| 1 | Construction of shed near Durga temple located in village Lo Community Buildings — KODERMA(DEPUTY COMMISSIONER KODARMA_IDA) - 189 days beyond expected completion
- 99% similarity with another nearby work
Read more (1 more)Show less- 88% of this agency's ₹18,356,889 spend went to one vendor (JE SATYENDRA KUMAR), across 3 vendors and 59 transactions
| KODERMA | ₹2.50 L | MEDIUM 64
delay 25duplication 17agency 15 | |
| 2 | Construction of 100 ft x 12 ft Open Sitting Gallery Stand in Education — GIRIDIH(Deputy Commissioner Giridh_IDA) - ₹900,000 against a ₹340,000 median for Education works in GIRIDIH (165% above, 37 peer works)
- 567 days beyond expected completion
Read more (1 more)Show less- 57% of this agency's ₹126,197,671 spend went to one vendor (Executive engineer), across 2 vendors and 380 transactions
| GIRIDIH | ₹9.00 L | MEDIUM 62 | |
| 3 | Construction of Room/Community Hall at Kushwaha Hostel , sit Education — GIRIDIH(Deputy Commissioner Giridh_IDA) - ₹800,000 against a ₹340,000 median for Education works in GIRIDIH (135% above, 37 peer works)
- 580 days beyond expected completion
Read more (1 more)Show less- 57% of this agency's ₹126,197,671 spend went to one vendor (Executive engineer), across 2 vendors and 380 transactions
| GIRIDIH | ₹8.00 L | MEDIUM 62 | |
| 4 | Construction of room/hall in Langta Baba College, Jamua, Jam Education — GIRIDIH(Deputy Commissioner Giridh_IDA) - ₹800,000 against a ₹340,000 median for Education works in GIRIDIH (135% above, 37 peer works)
- 656 days beyond expected completion
Read more (1 more)Show less- 57% of this agency's ₹126,197,671 spend went to one vendor (Executive engineer), across 2 vendors and 380 transactions
| GIRIDIH | ₹8.00 L | MEDIUM 62 | |
| 5 | Construction of Stairs at the eastern end of Manjhila Dohar Water — KODERMA(DEPUTY COMMISSIONER KODARMA_IDA) - 180 days beyond expected completion
- 99% similarity with another nearby work
Read more (1 more)Show less- 88% of this agency's ₹18,356,889 spend went to one vendor (JE SATYENDRA KUMAR), across 3 vendors and 59 transactions
| KODERMA | ₹3.00 L | MEDIUM 62
delay 25duplication 15agency 15 | |
| 6 | Construction of Stairs at the western end of Manjhila Dohar Water — KODERMA(DEPUTY COMMISSIONER KODARMA_IDA) - 180 days beyond expected completion
- 99% similarity with another nearby work
Read more (1 more)Show less- 88% of this agency's ₹18,356,889 spend went to one vendor (JE SATYENDRA KUMAR), across 3 vendors and 59 transactions
| KODERMA | ₹3.00 L | MEDIUM 62
delay 25duplication 15agency 15 | |
| 7 | Construction of five feet high and 21 x 21 feet saluting pla Community Buildings — KODERMA(DEPUTY COMMISSIONER KODARMA_IDA) - ₹800,000 against a ₹300,000 median for Community Buildings works in KODERMA (167% above, 38 peer works)
- 567 days beyond expected completion
Read more (1 more)Show less- 63% of this agency's ₹19,120,071 spend went to one vendor (JE SATYENDRA KUMAR), across 5 vendors and 72 transactions
| KODERMA | ₹8.00 L | MEDIUM 61 | |
| 8 | Construction of Two shed in vendor market located at Domchan Community Buildings — KODERMA(DEPUTY COMMISSIONER KODARMA_IDA) - ₹1,400,000 against a ₹300,000 median for Community Buildings works in KODERMA (367% above, 38 peer works)
- 567 days beyond expected completion
Read more (1 more)Show less- 63% of this agency's ₹19,120,071 spend went to one vendor (JE SATYENDRA KUMAR), across 5 vendors and 72 transactions
