| 1 | Construction of Community Centre at Village Sukhlasar Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - ₹400,000 against a ₹200,000 median for Community Buildings works in SUBARNAPUR (100% above, 139 peer works)
- 616 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹4.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 2 | Construction of Community Centre at Village Ainlapali Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - ₹400,000 against a ₹200,000 median for Community Buildings works in SUBARNAPUR (100% above, 139 peer works)
- 616 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹4.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 3 | Construction of Community Centre at Village Sukhlasar Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - ₹400,000 against a ₹200,000 median for Community Buildings works in SUBARNAPUR (100% above, 139 peer works)
- 616 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹4.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 4 | Construction of Community Centre at Village Ainlapali Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - ₹400,000 against a ₹200,000 median for Community Buildings works in SUBARNAPUR (100% above, 139 peer works)
- 616 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹4.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 5 | Cremation center near burial ground in Rajapur village in Ga Religious & Cultural — GANJAM(DISTRICT COLLECTOR GANJAM_IDA) - ₹1,000,000 against a ₹300,000 median for Religious & Cultural works in GANJAM (233% above, 112 peer works)
- 302 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 57% delay rate across its projects
| GANJAM | ₹10.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 6 | Cremation center near burial ground in Rajapur village in Ga Religious & Cultural — GANJAM(DISTRICT COLLECTOR GANJAM_IDA) - ₹1,000,000 against a ₹300,000 median for Religious & Cultural works in GANJAM (233% above, 112 peer works)
- 302 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 57% delay rate across its projects
| GANJAM | ₹10.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 7 | Renovation of Christian Cemetery in Jatni Town, Khurda distr Religious & Cultural — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹500,000 against a ₹250,000 median for Religious & Cultural works in KHORDHA (100% above, 128 peer works)
- 192 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹5.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 8 | Repair and Renovation of KUMAR PATHAGARA, Kumarangasasan, Ba Community Buildings — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in KHORDHA (100% above, 144 peer works)
- 302 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 9 | Construction of two additional classrooms of the B.B. Govt V Education — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,500,000 against a ₹500,000 median for Education works in KHORDHA (200% above, 131 peer works)
- 594 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹15.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 10 | Construction of two Guest Rooms inside the Hostel Premises o Education — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,500,000 against a ₹500,000 median for Education works in KHORDHA (200% above, 131 peer works)
- 595 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹15.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 11 | Construction of BATABRUKSHYA MANDAP COMMUNITY HALL near Daru Community Buildings — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in KHORDHA (100% above, 144 peer works)
- 620 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 12 | Construction of Auditorium of BJB (Autonomous) College, BJB Education — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹5,000,000 against a ₹500,000 median for Education works in KHORDHA (900% above, 131 peer works)
- 620 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹50.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 13 | Renovation of Christian Cemetery in Jatni Town, Khurda distr Religious & Cultural — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹500,000 against a ₹250,000 median for Religious & Cultural works in KHORDHA (100% above, 128 peer works)
- 192 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹5.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 14 | Repair and Renovation of KUMAR PATHAGARA, Kumarangasasan, Ba Community Buildings — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in KHORDHA (100% above, 144 peer works)
- 302 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 15 | Construction of two additional classrooms of the B.B. Govt V Education — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,500,000 against a ₹500,000 median for Education works in KHORDHA (200% above, 131 peer works)
- 594 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹15.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 16 | Construction of two Guest Rooms inside the Hostel Premises o Education — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,500,000 against a ₹500,000 median for Education works in KHORDHA (200% above, 131 peer works)
- 595 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹15.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 17 | Construction of BATABRUKSHYA MANDAP COMMUNITY HALL near Daru Community Buildings — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in KHORDHA (100% above, 144 peer works)
- 620 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 18 | Construction of Auditorium of BJB (Autonomous) College, BJB Education — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹5,000,000 against a ₹500,000 median for Education works in KHORDHA (900% above, 131 peer works)
- 620 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹50.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 19 | Erection of Gandhian Heritage Gate near Government Ayurvedic Health — Jajpur(DISTRICT COLLECTOR JAJPUR_IDA) - ₹1,000,000 against a ₹500,000 median for Health works in JAJPUR (100% above, 26 peer works)
- 192 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAJPUR | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 20 | Upgradation of Auditorium Hall in Municipal High School unde Education — Jajpur(DISTRICT COLLECTOR JAJPUR_IDA) - ₹12,500,000 against a ₹1,000,000 median for Education works in JAJPUR (1150% above, 96 peer works)
- 589 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAJPUR | ₹1.25 Cr | HIGH 76
cost 25delay 25duplication 20 | |
| 21 | Erection of Gandhian Heritage Gate near Government Ayurvedic Health — Jajpur(DISTRICT COLLECTOR JAJPUR_IDA) - ₹1,000,000 against a ₹500,000 median for Health works in JAJPUR (100% above, 26 peer works)
- 192 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAJPUR | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 22 | Upgradation of Auditorium Hall in Municipal High School unde Education — Jajpur(DISTRICT COLLECTOR JAJPUR_IDA) - ₹12,500,000 against a ₹1,000,000 median for Education works in JAJPUR (1150% above, 96 peer works)
- 589 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAJPUR | ₹1.25 Cr | HIGH 76
cost 25delay 25duplication 20 | |
| 23 | Construction of DPS Road from Niali Main Road to Mangala Man Roads & Paving — Kataka(DISTRICT COLLECTOR CUTTACK_IDA) - ₹1,000,000 against a ₹300,000 median for Roads & Paving works in KATAKA (233% above, 113 peer works)
- 291 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KATAKA | ₹10.00 L | HIGH 74
cost 25delay 25duplication 20 | |
| 24 | Construction of DPS Road from Mangala Mandir to DPS Kalinga Roads & Paving — Kataka(DISTRICT COLLECTOR CUTTACK_IDA) - ₹1,000,000 against a ₹300,000 median for Roads & Paving works in KATAKA (233% above, 113 peer works)
- 291 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KATAKA | ₹10.00 L | HIGH 74
cost 25delay 25duplication 20 | |
| 25 | Solar Water Pump with Tubewell for drinking purpose Near And Water — Kataka(DISTRICT COLLECTOR CUTTACK_IDA) - ₹800,000 against a ₹200,000 median for Water works in KATAKA (300% above, 69 peer works)
- 597 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KATAKA | ₹8.00 L | HIGH 74
cost 25delay 25duplication 20 | |