| 1 | Construction of community hall Community Buildings — PUNE(DISTRICT COLLECTOR PUNE_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 586 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| PUNE | ₹10.00 L | MEDIUM 63
delay 25duplication 20cost 13 | |
| 2 | Construction of Community Hall Community Buildings — PUNE(DISTRICT COLLECTOR PUNE_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 586 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| PUNE | ₹10.00 L | MEDIUM 63
delay 25duplication 20cost 13 | |
| 3 | Construction of Community Hall Community Buildings — PUNE(DISTRICT COLLECTOR PUNE_IDA) - 592 days beyond expected completion
- 100% similarity with another nearby work
| PUNE | ₹5.00 L | MEDIUM 58
delay 25duplication 20cost 8 | |
| 4 | Construction of approach Road At Savargaon towards Narayan S Street Lighting — PUNE(DISTRICT COLLECTOR PUNE_IDA) - ₹1,000,000 against a ₹500,000 median for Street Lighting works in PUNE (100% above, 57 peer works)
- 177 days beyond expected completion
| PUNE | ₹10.00 L | MEDIUM 55 | |
| 5 | Construction of Comminity Hall at Nimgaon Ketki Community Buildings — PUNE(DISTRICT COLLECTOR PUNE_IDA) - ₹2,000,000 against a ₹1,000,000 median for Community Buildings works in PUNE (100% above, 255 peer works)
- 177 days beyond expected completion
| PUNE | ₹20.00 L | MEDIUM 55 | |
| 6 | Construction of road from Arvind Patil Vasti to Indapur Bara Roads & Paving — PUNE(DISTRICT COLLECTOR PUNE_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 984 days beyond expected completion
| PUNE | ₹9.98 L | MEDIUM 48 | |
| 7 | Beautification from Pimple Bus Stop to Gram Panchayat. Roads & Paving — PUNE(DISTRICT COLLECTOR PUNE_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 984 days beyond expected completion
| PUNE | ₹10.00 L | MEDIUM 48 | |
| 8 | Making the road behind Maruti Mandir under Mauje Gogalwadi. Roads & Paving — PUNE(DISTRICT COLLECTOR PUNE_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 984 days beyond expected completion
| PUNE | ₹10.00 L | MEDIUM 48 | |
| 9 | Kalthan in Indapur Taluk No. 01 Construction of Social Hall. Community Buildings — PUNE(DISTRICT COLLECTOR PUNE_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 984 days beyond expected completion
| PUNE | ₹10.00 L | MEDIUM 48 | |
| 10 | Construction of Library at Parinche Boudhavasti in Purandar Education — PUNE(DISTRICT COLLECTOR PUNE_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 1119 days beyond expected completion
| PUNE | ₹7.00 L | MEDIUM 48 | |
| 11 | Construction of assembly hall at Mauje Ketkavale in Purandar Community Buildings — PUNE(DISTRICT COLLECTOR PUNE_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 984 days beyond expected completion
| PUNE | ₹6.99 L | MEDIUM 47 | |
| 12 | Construction of Shelter Shed at Dasakriya Vidhi Ghat at Mauj Community Buildings — PUNE(DISTRICT COLLECTOR PUNE_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 1119 days beyond expected completion
| PUNE | ₹5.50 L | MEDIUM 46 | |
| 13 | Construction of assembly hall at Ambwade Gulumkarwadi in Bho Community Buildings — PUNE(DISTRICT COLLECTOR PUNE_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 1287 days beyond expected completion
| PUNE | ₹2.50 L | MEDIUM 46 | |
| 14 | Construction of crematorium in backward class settlement at Religious & Cultural — PUNE(DISTRICT COLLECTOR PUNE_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 1287 days beyond expected completion
| PUNE | ₹3.50 L | MEDIUM 46 | |
| 15 | Mauje Gorhe Khu in Haveli taluka. Building a cemetery. Religious & Cultural — PUNE(DISTRICT COLLECTOR PUNE_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 1287 days beyond expected completion
| PUNE | ₹5.00 L | MEDIUM 46 | |
| 16 | Construction of a protective wall around a water supply well Water — PUNE(DISTRICT COLLECTOR PUNE_IDA) - ₹1,000,000 against a ₹598,815 median for Water works in PUNE (67% above, 20 peer works)
- 174 days beyond expected completion
| PUNE | ₹10.00 L | MEDIUM 46 | |
| 17 | Construction of closed drains at Mauje Aglambe Dehnewadi and Roads & Paving — PUNE(DISTRICT COLLECTOR PUNE_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 1119 days beyond expected completion
| PUNE | ₹2.50 L | MEDIUM 46 | |
| 18 | Construction of assembly hall at Mauje Ambwade Charamkar Vas Community Buildings — PUNE(DISTRICT COLLECTOR PUNE_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 1287 days beyond expected completion
| PUNE | ₹3.00 L | MEDIUM 46 | |
| 19 | Construction of Social Hall at Mauje Pise in Purandar Taluk. Community Buildings — PUNE(DISTRICT COLLECTOR PUNE_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 1119 days beyond expected completion
| PUNE | ₹4.99 L | MEDIUM 46 | |
| 20 | Concrete cementing of the road in front of Mauje Ahire Gram Roads & Paving — PUNE(DISTRICT COLLECTOR PUNE_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 1119 days beyond expected completion
| PUNE | ₹5.00 L | MEDIUM 46 | |
| 21 | Mauje Mauje Construction of assembly hall at Kambalwadi (Sat Community Buildings — PUNE(DISTRICT COLLECTOR PUNE_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 1119 days beyond expected completion
| PUNE | ₹3.00 L | MEDIUM 46 | |
| 22 | Laying of paving blocks at Khanwadi Samajmandir premises Roads & Paving — PUNE(DISTRICT COLLECTOR PUNE_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 984 days beyond expected completion
| PUNE | ₹5.00 L | MEDIUM 45 | |
| 23 | Construction of protective wall for Lingayat Samaj Crematori Boundary & Protection — PUNE(DISTRICT COLLECTOR PUNE_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 984 days beyond expected completion
| PUNE | ₹5.00 L | MEDIUM 45 | |
| 24 | Installation of paving blocks near Dalitvasti Mhasoba Mandir Religious & Cultural — PUNE(DISTRICT COLLECTOR PUNE_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 984 days beyond expected completion
| PUNE | ₹5.00 L | MEDIUM 45 | |
| 25 | Concreting of road under Sonarwadi Roads & Paving — PUNE(DISTRICT COLLECTOR PUNE_IDA) - ₹1,500,000 against a ₹999,680 median for Roads & Paving works in PUNE (50% above, 316 peer works)
- 574 days beyond expected completion
| PUNE | ₹15.00 L | MEDIUM 45 | |