| KODERMA | ₹14.00 L | MEDIUM 61 | |
| 9 | Construction of two rooms, staircase and verandah at khata n Community Buildings — KODERMA(DEPUTY COMMISSIONER KODARMA_IDA) - ₹800,000 against a ₹300,000 median for Community Buildings works in KODERMA (167% above, 38 peer works)
- 656 days beyond expected completion
Read more (1 more)Show less- 63% of this agency's ₹19,120,071 spend went to one vendor (JE SATYENDRA KUMAR), across 5 vendors and 72 transactions
| KODERMA | ₹8.00 L | MEDIUM 61 | |
| 10 | Construction of 70 ft x 12 ft Open Sitting Gallery Stand in Education — GIRIDIH(Deputy Commissioner Giridh_IDA) - ₹650,000 against a ₹340,000 median for Education works in GIRIDIH (91% above, 37 peer works)
- 567 days beyond expected completion
Read more (1 more)Show less- 57% of this agency's ₹126,197,671 spend went to one vendor (Executive engineer), across 2 vendors and 380 transactions
| GIRIDIH | ₹6.50 L | MEDIUM 60 | |
| 11 | Construction of PCC road from old health sub-centre located Roads & Paving — KODERMA(DEPUTY COMMISSIONER KODARMA_IDA) - ₹500,000 against a ₹299,932 median for Roads & Paving works in KODERMA (67% above, 112 peer works)
- 180 days beyond expected completion
Read more (1 more)Show less- 88% of this agency's ₹18,356,889 spend went to one vendor (JE SATYENDRA KUMAR), across 3 vendors and 59 transactions
| KODERMA | ₹5.00 L | MEDIUM 57 | |
| 12 | onstruction of solar powered water tank in Mariampur Virhor Water — KODERMA(DEPUTY COMMISSIONER KODARMA_IDA) - ₹450,000 against a ₹250,000 median for Water works in KODERMA (80% above, 27 peer works)
- 567 days beyond expected completion
Read more (1 more)Show less- 63% of this agency's ₹19,120,071 spend went to one vendor (JE SATYENDRA KUMAR), across 5 vendors and 72 transactions
| KODERMA | ₹4.50 L | MEDIUM 56 | |
| 13 | Construction of solar powered water tank in Dumariyatand of Water — KODERMA(DEPUTY COMMISSIONER KODARMA_IDA) - ₹450,000 against a ₹250,000 median for Water works in KODERMA (80% above, 27 peer works)
- 567 days beyond expected completion
Read more (1 more)Show less- 63% of this agency's ₹19,120,071 spend went to one vendor (JE SATYENDRA KUMAR), across 5 vendors and 72 transactions
| KODERMA | ₹4.50 L | MEDIUM 56 | |
| 14 | Construction of well on Khata No. 26, Plot No. 881, next to Water — KODERMA(DEPUTY COMMISSIONER KODARMA_IDA) - ₹450,000 against a ₹250,000 median for Water works in KODERMA (80% above, 27 peer works)
- 152 days beyond expected completion
Read more (1 more)Show less- 88% of this agency's ₹18,356,889 spend went to one vendor (JE SATYENDRA KUMAR), across 3 vendors and 59 transactions
| KODERMA | ₹4.50 L | MEDIUM 56 | |
| 15 | Construction of stairs in the river located in village Brind Other — KODERMA(DEPUTY COMMISSIONER KODARMA_IDA) - ₹400,000 against a ₹250,000 median for Other works in KODERMA (60% above, 9 peer works)
- 189 days beyond expected completion
Read more (1 more)Show less- 88% of this agency's ₹18,356,889 spend went to one vendor (JE SATYENDRA KUMAR), across 3 vendors and 59 transactions
| KODERMA | ₹4.00 L | MEDIUM 55 | |
| 16 | Construction of pavers block path from Mahendra Pandey's hou Roads & Paving — GIRIDIH(Deputy Commissioner Giridh_IDA) - 687 days beyond expected completion
- 57% of this agency's ₹126,197,671 spend went to one vendor (Executive engineer), across 2 vendors and 380 transactions
| GIRIDIH | ₹2.50 L | MEDIUM 53 | |
