| 1 | Construction of P.C.C Open Mancha infront of Manikora Maa Ka Religious & Cultural — Malda(DISTRICT MAGISTRATE MALDA_IDA) - ₹823,000 against a ₹400,000 median for Religious & Cultural works in MALDA (106% above, 33 peer works)
- 578 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 45% delay rate across its projects
| MALDA | ₹8.23 L | HIGH 76
cost 25delay 25duplication 19 | |
| 2 | Construction of P.C.C Open Mancha infront of Manikora Maa Ka Religious & Cultural — Malda(DISTRICT MAGISTRATE MALDA_IDA) - ₹823,000 against a ₹400,000 median for Religious & Cultural works in MALDA (106% above, 33 peer works)
- 578 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 45% delay rate across its projects
| MALDA | ₹8.23 L | HIGH 76
cost 25delay 25duplication 19 | |
| 3 | Installation of 15w* 2pc , 2 ways Rashmi Star/Osram/GE Led S Street Lighting — Malda(DISTRICT MAGISTRATE MALDA_IDA) - 617 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| MALDA | ₹50,000 | MEDIUM 61
delay 25duplication 20cost 10 | |
| 4 | Installation of 15w* 2pc , 2 ways Rashmi Star/Osram/GE Led S Street Lighting — Malda(DISTRICT MAGISTRATE MALDA_IDA) - 617 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| MALDA | ₹50,000 | MEDIUM 61
delay 25duplication 20cost 10 | |
| 5 | Installation of 15w* 2pc , 2 ways Rashmi Star/Osram/GE Led S Street Lighting — Malda(DISTRICT MAGISTRATE MALDA_IDA) - 617 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| MALDA | ₹50,000 | MEDIUM 61
delay 25duplication 19cost 10 | |
| 6 | Installation of 15w* 2pc , 2 ways Rashmi Star/Osram/GE Led S Street Lighting — Malda(DISTRICT MAGISTRATE MALDA_IDA) - 617 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| MALDA | ₹50,000 | MEDIUM 60
delay 25duplication 19cost 10 | |
| 7 | Installation of 15w* 2pc , 2 ways Rashmi Star/Osram/GE Led S Street Lighting — Malda(DISTRICT MAGISTRATE MALDA_IDA) - 617 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| MALDA | ₹50,000 | MEDIUM 60
delay 25duplication 19cost 10 | |
| 8 | Installation of 15w* 2pc , 2 ways Rashmi Star/Osram/GE Led S Street Lighting — Malda(DISTRICT MAGISTRATE MALDA_IDA) - 617 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| MALDA | ₹50,000 | MEDIUM 60
delay 25duplication 19cost 10 | |
| 9 | Installation of 15 w *1 pc Rashmi Star/Osram/GE Led Street S Street Lighting — Malda(DISTRICT MAGISTRATE MALDA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 620 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 45% delay rate across its projects
| MALDA | ₹32,000 | MEDIUM 60
delay 25duplication 18cost 10 | |
| 10 | Installation of 15w* 2pc , 2 ways Rashmi Star/Osram/GE Led Street Lighting — Malda(DISTRICT MAGISTRATE MALDA_IDA) - 617 days beyond expected completion
- 99% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| MALDA | ₹50,000 | MEDIUM 59
delay 25duplication 18cost 10 | |
| 11 | Installation of 15w* 2pc , 2 ways Rashmi Star/Osram/GE Led S Street Lighting — Malda(DISTRICT MAGISTRATE MALDA_IDA) - 617 days beyond expected completion
- 99% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| MALDA | ₹50,000 | MEDIUM 59
delay 25duplication 18cost 10 | |
| 12 | Installation of 15 w *1 pc Rashmi Star/Osram/GE Led Street S Street Lighting — Malda(DISTRICT MAGISTRATE MALDA_IDA) - 617 days beyond expected completion
- 99% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| MALDA | ₹32,000 | MEDIUM 59
delay 25duplication 17cost 10 | |
| 13 | Installation of 15 w* 2pc , 2 ways Rashmi Star/Osram/GE Led Street Lighting — Malda(DISTRICT MAGISTRATE MALDA_IDA) - 617 days beyond expected completion
- 99% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| MALDA | ₹50,000 | MEDIUM 59
delay 25duplication 17cost 10 | |
| 14 | Installation of 15 w* 2pc , 2 ways Rashmi Star/Osram/GE Led Street Lighting — Malda(DISTRICT MAGISTRATE MALDA_IDA) - 617 days beyond expected completion
