| 1 | Construction of C/Hall at Uttar Sootea Yubak Sangha, Mudoi G Community Buildings — Biswanath(Deputy Commissioner Biswanath_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in BISWANATH (100% above, 46 peer works)
- 555 days beyond expected completion
Read more (1 more)Show less- 94% of this agency's ₹26,228,960 spend went to one vendor (LOHIT BHUYAN), across 2 vendors and 196 transactions
| BISWANATH | ₹10.00 L | MEDIUM 65 | |
| 2 | Construction of C/Hall in Seva Bharati, Missamari Community Buildings — SONITPUR(Deputy Commissioner Sonitpur, Tezpur) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in SONITPUR (100% above, 73 peer works)
- 594 days beyond expected completion
Read more (1 more)Show less- 77% of this agency's ₹39,850,751 spend went to one vendor (MAHAMAYA CONSTRUCTION), across 6 vendors and 302 transactions
| SONITPUR | ₹10.00 L | MEDIUM 65 | |
| 3 | Construction of C/Hall near Thakurbari Mandir, Ward No. 5 Bi Community Buildings — Biswanath(Deputy Commissioner Biswanath_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in BISWANATH (100% above, 46 peer works)
- 594 days beyond expected completion
Read more (1 more)Show less- 94% of this agency's ₹26,228,960 spend went to one vendor (LOHIT BHUYAN), across 2 vendors and 196 transactions
| BISWANATH | ₹10.00 L | MEDIUM 65 | |
| 4 | Const of C/Hall at ACMS Tezpur Branch, Ward No 7 Community Buildings — SONITPUR(Deputy Commissioner Sonitpur, Tezpur) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in SONITPUR (100% above, 73 peer works)
- 597 days beyond expected completion
Read more (1 more)Show less- 77% of this agency's ₹39,850,751 spend went to one vendor (MAHAMAYA CONSTRUCTION), across 6 vendors and 302 transactions
| SONITPUR | ₹10.00 L | MEDIUM 65 | |
| 5 | Construction of Community Hall near Phuloni Than, Ward No. 1 Community Buildings — LAKHIMPUR(DEPUTY COMMISSIONER LAKHIMPUR_IDA) - ₹1,000,000 against a ₹300,000 median for Community Buildings works in LAKHIMPUR (233% above, 71 peer works)
- 547 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| LAKHIMPUR | ₹10.00 L | MEDIUM 59 | |
| 6 | Construction of Auditorium at Sankardev College, Pathalipaha Education — LAKHIMPUR(DEPUTY COMMISSIONER LAKHIMPUR_IDA) - ₹1,000,000 against a ₹500,000 median for Education works in LAKHIMPUR (100% above, 24 peer works)
- 594 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| LAKHIMPUR | ₹10.00 L | MEDIUM 59 | |
| 7 | Elevator facility for Divyang and Elderly Citizens at DC Off Equipment & Vehicles — SONITPUR(Deputy Commissioner Sonitpur, Tezpur) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 574 days beyond expected completion
Read more (1 more)Show less- 77% of this agency's ₹39,850,751 spend went to one vendor (MAHAMAYA CONSTRUCTION), across 6 vendors and 302 transactions
| SONITPUR | ₹25.00 L | MEDIUM 58 | |
| 8 | Construction of Community Hall near Mornoiguri Namghar, 1 No Community Buildings — LAKHIMPUR(DEPUTY COMMISSIONER LAKHIMPUR_IDA) - ₹500,000 against a ₹300,000 median for Community Buildings works in LAKHIMPUR (67% above, 71 peer works)
- 546 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| LAKHIMPUR | ₹5.00 L | MEDIUM 51 | |
| 9 | Construction of Community Hall near Pathalipahar Bor Namghar Community Buildings — LAKHIMPUR(DEPUTY COMMISSIONER LAKHIMPUR_IDA) - ₹500,000 against a ₹300,000 median for Community Buildings works in LAKHIMPUR (67% above, 71 peer works)
- 547 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| LAKHIMPUR | ₹5.00 L | MEDIUM 51 | |
| 10 | Construction of Community Hall near Sangini Satra, Bodoti Community Buildings — LAKHIMPUR(DEPUTY COMMISSIONER LAKHIMPUR_IDA) - ₹500,000 against a ₹300,000 median for Community Buildings works in LAKHIMPUR (67% above, 71 peer works)
- 547 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| LAKHIMPUR | ₹5.00 L | MEDIUM 51 | |
| 11 | Construction of Community Hall near Jarabari Namghar, Bihpur Community Buildings — LAKHIMPUR(DEPUTY COMMISSIONER LAKHIMPUR_IDA) - ₹500,000 against a ₹300,000 median for Community Buildings works in LAKHIMPUR (67% above, 71 peer works)
- 547 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| LAKHIMPUR | ₹5.00 L | MEDIUM 51 | |
| 12 | Construction of Community Hall near Shri Gopal Maha Prabhu T Community Buildings — LAKHIMPUR(DEPUTY COMMISSIONER LAKHIMPUR_IDA) - ₹500,000 against a ₹300,000 median for Community Buildings works in LAKHIMPUR (67% above, 71 peer works)
