| 1 | vidhan Sabha Setra Jhadol Phalasia ke Panchayat Samiti Phala Education — UDAIPUR(DISTRICT COLLECTOR UDAIPUR_IDA) - ₹2,000,000 against a ₹799,781 median for Education works in UDAIPUR (150% above, 38 peer works)
- 580 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 1 payment still in progress, oldest 763 days
| UDAIPUR | ₹20.00 L | HIGH 84
cost 25delay 25duplication 19 | |
| 2 | Vidhan Sabha Setra Jhadol Phalasiya ke Panchayat Samiti Kotr Education — UDAIPUR(DISTRICT COLLECTOR UDAIPUR_IDA) - ₹2,000,000 against a ₹799,781 median for Education works in UDAIPUR (150% above, 38 peer works)
- 580 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 1 payment still in progress, oldest 763 days
| UDAIPUR | ₹20.00 L | HIGH 84
cost 25delay 25duplication 19 | |
| 3 | Vidhan Sabha Setra Jhadol Falasia ke Panchayat Samiti Jhadol Education — UDAIPUR(DISTRICT COLLECTOR UDAIPUR_IDA) - ₹2,000,000 against a ₹799,781 median for Education works in UDAIPUR (150% above, 38 peer works)
- 580 days beyond expected completion
Read more (2 more)Show less- 98% similarity with another nearby work
- 1 payment still in progress, oldest 763 days
| UDAIPUR | ₹20.00 L | HIGH 80 | |
| 4 | Vidhan Sabha Setra Udaipur Rural ke Panchayat Samiti badgaon Education — UDAIPUR(DISTRICT COLLECTOR UDAIPUR_IDA) - ₹2,000,000 against a ₹799,781 median for Education works in UDAIPUR (150% above, 38 peer works)
- 580 days beyond expected completion
Read more (1 more)Show less- 1 payment still in progress, oldest 763 days
| UDAIPUR | ₹20.00 L | MEDIUM 69 | |
| 5 | Vidhan Sabha Chetra Kherwada ke Panchayat Samiti Rishabhdeo Education — UDAIPUR(DISTRICT COLLECTOR UDAIPUR_IDA) - ₹2,500,000 against a ₹799,781 median for Education works in UDAIPUR (213% above, 38 peer works)
- 549 days beyond expected completion
Read more (1 more)Show less- 1 payment still in progress, oldest 763 days
| UDAIPUR | ₹25.00 L | MEDIUM 65 | |
| 6 | Aaryabhatt Vighyan Chetana Kendra (Science Activity Center) Community Buildings — UDAIPUR(DISTRICT COLLECTOR UDAIPUR_IDA) - ₹1,000,000 against a ₹398,710 median for Community Buildings works in UDAIPUR (151% above, 61 peer works)
- 561 days beyond expected completion
Read more (1 more)Show less- 1 payment still in progress, oldest 763 days
| UDAIPUR | ₹10.00 L | MEDIUM 65 | |
| 7 | HALL NIRMAN KARYA VIDHYA NIKETAN Sec. Shool Jhadol (F) Gram Community Buildings — UDAIPUR(DISTRICT COLLECTOR UDAIPUR_IDA) - ₹1,000,000 against a ₹398,710 median for Community Buildings works in UDAIPUR (151% above, 61 peer works)
- 568 days beyond expected completion
Read more (1 more)Show less- 1 payment still in progress, oldest 763 days
| UDAIPUR | ₹10.00 L | MEDIUM 65 | |
| 8 | Hnad Pumps Installing at Gram Panchayat at Masaron ki ovri A Water — UDAIPUR(DISTRICT COLLECTOR UDAIPUR_IDA) - ₹186,000 against a ₹95,000 median for Water works in UDAIPUR (96% above, 23 peer works)
- 582 days beyond expected completion
Read more (1 more)Show less- 1 payment still in progress, oldest 763 days
| UDAIPUR | ₹1.86 L | MEDIUM 64 | |
| 9 | Vidhan Sabha Shetra Jhadol (F) ke Panchayat Samiti Jhadol me Education — UDAIPUR(DISTRICT COLLECTOR UDAIPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 555 days beyond expected completion
Read more (1 more)Show less- 1 payment still in progress, oldest 763 days
| UDAIPUR | ₹10.00 L | MEDIUM 57 | |
| 10 | Vidhan Sabha Shetra Jhadol (Ph.) ke Panchayat Samiti Phalasi Education — UDAIPUR(DISTRICT COLLECTOR UDAIPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 555 days beyond expected completion
Read more (1 more)Show less- 1 payment still in progress, oldest 763 days
| UDAIPUR | ₹10.00 L | MEDIUM 57 | |
| 11 | Greval Sadak May Returning Wall Nirman Karya Kagra Gram Panc Roads & Paving — Salumbar(DISTRICT COLLECTOR Salumbar_IDA) - ₹1,500,000 against a ₹500,000 median for Roads & Paving works in SALUMBAR (200% above, 21 peer works)
- 572 days beyond expected completion
| SALUMBAR | ₹15.00 L | MEDIUM 55 | |
