| 1 | Construction work of Interlocking Tiles from Main Stand to V Roads & Paving — MUZAFFARNAGAR(DISTRICT MAGISTRATE MUZAFFARNAGAR_IDA) - ₹2,800,000 against a ₹695,000 median for Roads & Paving works in MUZAFFARNAGAR (303% above, 327 peer works)
- 211 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 42 payments still in progress, oldest 686 days
| MUZAFFARNAGAR | ₹28.00 L | HIGH 84
cost 25delay 25duplication 20 | |
| 2 | Construction of Interlocking Tiles and Drain from Main Bus S Roads & Paving — MUZAFFARNAGAR(DISTRICT MAGISTRATE MUZAFFARNAGAR_IDA) - ₹2,499,400 against a ₹695,000 median for Roads & Paving works in MUZAFFARNAGAR (260% above, 327 peer works)
- 395 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 42 payments still in progress, oldest 686 days
| MUZAFFARNAGAR | ₹24.99 L | HIGH 84
cost 25delay 25duplication 20 | |
| 3 | Construction of interlocking tiles on Road and Drain from Ma Roads & Paving — MUZAFFARNAGAR(DISTRICT MAGISTRATE MUZAFFARNAGAR_IDA) - ₹1,370,000 against a ₹695,000 median for Roads & Paving works in MUZAFFARNAGAR (97% above, 327 peer works)
- 610 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 42 payments still in progress, oldest 686 days
| MUZAFFARNAGAR | ₹13.70 L | HIGH 83
delay 25cost 24duplication 20 | |
| 4 | Construction of Building for Dujana Public School Education — GAUTAM BUDDHA NAGAR(DISTRICT MAGISTRATE GAUTAMBUDHNAGAR) - ₹3,500,000 against a ₹798,100 median for Education works in GAUTAM BUDDHA NAGAR (339% above, 72 peer works)
- 567 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 53% delay rate across its projects
| GAUTAM BUDDHA NAGAR | ₹35.00 L | HIGH 78
cost 25delay 25duplication 20 | |
| 5 | Construction of Building for Dujana Public School Education — GAUTAM BUDDHA NAGAR(DISTRICT MAGISTRATE GAUTAMBUDHNAGAR) - ₹3,500,000 against a ₹798,100 median for Education works in GAUTAM BUDDHA NAGAR (339% above, 72 peer works)
- 567 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 53% delay rate across its projects
| GAUTAM BUDDHA NAGAR | ₹35.00 L | HIGH 78
cost 25delay 25duplication 20 | |
| 6 | Construction work of C.C. Road from Kalu's House to Dalel's Roads & Paving — MUZAFFARNAGAR(DISTRICT MAGISTRATE MUZAFFARNAGAR_IDA) - ₹1,197,700 against a ₹695,000 median for Roads & Paving works in MUZAFFARNAGAR (72% above, 327 peer works)
- 265 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 42 payments still in progress, oldest 686 days
| MUZAFFARNAGAR | ₹11.98 L | HIGH 77
delay 25duplication 20cost 18 | |
| 7 | Construction of Classrooms & Laboratory at Gandhi Inter Coll Education — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - ₹2,000,000 against a ₹80,400 median for Education works in PRATAPGARH (2388% above, 216 peer works)
- 339 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 26 payments still in progress, oldest 377 days
| PRATAPGARH | ₹20.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 8 | Installation of Handpumps at Raki, Mustafabad, Narwal, Usman Water — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - ₹508,000 against a ₹50,800 median for Water works in PRATAPGARH (900% above, 445 peer works)
- 342 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 26 payments still in progress, oldest 377 days
| PRATAPGARH | ₹5.08 L | HIGH 77
cost 25delay 25duplication 20 | |
| 9 | Installation of Handpumps at Raki, Mustafabad, Narwal, Usman Water — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - ₹558,800 against a ₹50,800 median for Water works in PRATAPGARH (1000% above, 445 peer works)
- 342 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 26 payments still in progress, oldest 377 days
| PRATAPGARH | ₹5.59 L | HIGH 77
cost 25delay 25duplication 20 | |
| 10 | Installation of Handpumps at Raki, Mustafabad, Narwal, Usman Water — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - ₹406,400 against a ₹50,800 median for Water works in PRATAPGARH (700% above, 445 peer works)
- 342 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 26 payments still in progress, oldest 377 days
| PRATAPGARH | ₹4.06 L | HIGH 77
cost 25delay 25duplication 20 | |
| 11 | Construction of Classrooms & Laboratory at Gandhi Inter Coll Education — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - ₹2,000,000 against a ₹80,400 median for Education works in PRATAPGARH (2388% above, 216 peer works)
- 339 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 176 payments still in progress, oldest 377 days
| PRATAPGARH | ₹20.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 12 | Installation of Handpumps at Raki, Mustafabad, Narwal, Usman Water — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - ₹508,000 against a ₹50,800 median for Water works in PRATAPGARH (900% above, 445 peer works)
- 342 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 176 payments still in progress, oldest 377 days
| PRATAPGARH | ₹5.08 L | HIGH 77
