| 1 | Construction of Gully control at No 2 Polashguri village und Boundary & Protection — CHIRANG(Deputy Commissioner Chirang_IDA) - ₹2,000,000 against a ₹1,000,000 median for Boundary & Protection works in CHIRANG (100% above, 25 peer works)
- 241 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 65% delay rate across its projects
| CHIRANG | ₹20.00 L | HIGH 80
cost 25delay 25duplication 20 | |
| 2 | Construction of New Nilibary Community Hall at New Nilibary Community Buildings — CHIRANG(Deputy Commissioner Chirang_IDA) - ₹2,000,000 against a ₹1,000,000 median for Community Buildings works in CHIRANG (100% above, 52 peer works)
- 332 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 65% delay rate across its projects
| CHIRANG | ₹20.00 L | HIGH 80
cost 25delay 25duplication 20 | |
| 3 | Construction of road at Shiv nagar, Dangtal Bazar under Dang Roads & Paving — CHIRANG(Deputy Commissioner Chirang_IDA) - ₹2,000,000 against a ₹800,000 median for Roads & Paving works in CHIRANG (150% above, 144 peer works)
- 346 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 65% delay rate across its projects
| CHIRANG | ₹20.00 L | HIGH 80
cost 25delay 25duplication 20 | |
| 4 | construction of Bridge at Dawkhanwgwr-2 over Fwilamari dong Roads & Paving — CHIRANG(Deputy Commissioner Chirang_IDA) - ₹2,200,000 against a ₹800,000 median for Roads & Paving works in CHIRANG (175% above, 144 peer works)
- 351 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 65% delay rate across its projects
| CHIRANG | ₹22.00 L | HIGH 80
cost 25delay 25duplication 20 | |
| 5 | Construction of Crematorium or structure and approach road o Roads & Paving — CHIRANG(Deputy Commissioner Chirang_IDA) - ₹2,000,000 against a ₹800,000 median for Roads & Paving works in CHIRANG (150% above, 144 peer works)
- 448 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 65% delay rate across its projects
| CHIRANG | ₹20.00 L | HIGH 80
cost 25delay 25duplication 20 | |
| 6 | Construction of Building for multi-gym near ABSU office at U Sports — CHIRANG(Deputy Commissioner Chirang_IDA) - ₹2,500,000 against a ₹1,000,000 median for Sports works in CHIRANG (150% above, 8 peer works)
- 448 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 65% delay rate across its projects
| CHIRANG | ₹25.00 L | HIGH 80
cost 25delay 25duplication 20 | |
| 7 | construction of road from Kukurmari Market to Namghor, ward Roads & Paving — CHIRANG(Deputy Commissioner Chirang_IDA) - ₹3,000,000 against a ₹800,000 median for Roads & Paving works in CHIRANG (275% above, 144 peer works)
- 450 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 65% delay rate across its projects
| CHIRANG | ₹30.00 L | HIGH 80
cost 25delay 25duplication 20 | |
| 8 | construction of RCC Box Culvert at Anthaiguri(Silguri) villa Roads & Paving — CHIRANG(Deputy Commissioner Chirang_IDA) - ₹1,800,000 against a ₹800,000 median for Roads & Paving works in CHIRANG (125% above, 144 peer works)
- 451 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 65% delay rate across its projects
| CHIRANG | ₹18.00 L | HIGH 80
cost 25delay 25duplication 20 | |
| 9 | Renovation of administrative Building of Bodosa High School Education — CHIRANG(Deputy Commissioner Chirang_IDA) - ₹3,500,000 against a ₹1,000,000 median for Education works in CHIRANG (250% above, 46 peer works)
- 451 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 65% delay rate across its projects
| CHIRANG | ₹35.00 L | HIGH 80
cost 25delay 25duplication 20 | |
| 10 | constructionn of Kujia River erosion protection at middle K Boundary & Protection — CHIRANG(Deputy Commissioner Chirang_IDA) - ₹2,000,000 against a ₹1,000,000 median for Boundary & Protection works in CHIRANG (100% above, 25 peer works)
- 451 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 65% delay rate across its projects
| CHIRANG | ₹20.00 L | HIGH 80
cost 25delay 25duplication 20 | |
| 11 | Construction of Gully control at No 2 Polashguri village und Boundary & Protection — CHIRANG(Deputy Commissioner Chirang_IDA) - ₹2,000,000 against a ₹1,000,000 median for Boundary & Protection works in CHIRANG (100% above, 25 peer works)
- 241 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 65% delay rate across its projects
| CHIRANG | ₹20.00 L | HIGH 80
cost 25delay 25duplication 20 | |
| 12 | Construction of New Nilibary Community Hall at New Nilibary Community Buildings — CHIRANG(Deputy Commissioner Chirang_IDA) - ₹2,000,000 against a ₹1,000,000 median for Community Buildings works in CHIRANG (100% above, 52 peer works)
- 332 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 65% delay rate across its projects
| CHIRANG | ₹20.00 L | HIGH 80
cost 25delay 25duplication 20 | |
| 13 | Construction of road at Shiv nagar, Dangtal Bazar under Dang Roads & Paving — CHIRANG(Deputy Commissioner Chirang_IDA) - ₹2,000,000 against a ₹800,000 median for Roads & Paving works in CHIRANG (150% above, 144 peer works)
