| 1 | Construction of Community hall Community Buildings — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - ₹1,000,000 against a ₹499,000 median for Community Buildings works in CHIKKABALLAPURA (100% above, 56 peer works)
- 600 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| CHIKKABALLAPURA | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 2 | Road Development Roads & Paving — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - ₹1,000,000 against a ₹500,000 median for Roads & Paving works in CHIKKABALLAPURA (100% above, 36 peer works)
- 610 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| CHIKKABALLAPURA | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 3 | Road Development Roads & Paving — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - ₹1,200,000 against a ₹500,000 median for Roads & Paving works in CHIKKABALLAPURA (140% above, 36 peer works)
- 610 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| CHIKKABALLAPURA | ₹12.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 4 | Road Development Roads & Paving — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - ₹900,000 against a ₹500,000 median for Roads & Paving works in CHIKKABALLAPURA (80% above, 36 peer works)
- 610 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| CHIKKABALLAPURA | ₹9.00 L | HIGH 71
delay 25cost 20duplication 20 | |
| 5 | Construction of Bus Stand Community Buildings — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - 633 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| CHIKKABALLAPURA | ₹5.00 L | MEDIUM 60
delay 25duplication 20cost 9 | |
| 6 | CC Road Roads & Paving — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - 633 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| CHIKKABALLAPURA | ₹5.00 L | MEDIUM 60
delay 25duplication 20cost 9 | |
| 7 | CC Road Roads & Paving — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - 633 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| CHIKKABALLAPURA | ₹5.00 L | MEDIUM 60
delay 25duplication 20cost 9 | |
| 8 | CC Road Roads & Paving — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - 633 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| CHIKKABALLAPURA | ₹5.00 L | MEDIUM 60
delay 25duplication 20cost 9 | |
| 9 | Road Development Roads & Paving — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - 610 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| CHIKKABALLAPURA | ₹5.00 L | MEDIUM 59
delay 25duplication 20cost 8 | |
| 10 | Road Development Roads & Paving — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - 610 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| CHIKKABALLAPURA | ₹5.00 L | MEDIUM 59
delay 25duplication 20cost 8 | |
| 11 | Road Development Roads & Paving — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - 610 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| CHIKKABALLAPURA | ₹5.00 L | MEDIUM 59
delay 25duplication 20cost 8 | |
| 12 | Construction of Community Hall Community Buildings — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - 610 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| CHIKKABALLAPURA | ₹5.00 L | MEDIUM 59
delay 25duplication 20cost 8 | |
| 13 | Road Development Roads & Paving — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - 610 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| CHIKKABALLAPURA | ₹5.00 L | MEDIUM 59
delay 25duplication 20cost 8 | |
| 14 | CC Road Roads & Paving — BENGALURU RURAL(DEPUTY COMMISSIONER BANGALORE RURAL SBM URBAN) - 635 days beyond expected completion
- 100% similarity with another nearby work
| BENGALURU RURAL | ₹5.00 L | MEDIUM 57
delay 25duplication 20cost 9 | |
| 15 | road development Roads & Paving — BENGALURU RURAL(DEPUTY COMMISSIONER BANGALORE RURAL SBM URBAN) - 635 days beyond expected completion
- 100% similarity with another nearby work
| BENGALURU RURAL | ₹4.90 L | MEDIUM 57
delay 25duplication 20cost 9 | |
| 16 | Construction of Road and Drain Roads & Paving — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - ₹1,000,000 against a ₹500,000 median for Roads & Paving works in CHIKKABALLAPURA (100% above, 36 peer works)
- 610 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| CHIKKABALLAPURA | ₹10.00 L | MEDIUM 56 | |
| 17 | Construction of first floor for media association Community Buildings — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - ₹1,000,000 against a ₹499,000 median for Community Buildings works in CHIKKABALLAPURA (100% above, 56 peer works)
- 633 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| CHIKKABALLAPURA | ₹10.00 L | MEDIUM 56 | |
| 18 | High Mask Light Street Lighting — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - Completed work has no photographic documentation on record
- ₹498,803 against a ₹250,000 median for Street Lighting works in CHIKKABALLAPURA (100% above, 53 peer works)
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| CHIKKABALLAPURA | ₹4.99 L | MEDIUM 56
cost 25duplication 20agency 6 | |
| 19 | High Mask Light Street Lighting — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - Completed work has no photographic documentation on record
- ₹498,803 against a ₹250,000 median for Street Lighting works in CHIKKABALLAPURA (100% above, 53 peer works)
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| CHIKKABALLAPURA | ₹4.99 L | MEDIUM 56
cost 25duplication 20agency 6 | |
| 20 | High Mask Light Street Lighting — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - Completed work has no photographic documentation on record
- ₹498,500 against a ₹250,000 median for Street Lighting works in CHIKKABALLAPURA (99% above, 53 peer works)
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| CHIKKABALLAPURA | ₹4.99 L | MEDIUM 56
cost 25duplication 20agency 6 | |
| 21 | High mask Light Street Lighting — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) - Completed work has no photographic documentation on record
- ₹496,915 against a ₹250,000 median for Street Lighting works in CHIKKABALLAPURA (99% above, 53 peer works)
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| CHIKKABALLAPURA | ₹4.97 L | MEDIUM 55
cost 25duplication 20agency 6 | |
| 22 | Road Development Roads & Paving — BENGALURU RURAL(DEPUTY COMMISSIONER BANGALORE RURAL SBM URBAN) - 619 days beyond expected completion
- 100% similarity with another nearby work
| BENGALURU RURAL | ₹2.50 L | MEDIUM 55
delay 25duplication 20cost 7 | |
| 23 | Road Development Roads & Paving — BENGALURU RURAL(DEPUTY COMMISSIONER BANGALORE RURAL SBM URBAN) - 619 days beyond expected completion
- 100% similarity with another nearby work
| BENGALURU RURAL | ₹2.50 L | MEDIUM 55
delay 25duplication 20cost 7 | |
| 24 | Road Development Roads & Paving — BENGALURU RURAL(DEPUTY COMMISSIONER BANGALORE RURAL SBM URBAN) - 619 days beyond expected completion
- 100% similarity with another nearby work
| BENGALURU RURAL | ₹2.50 L | MEDIUM 55
delay 25duplication 20cost 7 | |
| 25 | Road Development Roads & Paving — BENGALURU RURAL(DEPUTY COMMISSIONER BANGALORE RURAL SBM URBAN) - 619 days beyond expected completion
- 100% similarity with another nearby work
| BENGALURU RURAL | ₹2.50 L | MEDIUM 55
delay 25duplication 20cost 7 | |