- 547 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| LAKHIMPUR | ₹5.00 L | MEDIUM 51 | |
| 13 | Construction of Community Hall near Keshab Sharan Atta Than Community Buildings — LAKHIMPUR(DEPUTY COMMISSIONER LAKHIMPUR_IDA) - ₹500,000 against a ₹300,000 median for Community Buildings works in LAKHIMPUR (67% above, 71 peer works)
- 547 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| LAKHIMPUR | ₹5.00 L | MEDIUM 51 | |
| 14 | Construction of Community Hall near Belaguri Satra, Bihpuria Community Buildings — LAKHIMPUR(DEPUTY COMMISSIONER LAKHIMPUR_IDA) - ₹500,000 against a ₹300,000 median for Community Buildings works in LAKHIMPUR (67% above, 71 peer works)
- 547 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| LAKHIMPUR | ₹5.00 L | MEDIUM 51 | |
| 15 | Construction of C/Hall at Rodali Sangha, Ward No. 6, Bihpuri Community Buildings — LAKHIMPUR(DEPUTY COMMISSIONER LAKHIMPUR_IDA) - ₹500,000 against a ₹300,000 median for Community Buildings works in LAKHIMPUR (67% above, 71 peer works)
- 594 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| LAKHIMPUR | ₹5.00 L | MEDIUM 51 | |
| 16 | Construction of Community Hall near Jagannath Mandir, Niz-La Community Buildings — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 574 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹10.15 L | MEDIUM 49 | |
| 17 | Construction of C/Hall near Kali Mandir (Cremation Ground) , Community Buildings — SONITPUR(Deputy Commissioner Sonitpur, Tezpur) - 546 days beyond expected completion
- 77% of this agency's ₹39,850,751 spend went to one vendor (MAHAMAYA CONSTRUCTION), across 6 vendors and 302 transactions
| SONITPUR | ₹5.00 L | MEDIUM 49 | |
| 18 | Const of C/Hall near Radha Krishna Mandir, 2 No Bagipukhuri Community Buildings — SONITPUR(Deputy Commissioner Sonitpur, Tezpur) - 546 days beyond expected completion
- 77% of this agency's ₹39,850,751 spend went to one vendor (MAHAMAYA CONSTRUCTION), across 6 vendors and 302 transactions
| SONITPUR | ₹5.00 L | MEDIUM 49 | |
| 19 | Construction of Boundary Wall at Dhullie 3. No Cremation Gro Boundary & Protection — Biswanath(Deputy Commissioner Biswanath_IDA) - 546 days beyond expected completion
- 94% of this agency's ₹26,228,960 spend went to one vendor (LOHIT BHUYAN), across 2 vendors and 196 transactions
| BISWANATH | ₹5.00 L | MEDIUM 49 | |
| 20 | Construction of Cycle Stand at Dekorai High Secondary School Education — Biswanath(Deputy Commissioner Biswanath_IDA) - 556 days beyond expected completion
- 94% of this agency's ₹26,228,960 spend went to one vendor (LOHIT BHUYAN), across 2 vendors and 196 transactions
| BISWANATH | ₹5.00 L | MEDIUM 48 | |
| 21 | Construction of Additional Class Room at Kalahandi LP School Education — Biswanath(Deputy Commissioner Biswanath_IDA) - 556 days beyond expected completion
- 94% of this agency's ₹26,228,960 spend went to one vendor (LOHIT BHUYAN), across 2 vendors and 196 transactions
| BISWANATH | ₹5.00 L | MEDIUM 48 | |
| 22 | Construction of Community Hall near Kamona Mandir, Pabhoi TE Community Buildings — Biswanath(Deputy Commissioner Biswanath_IDA) - 556 days beyond expected completion
- 94% of this agency's ₹26,228,960 spend went to one vendor (LOHIT BHUYAN), across 2 vendors and 196 transactions
| BISWANATH | ₹5.00 L | MEDIUM 48 | |
| 23 | Development of Kenduguri Bura Dangoria Than Religious & Cultural — SONITPUR(Deputy Commissioner Sonitpur, Tezpur) - 581 days beyond expected completion
- 77% of this agency's ₹39,850,751 spend went to one vendor (MAHAMAYA CONSTRUCTION), across 6 vendors and 302 transactions
| SONITPUR | ₹5.00 L | MEDIUM 48 | |
| 24 | Construction of Staircase at Jugalani Chhat Ghat Religious & Cultural — SONITPUR(Deputy Commissioner Sonitpur, Tezpur) - 581 days beyond expected completion
- 77% of this agency's ₹39,850,751 spend went to one vendor (MAHAMAYA CONSTRUCTION), across 6 vendors and 302 transactions
| SONITPUR | ₹5.00 L | MEDIUM 48 | |
| 25 | Development of Namghar at Hanupam Gaon, Chengamari, Sootea Religious & Cultural — Biswanath(Deputy Commissioner Biswanath_IDA) - 581 days beyond expected completion
- 94% of this agency's ₹26,228,960 spend went to one vendor (LOHIT BHUYAN), across 2 vendors and 196 transactions
| BISWANATH | ₹5.00 L | MEDIUM 48 | |