- 99% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| MALDA | ₹50,000 | MEDIUM 59
delay 25duplication 17cost 10 | |
| 15 | Installation of All in one 30 w *1 pc Rashmi Star Led Solar Street Lighting — Malda(DISTRICT MAGISTRATE MALDA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 545 days beyond expected completion
Read more (2 more)Show less- 99% similarity with another nearby work
- Implementing agency has a 45% delay rate across its projects
| MALDA | ₹50,000 | MEDIUM 58
delay 25duplication 16cost 10 | |
| 16 | Installation of All in one 30 w *1 pc Rashmi Star Led Solar Street Lighting — Malda(DISTRICT MAGISTRATE MALDA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 545 days beyond expected completion
Read more (2 more)Show less- 99% similarity with another nearby work
- Implementing agency has a 45% delay rate across its projects
| MALDA | ₹50,000 | MEDIUM 58
delay 25duplication 16cost 10 | |
| 17 | Installation of Rashmi Star 1 pc*15w Solar Light at 1 Place Street Lighting — Malda(DISTRICT MAGISTRATE MALDA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 577 days beyond expected completion
Read more (2 more)Show less- 99% similarity with another nearby work
- Implementing agency has a 45% delay rate across its projects
| MALDA | ₹32,000 | MEDIUM 58
delay 25duplication 17cost 10 | |
| 18 | Installation of Rashmi Star 1 pc*15w Solar Light at 1 Place Street Lighting — Malda(DISTRICT MAGISTRATE MALDA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 577 days beyond expected completion
Read more (2 more)Show less- 99% similarity with another nearby work
- Implementing agency has a 45% delay rate across its projects
| MALDA | ₹32,000 | MEDIUM 58
delay 25duplication 17cost 10 | |
| 19 | Installation of 15w* 2pc , 2 ways Rashmi Star/Osram/GE Led S Street Lighting — Malda(DISTRICT MAGISTRATE MALDA_IDA) - 617 days beyond expected completion
- 99% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| MALDA | ₹50,000 | MEDIUM 58
delay 25duplication 16cost 10 | |
| 20 | Installation of 15 w *1 pc Rashmi Star/Osram/GE Led Street S Street Lighting — Malda(DISTRICT MAGISTRATE MALDA_IDA) - 617 days beyond expected completion
- 99% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| MALDA | ₹32,000 | MEDIUM 58
delay 25duplication 16cost 10 | |
| 21 | Installation of 15w* 2pc , 2 ways Rashmi Star/Osram/GE Led S Street Lighting — Malda(DISTRICT MAGISTRATE MALDA_IDA) - 617 days beyond expected completion
- 99% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| MALDA | ₹50,000 | MEDIUM 57
delay 25duplication 16cost 10 | |
| 22 | Construction of CC Road at Gopalpur Haat from Tapes Barman H Roads & Paving — Malda(DISTRICT MAGISTRATE MALDA_IDA) - ₹1,100,000 against a ₹400,000 median for Roads & Paving works in MALDA (175% above, 165 peer works)
- 577 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| MALDA | ₹11.00 L | MEDIUM 57 | |
| 23 | Construction of Pakka Concrete 2 no. of Bathroom, 2no. of To Water — Malda(DISTRICT MAGISTRATE MALDA_IDA) - ₹1,070,000 against a ₹180,000 median for Water works in MALDA (494% above, 12 peer works)
- 625 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| MALDA | ₹10.70 L | MEDIUM 57 | |
| 24 | Construction of Guest Room at Gabarjana at near Kali mandir Religious & Cultural — Malda(DISTRICT MAGISTRATE MALDA_IDA) - ₹979,666 against a ₹400,000 median for Religious & Cultural works in MALDA (145% above, 33 peer works)
- 626 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| MALDA | ₹9.80 L | MEDIUM 57 | |
| 25 | Construction of CC Road from Dhaoel Pratibesi Sangha toward Roads & Paving — Malda(DISTRICT MAGISTRATE MALDA_IDA) - ₹1,000,000 against a ₹400,000 median for Roads & Paving works in MALDA (150% above, 165 peer works)
- 639 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| MALDA | ₹10.00 L | MEDIUM 57 | |