| 1 | Construction of new Multi-Purpose Hall. Community Buildings — CHENNAI(COMMISSIONER MUNCIPAL CORPORATION CHENNAI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 719 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| CHENNAI | ₹26.99 L | MEDIUM 68
delay 25duplication 20cost 19 | |
| 2 | Construction of new Multi-Purpose Hall. Community Buildings — CHENNAI(COMMISSIONER MUNCIPAL CORPORATION CHENNAI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 719 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| CHENNAI | ₹26.99 L | MEDIUM 68
delay 25duplication 20cost 19 | |
| 3 | Construction of a Community Hall. Community Buildings — Kancheepuram(DISTRICT COLLECTOR KANCHEEPURAM_IDA) - ₹4,383,000 against a ₹1,000,000 median for Community Buildings works in KANCHEEPURAM (338% above, 35 peer works)
- 244 days beyond expected completion
Read more (1 more)Show less- 99% similarity with another nearby work
| KANCHEEPURAM | ₹43.83 L | MEDIUM 67
cost 25delay 25duplication 16 | |
| 4 | Providing 1 Nos. Highmast Light. Street Lighting — CHENNAI(COMMISSIONER MUNCIPAL CORPORATION CHENNAI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 665 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| CHENNAI | ₹5.60 L | MEDIUM 59
delay 25duplication 20cost 11 | |
| 5 | Providing 1 Nos Highmast Light. Street Lighting — CHENNAI(COMMISSIONER MUNCIPAL CORPORATION CHENNAI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 665 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| CHENNAI | ₹5.50 L | MEDIUM 59
delay 25duplication 20cost 10 | |
| 6 | Providing 1 Nos Highmast Light. Street Lighting — CHENNAI(COMMISSIONER MUNCIPAL CORPORATION CHENNAI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 665 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| CHENNAI | ₹5.50 L | MEDIUM 59
delay 25duplication 20cost 10 | |
| 7 | Providing 1 Nos Highmast Light. Street Lighting — CHENNAI(COMMISSIONER MUNCIPAL CORPORATION CHENNAI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 665 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| CHENNAI | ₹5.50 L | MEDIUM 59
delay 25duplication 20cost 10 | |
| 8 | Providing 1 Nos. Highmast Light. Street Lighting — CHENNAI(COMMISSIONER MUNCIPAL CORPORATION CHENNAI_IDA) - 665 days beyond expected completion
- 100% similarity with another nearby work
| CHENNAI | ₹3.80 L | MEDIUM 58
delay 25duplication 20cost 9 | |
| 9 | Construction of 2 Classroom buildings (2nd Floor) Education — CHENNAI(COMMISSIONER MUNCIPAL CORPORATION CHENNAI_IDA) - ₹3,700,000 against a ₹1,285,158 median for Education works in CHENNAI (188% above, 107 peer works)
- 665 days beyond expected completion
| CHENNAI | ₹37.00 L | MEDIUM 57 | |
| 10 | Providing 1 Nos. Mini Highmast Light Street Lighting — CHENGALPATTU(District Collector Chengalpattu_IDA) - 665 days beyond expected completion
- 100% similarity with another nearby work
| CHENGALPATTU | ₹4.35 L | MEDIUM 55
delay 25duplication 20cost 9 | |
| 11 | Providing 1 Nos. Highmast Light (16m). Street Lighting — CHENNAI(COMMISSIONER MUNCIPAL CORPORATION CHENNAI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 575 days beyond expected completion
Read more (1 more)Show less- 98% similarity with another nearby work
| CHENNAI | ₹7.42 L | MEDIUM 53
delay 25duplication 13cost 11 | |
| 12 | Construction of Anganwadi Building inside the Adi-Dravidar W Education — CHENNAI(COMMISSIONER MUNCIPAL CORPORATION CHENNAI_IDA) - ₹2,500,000 against a ₹1,285,158 median for Education works in CHENNAI (95% above, 107 peer works)
- 282 days beyond expected completion
| CHENNAI | ₹25.00 L | MEDIUM 52 | |