cost 25delay 25duplication 20 | |
| 13 | Installation of Handpumps at Raki, Mustafabad, Narwal, Usman Water — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - ₹558,800 against a ₹50,800 median for Water works in PRATAPGARH (1000% above, 445 peer works)
- 342 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 176 payments still in progress, oldest 377 days
| PRATAPGARH | ₹5.59 L | HIGH 77
cost 25delay 25duplication 20 | |
| 14 | Installation of Handpumps at Raki, Mustafabad, Narwal, Usman Water — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - ₹406,400 against a ₹50,800 median for Water works in PRATAPGARH (700% above, 445 peer works)
- 342 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 176 payments still in progress, oldest 377 days
| PRATAPGARH | ₹4.06 L | HIGH 77
cost 25delay 25duplication 20 | |
| 15 | Construction work of Interlocking Tiles from Main Stand to V Roads & Paving — MUZAFFARNAGAR(DISTRICT MAGISTRATE MUZAFFARNAGAR_IDA) - ₹2,800,000 against a ₹695,000 median for Roads & Paving works in MUZAFFARNAGAR (303% above, 327 peer works)
- 211 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MUZAFFARNAGAR | ₹28.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 16 | Construction of Interlocking Tiles and Drain from Main Bus S Roads & Paving — MUZAFFARNAGAR(DISTRICT MAGISTRATE MUZAFFARNAGAR_IDA) - ₹2,499,400 against a ₹695,000 median for Roads & Paving works in MUZAFFARNAGAR (260% above, 327 peer works)
- 395 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MUZAFFARNAGAR | ₹24.99 L | HIGH 76
cost 25delay 25duplication 20 | |
| 17 | Construction of Library and Two Rooms at Baba Gopi Das Memor Education — AZAMGARH(DISTRICT MAGISTRATE AZAMGARH_IDA) - ₹1,090,000 against a ₹516,000 median for Education works in AZAMGARH (111% above, 63 peer works)
- 596 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| AZAMGARH | ₹10.90 L | HIGH 76
cost 25delay 25duplication 20 | |
| 18 | Construction of Library and Two Rooms at Baba Gopi Das Memor Education — AZAMGARH(DISTRICT MAGISTRATE AZAMGARH_IDA) - ₹1,090,000 against a ₹516,000 median for Education works in AZAMGARH (111% above, 63 peer works)
- 596 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| AZAMGARH | ₹10.90 L | HIGH 76
cost 25delay 25duplication 20 | |
| 19 | Construction of interlocking tiles on Road and Drain from Ma Roads & Paving — MUZAFFARNAGAR(DISTRICT MAGISTRATE MUZAFFARNAGAR_IDA) - ₹1,370,000 against a ₹695,000 median for Roads & Paving works in MUZAFFARNAGAR (97% above, 327 peer works)
- 610 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MUZAFFARNAGAR | ₹13.70 L | HIGH 75
delay 25cost 24duplication 20 | |
| 20 | Construction of interlocking tile works on Road and Drain fr Roads & Paving — MUZAFFARNAGAR(DISTRICT MAGISTRATE MUZAFFARNAGAR_IDA) - ₹1,107,000 against a ₹695,000 median for Roads & Paving works in MUZAFFARNAGAR (59% above, 327 peer works)
- 610 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 42 payments still in progress, oldest 686 days
| MUZAFFARNAGAR | ₹11.07 L | HIGH 74
delay 25duplication 20cost 15 | |
| 21 | Construction of Building at Baba Kamdev Singh Mahavidyalaya, Education — JAUNPUR(DISTRICT MAGISTRATE JAUNPUR_IDA) - ₹2,560,000 against a ₹689,000 median for Education works in JAUNPUR (272% above, 92 peer works)
- 290 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAUNPUR | ₹25.60 L | HIGH 73
cost 25delay 25duplication 20 | |
| 22 | Construction of 2 Nos. Classrooms at Dwarika Das Hari Mahavi Education — JAUNPUR(DISTRICT MAGISTRATE JAUNPUR_IDA) - ₹2,500,000 against a ₹689,000 median for Education works in JAUNPUR (263% above, 92 peer works)
- 373 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAUNPUR | ₹25.00 L | HIGH 73
cost 25delay 25duplication 20 | |
| 23 | Construction of Building at Baba Kamdev Singh Mahavidyalaya, Education — JAUNPUR(DISTRICT MAGISTRATE JAUNPUR_IDA) - ₹2,560,000 against a ₹689,000 median for Education works in JAUNPUR (272% above, 92 peer works)
- 290 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAUNPUR | ₹25.60 L | HIGH 73
cost 25delay 25duplication 20 | |
| 24 | Construction of 2 Nos. Classrooms at Dwarika Das Hari Mahavi Education — JAUNPUR(DISTRICT MAGISTRATE JAUNPUR_IDA) - ₹2,500,000 against a ₹689,000 median for Education works in JAUNPUR (263% above, 92 peer works)
- 373 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAUNPUR | ₹25.00 L | HIGH 73
cost 25delay 25duplication 20 | |
| 25 | Construction work of Interlocking Tiles from Pandit Jaipraka Roads & Paving — MUZAFFARNAGAR(DISTRICT MAGISTRATE MUZAFFARNAGAR_IDA) - ₹1,066,500 against a ₹695,000 median for Roads & Paving works in MUZAFFARNAGAR (53% above, 327 peer works)
- 265 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 42 payments still in progress, oldest 686 days
| MUZAFFARNAGAR | ₹10.67 L | HIGH 72
delay 25duplication 20agency 14 | |