- 346 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 65% delay rate across its projects
| CHIRANG | ₹20.00 L | HIGH 80
cost 25delay 25duplication 20 | |
| 14 | construction of Bridge at Dawkhanwgwr-2 over Fwilamari dong Roads & Paving — CHIRANG(Deputy Commissioner Chirang_IDA) - ₹2,200,000 against a ₹800,000 median for Roads & Paving works in CHIRANG (175% above, 144 peer works)
- 351 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 65% delay rate across its projects
| CHIRANG | ₹22.00 L | HIGH 80
cost 25delay 25duplication 20 | |
| 15 | Construction of Crematorium or structure and approach road o Roads & Paving — CHIRANG(Deputy Commissioner Chirang_IDA) - ₹2,000,000 against a ₹800,000 median for Roads & Paving works in CHIRANG (150% above, 144 peer works)
- 448 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 65% delay rate across its projects
| CHIRANG | ₹20.00 L | HIGH 80
cost 25delay 25duplication 20 | |
| 16 | Construction of Building for multi-gym near ABSU office at U Sports — CHIRANG(Deputy Commissioner Chirang_IDA) - ₹2,500,000 against a ₹1,000,000 median for Sports works in CHIRANG (150% above, 8 peer works)
- 448 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 65% delay rate across its projects
| CHIRANG | ₹25.00 L | HIGH 80
cost 25delay 25duplication 20 | |
| 17 | construction of road from Kukurmari Market to Namghor, ward Roads & Paving — CHIRANG(Deputy Commissioner Chirang_IDA) - ₹3,000,000 against a ₹800,000 median for Roads & Paving works in CHIRANG (275% above, 144 peer works)
- 450 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 65% delay rate across its projects
| CHIRANG | ₹30.00 L | HIGH 80
cost 25delay 25duplication 20 | |
| 18 | construction of RCC Box Culvert at Anthaiguri(Silguri) villa Roads & Paving — CHIRANG(Deputy Commissioner Chirang_IDA) - ₹1,800,000 against a ₹800,000 median for Roads & Paving works in CHIRANG (125% above, 144 peer works)
- 451 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 65% delay rate across its projects
| CHIRANG | ₹18.00 L | HIGH 80
cost 25delay 25duplication 20 | |
| 19 | Renovation of administrative Building of Bodosa High School Education — CHIRANG(Deputy Commissioner Chirang_IDA) - ₹3,500,000 against a ₹1,000,000 median for Education works in CHIRANG (250% above, 46 peer works)
- 451 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 65% delay rate across its projects
| CHIRANG | ₹35.00 L | HIGH 80
cost 25delay 25duplication 20 | |
| 20 | constructionn of Kujia River erosion protection at middle K Boundary & Protection — CHIRANG(Deputy Commissioner Chirang_IDA) - ₹2,000,000 against a ₹1,000,000 median for Boundary & Protection works in CHIRANG (100% above, 25 peer works)
- 451 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 65% delay rate across its projects
| CHIRANG | ₹20.00 L | HIGH 80
cost 25delay 25duplication 20 | |
| 21 | Construction of Road from Natunbasti to Ahom pathar via to d Roads & Paving — BARPETA(DEPUTY COMMISSIONER BARPETA 1) - ₹2,000,000 against a ₹500,000 median for Roads & Paving works in BARPETA (300% above, 143 peer works)
- 365 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 50% delay rate across its projects
| BARPETA | ₹20.00 L | HIGH 78
cost 25delay 25duplication 20 | |
| 22 | Construction of road from PWD road to Prodip Das house near Roads & Paving — BARPETA(DEPUTY COMMISSIONER BARPETA 1) - ₹1,200,000 against a ₹500,000 median for Roads & Paving works in BARPETA (140% above, 143 peer works)
- 450 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 50% delay rate across its projects
| BARPETA | ₹12.00 L | HIGH 78
cost 25delay 25duplication 20 | |
| 23 | Construction of Road from Natunbasti to Ahom pathar via to d Roads & Paving — BARPETA(DEPUTY COMMISSIONER BARPETA 1) - ₹2,000,000 against a ₹500,000 median for Roads & Paving works in BARPETA (300% above, 143 peer works)
- 365 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 50% delay rate across its projects
| BARPETA | ₹20.00 L | HIGH 78
cost 25delay 25duplication 20 | |
| 24 | Construction of road from PWD road to Prodip Das house near Roads & Paving — BARPETA(DEPUTY COMMISSIONER BARPETA 1) - ₹1,200,000 against a ₹500,000 median for Roads & Paving works in BARPETA (140% above, 143 peer works)
- 450 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 50% delay rate across its projects
| BARPETA | ₹12.00 L | HIGH 78
cost 25delay 25duplication 20 | |
| 25 | Construction of road at Amguri No.1 village under Dangtal VC Roads & Paving — CHIRANG(Deputy Commissioner Chirang_IDA) - ₹1,500,000 against a ₹800,000 median for Roads & Paving works in CHIRANG (88% above, 144 peer works)
- 448 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 65% delay rate across its projects
| CHIRANG | ₹15.00 L | HIGH 77
delay 25cost 22duplication 20 | |