹5.00 L | MEDIUM 43 | |
| 21 | Construction of bus-sheds or bus-stops at Kondapura Village, Community Buildings — Bengaluru South(DEPUTY COMMISSIONER RAMANAGARA_IDA) - 341 days beyond expected completion
- 63% of this agency's ₹47,782,352 spend went to one vendor (PROJECT MANAGER NIRMITHI KENDRA RAMANAGARA), across 27 vendors and 167 transactions
| BENGALURU SOUTH | ₹5.00 L | MEDIUM 43 | |
| 22 | Construction of bus-sheds or bus-stops at Santhe Mogenahalli Roads & Paving — Bengaluru South(DEPUTY COMMISSIONER RAMANAGARA_IDA) - 341 days beyond expected completion
- 63% of this agency's ₹47,782,352 spend went to one vendor (PROJECT MANAGER NIRMITHI KENDRA RAMANAGARA), across 27 vendors and 167 transactions
| BENGALURU SOUTH | ₹5.00 L | MEDIUM 43 | |
| 23 | Construction of bus-sheds or bus-stops at Doddakabballi Gate Community Buildings — Bengaluru South(DEPUTY COMMISSIONER RAMANAGARA_IDA) - 341 days beyond expected completion
- 63% of this agency's ₹47,782,352 spend went to one vendor (PROJECT MANAGER NIRMITHI KENDRA RAMANAGARA), across 27 vendors and 167 transactions
| BENGALURU SOUTH | ₹5.00 L | MEDIUM 43 | |
| 24 | Construction of bus-sheds or bus-stops at Aralalu Village, S Community Buildings — Bengaluru South(DEPUTY COMMISSIONER RAMANAGARA_IDA) - 341 days beyond expected completion
- 63% of this agency's ₹47,782,352 spend went to one vendor (PROJECT MANAGER NIRMITHI KENDRA RAMANAGARA), across 27 vendors and 167 transactions
| BENGALURU SOUTH | ₹5.00 L | MEDIUM 43 | |
| 25 | Construction of bus-sheds or bus-stops at Kebbehalli Village Community Buildings — Bengaluru South(DEPUTY COMMISSIONER RAMANAGARA_IDA) - 341 days beyond expected completion
- 63% of this agency's ₹47,782,352 spend went to one vendor (PROJECT MANAGER NIRMITHI KENDRA RAMANAGARA), across 27 vendors and 167 transactions
| BENGALURU SOUTH | ₹5.00 L | MEDIUM 43 | |