| 12 | Kuva Nirman Karya Pashupati Aashram Ke pas Kenar Gram Pancha Water — Salumbar(DISTRICT COLLECTOR Salumbar_IDA) - ₹1,000,000 against a ₹95,000 median for Water works in SALUMBAR (953% above, 25 peer works)
- 572 days beyond expected completion
| SALUMBAR | ₹10.00 L | MEDIUM 55 | |
| 13 | Anikat Nirman Karya Kundiya Vela Ganganagar Bedawal Gram Pan Water — Salumbar(DISTRICT COLLECTOR Salumbar_IDA) - ₹500,000 against a ₹95,000 median for Water works in SALUMBAR (426% above, 25 peer works)
- 577 days beyond expected completion
| SALUMBAR | ₹5.00 L | MEDIUM 55 | |
| 14 | 1.Moksh Vahini Krya Kar Chechis Par Body Nirman Karya 1. MAX Equipment & Vehicles — UDAIPUR(DISTRICT COLLECTOR UDAIPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 572 days beyond expected completion
Read more (1 more)Show less- 1 payment still in progress, oldest 763 days
| UDAIPUR | ₹10.84 L | MEDIUM 53 | |
| 15 | Kaksha Kaksh Nirman Karya Govt. Sr. Secoundry School Jolawa Education — UDAIPUR(DISTRICT COLLECTOR UDAIPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 576 days beyond expected completion
Read more (1 more)Show less- 1 payment still in progress, oldest 763 days
| UDAIPUR | ₹10.00 L | MEDIUM 53 | |
| 16 | Prarthana Sthal Par Dom Nirman Karya Govt. Sr/ Sec. School G Education — UDAIPUR(DISTRICT COLLECTOR UDAIPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 576 days beyond expected completion
Read more (1 more)Show less- 1 payment still in progress, oldest 763 days
| UDAIPUR | ₹10.00 L | MEDIUM 53 | |
| 17 | C.C. Road Maya Riterningwall Nirman Karya Govt. Sr. Sec. Sch Roads & Paving — UDAIPUR(DISTRICT COLLECTOR UDAIPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 561 days beyond expected completion
Read more (1 more)Show less- 1 payment still in progress, oldest 763 days
| UDAIPUR | ₹10.00 L | MEDIUM 52 | |
| 18 | C.C. Road May Returnwall Nirman Karya Govt Primary School Bu Roads & Paving — UDAIPUR(DISTRICT COLLECTOR UDAIPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 561 days beyond expected completion
Read more (1 more)Show less- 1 payment still in progress, oldest 763 days
| UDAIPUR | ₹10.00 L | MEDIUM 52 | |
| 19 | Interlocking Tailes Nirman Karya Bansilal/Dhula ke Ghar ke P Roads & Paving — UDAIPUR(DISTRICT COLLECTOR UDAIPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 568 days beyond expected completion
Read more (1 more)Show less- 1 payment still in progress, oldest 763 days
| UDAIPUR | ₹10.00 L | MEDIUM 52 | |
| 20 | Kasturba Matra Mandir Dr Aatma Prakash Bhati Hospital, Dehli Street Lighting — UDAIPUR(DISTRICT COLLECTOR UDAIPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 572 days beyond expected completion
Read more (1 more)Show less- 1 payment still in progress, oldest 763 days
| UDAIPUR | ₹8.96 L | MEDIUM 52 | |
| 21 | Samudayik Bhawan Nirman Karya Gayatri Nohra ke Pass Chovra K Community Buildings — Salumbar(DISTRICT COLLECTOR Salumbar_IDA) - ₹800,000 against a ₹450,000 median for Community Buildings works in SALUMBAR (78% above, 17 peer works)
- 561 days beyond expected completion
| SALUMBAR | ₹8.00 L | MEDIUM 49 | |
| 22 | Samudayik Khula Baramda Nirman Karya Radha Krishna Mandir Ke Community Buildings — Salumbar(DISTRICT COLLECTOR Salumbar_IDA) - ₹800,000 against a ₹450,000 median for Community Buildings works in SALUMBAR (78% above, 17 peer works)
- 577 days beyond expected completion
| SALUMBAR | ₹8.00 L | MEDIUM 49 | |
| 23 | Hand Pumps Installing at Gram Panchyat Kikawat as per List Water — UDAIPUR(DISTRICT COLLECTOR UDAIPUR_IDA) - 582 days beyond expected completion
- 1 payment still in progress, oldest 763 days
| UDAIPUR | ₹93,000 | MEDIUM 48 | |
| 24 | Installing hand pumps ranjit /somraj meena ke ghar ke pass g Water — UDAIPUR(DISTRICT COLLECTOR UDAIPUR_IDA) - 583 days beyond expected completion
- 1 payment still in progress, oldest 763 days
| UDAIPUR | ₹93,000 | MEDIUM 48 | |
| 25 | Vishranti Grah Nirman Karya Shri Hanuman Mandir Ke Pas Vada Religious & Cultural — UDAIPUR(DISTRICT COLLECTOR UDAIPUR_IDA) - 580 days beyond expected completion
- 1 payment still in progress, oldest 763 days
| UDAIPUR | ₹4.80 L | MEDIUM 48 | |