| 1 | MARUTI SABHA BHAVAN Community Buildings — HAVERI(DEPUTY COMMISSIONER HAVERI_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in HAVERI (100% above, 155 peer works)
- 191 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 56% of this agency's ₹59,687,756 spend went to one vendor (Bommai Zilla Nirmithi Kendra), across 23 vendors and 185 transactions
| HAVERI | ₹10.00 L | HIGH 78
cost 25delay 25duplication 20 | |
| 2 | VEERABHADRESHWAR SABHA BHAVAN Community Buildings — HAVERI(DEPUTY COMMISSIONER HAVERI_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in HAVERI (100% above, 155 peer works)
- 147 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 56% of this agency's ₹59,687,756 spend went to one vendor (Bommai Zilla Nirmithi Kendra), across 23 vendors and 185 transactions
| HAVERI | ₹10.00 L | HIGH 73
cost 25delay 20duplication 20 | |
| 3 | KALMESHWAR SABHA BHAVAN Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - 190 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹5.00 L | MEDIUM 67
delay 25duplication 20agency 15 | |
| 4 | KALMESHWAR SABHA BHAVAN Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - 191 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹5.00 L | MEDIUM 67
delay 25duplication 20agency 15 | |
| 5 | KALMESHWAR SABHA BHAVAN Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - 147 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹5.00 L | MEDIUM 61
delay 20duplication 20agency 15 | |
| 6 | VEERABHADRESHWAR SABHA BHAVAN Community Buildings — HAVERI(DEPUTY COMMISSIONER HAVERI_IDA) - 208 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 56% of this agency's ₹59,687,756 spend went to one vendor (Bommai Zilla Nirmithi Kendra), across 23 vendors and 185 transactions
| HAVERI | ₹5.00 L | MEDIUM 60
delay 25duplication 20agency 8 | |
| 7 | BASAVESHWAR SABHA BHAVAN Community Buildings — HAVERI(DEPUTY COMMISSIONER HAVERI_IDA) - 190 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 56% of this agency's ₹59,687,756 spend went to one vendor (Bommai Zilla Nirmithi Kendra), across 23 vendors and 185 transactions
| HAVERI | ₹5.00 L | MEDIUM 59
delay 25duplication 20agency 8 | |
| 8 | MARUTI SABHA BHAVAN Community Buildings — HAVERI(DEPUTY COMMISSIONER HAVERI_IDA) - 190 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 56% of this agency's ₹59,687,756 spend went to one vendor (Bommai Zilla Nirmithi Kendra), across 23 vendors and 185 transactions
| HAVERI | ₹5.00 L | MEDIUM 59
delay 25duplication 20agency 8 | |
| 9 | VEERABHADRESHWAR SABHA BHAVAN Community Buildings — HAVERI(DEPUTY COMMISSIONER HAVERI_IDA) - 191 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 56% of this agency's ₹59,687,756 spend went to one vendor (Bommai Zilla Nirmithi Kendra), across 23 vendors and 185 transactions
| HAVERI | ₹5.00 L | MEDIUM 59
delay 25duplication 20agency 8 | |
| 10 | MARUTI SABHA BHAVAN Community Buildings — HAVERI(DEPUTY COMMISSIONER HAVERI_IDA) - 157 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 56% of this agency's ₹59,687,756 spend went to one vendor (Bommai Zilla Nirmithi Kendra), across 23 vendors and 185 transactions
| HAVERI | ₹50,000 | MEDIUM 58
delay 22duplication 20cost 8 | |
| 11 | BASAVESHWAR SABHA BHAVAN Community Buildings — HAVERI(DEPUTY COMMISSIONER HAVERI_IDA) - 157 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 56% of this agency's ₹59,687,756 spend went to one vendor (Bommai Zilla Nirmithi Kendra), across 23 vendors and 185 transactions
| HAVERI | ₹5.00 L | MEDIUM 55
delay 22duplication 20agency 8 | |
| 12 | BASAVESHWAR SABHA BHAVAN Community Buildings — HAVERI(DEPUTY COMMISSIONER HAVERI_IDA) - 147 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 56% of this agency's ₹59,687,756 spend went to one vendor (Bommai Zilla Nirmithi Kendra), across 23 vendors and 185 transactions
| HAVERI | ₹5.00 L | MEDIUM 54
delay 20duplication 20agency 8 | |
| 13 | MAHANTA SHIVACHARYA MATHAD ABHIVRUDDI SABHA BHAVAN Community Buildings — HAVERI(DEPUTY COMMISSIONER HAVERI_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in HAVERI (100% above, 155 peer works)
- 147 days beyond expected completion
Read more (1 more)Show less- 56% of this agency's ₹59,687,756 spend went to one vendor (Bommai Zilla Nirmithi Kendra), across 23 vendors and 185 transactions
| HAVERI | ₹10.00 L | MEDIUM 53 | |
| 14 | CONSTRUCTION OF CONCRETE ROAD Roads & Paving — GADAG(Deputy Commsioner Gadag_ida) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 191 days beyond expected completion
Read more (1 more)Show less- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹15.00 L | MEDIUM 52 | |
| 15 | KUMARSWAMI SABHA BHAVAN AVARANADALLI BOREWELL RIGGING MOTUR Water — HAVERI(DEPUTY COMMISSIONER HAVERI_IDA) - ₹500,000 against a ₹199,475 median for Water works in HAVERI (151% above, 21 peer works)
- 129 days beyond expected completion
Read more (1 more)Show less- 56% of this agency's ₹59,687,756 spend went to one vendor (Bommai Zilla Nirmithi Kendra), across 23 vendors and 185 transactions
| HAVERI | ₹5.00 L | MEDIUM 50 | |
| 16 | MANJUNATH SABHA BHAVAN Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - 208 days beyond expected completion
- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹5.00 L | MEDIUM 47 | |
| 17 | HINGULAMBIKA SABHA BHAVAN Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - 208 days beyond expected completion
- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹5.00 L | MEDIUM 47 | |
| 18 | MADIWAL MACHAYYA SABHA BHAVAN Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - 208 days beyond expected completion
- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹5.00 L | MEDIUM 47 | |
| 19 | MARUTI SABHA BHAVAN Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - 190 days beyond expected completion
- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹5.00 L | MEDIUM 47 | |
| 20 | VEERABHADRESHWAR SABHA BHAVAN Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - 190 days beyond expected completion
- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹5.00 L | MEDIUM 47 | |
| 21 | NANDI BASAVESHWAR SEVA SAMITI SABHA BHAVAN Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - 191 days beyond expected completion
- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹5.00 L | MEDIUM 47 | |
| 22 | BEERALINGESHWAR SABHA BHAVAN Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - 191 days beyond expected completion
- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹5.00 L | MEDIUM 47 | |
| 23 | BISEROTTI VEERABHADRESHWAR SABHA BHAVAN Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - 191 days beyond expected completion
- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹5.00 L | MEDIUM 47 | |
| 24 | GRAMADEVI DYAMAVVA DEVI SABHA BHAVAN Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - 191 days beyond expected completion
- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹5.00 L | MEDIUM 47 | |
| 25 | SEVALAL SABHA BHAVAN Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - 191 days beyond expected completion
- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹5.00 L | MEDIUM 47 | |