| 13 | Construction of Kitchen Room for TNHB Girls Higher Scondary Education — THIRUVALLUR(DISTRICT COLLECTOR TIRUVALLUR_IDA) - ₹2,500,000 against a ₹312,500 median for Education works in THIRUVALLUR (700% above, 91 peer works)
- 299 days beyond expected completion
| THIRUVALLUR | ₹25.00 L | MEDIUM 52 | |
| 14 | Construction of a Community Hall. Community Buildings — CHENGALPATTU(District Collector Chengalpattu_IDA) - ₹5,000,000 against a ₹944,806 median for Community Buildings works in CHENGALPATTU (429% above, 52 peer works)
- 188 days beyond expected completion
| CHENGALPATTU | ₹50.00 L | MEDIUM 51 | |
| 15 | Providing 1 Nos. Highmast Light (8m). Street Lighting — CHENNAI(COMMISSIONER MUNCIPAL CORPORATION CHENNAI_IDA) - 575 days beyond expected completion
- 98% similarity with another nearby work
| CHENNAI | ₹1.92 L | MEDIUM 49
delay 25duplication 13cost 7 | |
| 16 | Construction of a Gym at Block No.48, 49 OSR Land Sports — CHENNAI(COMMISSIONER MUNCIPAL CORPORATION CHENNAI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 719 days beyond expected completion
| CHENNAI | ₹29.50 L | MEDIUM 48 | |
| 17 | Construction of Class Room Building for Chennai Corporation Education — CHENNAI(COMMISSIONER MUNCIPAL CORPORATION CHENNAI_IDA) - ₹2,000,000 against a ₹1,285,158 median for Education works in CHENNAI (56% above, 107 peer works)
- 719 days beyond expected completion
| CHENNAI | ₹20.00 L | MEDIUM 47 | |
| 18 | Construction of Class Room Building for Athipattu Government Education — CHENNAI(COMMISSIONER MUNCIPAL CORPORATION CHENNAI_IDA) - ₹2,000,000 against a ₹1,285,158 median for Education works in CHENNAI (56% above, 107 peer works)
- 719 days beyond expected completion
| CHENNAI | ₹20.00 L | MEDIUM 47 | |
| 19 | Providing 1 Nos of Highmast Light (12mts). Street Lighting — CHENNAI(COMMISSIONER MUNCIPAL CORPORATION CHENNAI_IDA) - 151 days beyond expected completion
- 99% similarity with another nearby work
| CHENNAI | ₹5.38 L | MEDIUM 47
delay 21duplication 15cost 6 | |
| 20 | Construction of an Anganwadi Building. Education — Kancheepuram(DISTRICT COLLECTOR KANCHEEPURAM_IDA) - ₹1,725,000 against a ₹250,000 median for Education works in KANCHEEPURAM (590% above, 307 peer works)
- 100% similarity with another nearby work
| KANCHEEPURAM | ₹17.25 L | MEDIUM 45 | |
| 21 | Construction of Anganwadi Building. Education — Kancheepuram(DISTRICT COLLECTOR KANCHEEPURAM_IDA) - ₹1,337,000 against a ₹250,000 median for Education works in KANCHEEPURAM (435% above, 307 peer works)
- 100% similarity with another nearby work
| KANCHEEPURAM | ₹13.37 L | MEDIUM 45 | |
| 22 | Construction of Public Library Building Education — Kancheepuram(DISTRICT COLLECTOR KANCHEEPURAM_IDA) - ₹1,409,656 against a ₹250,000 median for Education works in KANCHEEPURAM (464% above, 307 peer works)
- 100% similarity with another nearby work
| KANCHEEPURAM | ₹14.10 L | MEDIUM 45 | |
| 23 | Construction of a Community Hall Community Buildings — Kancheepuram(DISTRICT COLLECTOR KANCHEEPURAM_IDA) - ₹4,999,501 against a ₹1,000,000 median for Community Buildings works in KANCHEEPURAM (400% above, 35 peer works)
- 100% similarity with another nearby work
| KANCHEEPURAM | ₹50.00 L | MEDIUM 45 | |
| 24 | Construction of a Community Hall Community Buildings — Kancheepuram(DISTRICT COLLECTOR KANCHEEPURAM_IDA) - ₹4,998,986 against a ₹1,000,000 median for Community Buildings works in KANCHEEPURAM (400% above, 35 peer works)
- 100% similarity with another nearby work
| KANCHEEPURAM | ₹49.99 L | MEDIUM 45 | |
| 25 | Construction of an Anganwadi Building. Education — Kancheepuram(DISTRICT COLLECTOR KANCHEEPURAM_IDA) - ₹1,450,000 against a ₹250,000 median for Education works in KANCHEEPURAM (480% above, 307 peer works)
- 100% similarity with another nearby work
| KANCHEEPURAM | ₹14.50 L | MEDIUM 45 | |