| 17 | Construction of boundary wall of Community hall near Saraswa Community Buildings — KODERMA(DEPUTY COMMISSIONER KODARMA_IDA) - ₹500,000 against a ₹300,000 median for Community Buildings works in KODERMA (67% above, 38 peer works)
- 590 days beyond expected completion
Read more (1 more)Show less- 63% of this agency's ₹19,120,071 spend went to one vendor (JE SATYENDRA KUMAR), across 5 vendors and 72 transactions
| KODERMA | ₹5.00 L | MEDIUM 53 | |
| 18 | Construction of 100 ft x 12 ft Open Sitting Gallery Stand in Sports — HAZARIBAGH(DEPUTY COMMISSIONER HAZARIBAGH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 567 days beyond expected completion
Read more (1 more)Show less- 100% of this agency's ₹39,899,950 spend went to one vendor (RAJ KUMAR SAGAR), across 1 vendor and 97 transactions
| HAZARIBAGH | ₹9.00 L | MEDIUM 52 | |
| 19 | Construction of a shed in the fair ground located on Bajrang Roads & Paving — HAZARIBAGH(DEPUTY COMMISSIONER HAZARIBAGH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 751 days beyond expected completion
Read more (1 more)Show less- 100% of this agency's ₹39,899,950 spend went to one vendor (RAJ KUMAR SAGAR), across 1 vendor and 97 transactions
| HAZARIBAGH | ₹2.50 L | MEDIUM 51 | |
| 20 | Installation of two Nos Deep borings in Police Line Chandwar Water — KODERMA(DEPUTY COMMISSIONER KODARMA_IDA) - ₹400,000 against a ₹250,000 median for Water works in KODERMA (60% above, 27 peer works)
- 567 days beyond expected completion
Read more (1 more)Show less- 63% of this agency's ₹19,120,071 spend went to one vendor (JE SATYENDRA KUMAR), across 5 vendors and 72 transactions
| KODERMA | ₹4.00 L | MEDIUM 51 | |
| 21 | Construction of Computer room at khata no. 201 ,444 Barganda Equipment & Vehicles — GIRIDIH(Deputy Commissioner Giridh_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 568 days beyond expected completion
Read more (1 more)Show less- 57% of this agency's ₹126,197,671 spend went to one vendor (Executive engineer), across 2 vendors and 380 transactions
| GIRIDIH | ₹12.00 L | MEDIUM 50 | |
| 22 | Construction of community building near Shiva temple Baba Dh Religious & Cultural — KODERMA(DEPUTY COMMISSIONER KODARMA_IDA) - ₹500,000 against a ₹250,000 median for Religious & Cultural works in KODERMA (100% above, 10 peer works)
- 73 days beyond expected completion
Read more (1 more)Show less- 88% of this agency's ₹18,356,889 spend went to one vendor (JE SATYENDRA KUMAR), across 3 vendors and 59 transactions
| KODERMA | ₹5.00 L | MEDIUM 50 | |
| 23 | Construction of community hall in Devpahari village of Nekpu Community Buildings — GIRIDIH(Deputy Commissioner Giridh_IDA) - ₹500,000 against a ₹300,000 median for Community Buildings works in GIRIDIH (67% above, 90 peer works)
- 140 days beyond expected completion
Read more (1 more)Show less- 65% of this agency's ₹110,464,562 spend went to one vendor (Executive engineer), across 2 vendors and 335 transactions
| GIRIDIH | ₹5.00 L | MEDIUM 49 | |
| 24 | Construction of PCC road from Panchayat Luppi village Lodhra Roads & Paving — GIRIDIH(Deputy Commissioner Giridh_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 757 days beyond expected completion
Read more (1 more)Show less- 57% of this agency's ₹126,197,671 spend went to one vendor (Executive engineer), across 2 vendors and 380 transactions
| GIRIDIH | ₹2.50 L | MEDIUM 49 | |
| 25 | Construction of Stairs in Satpinda pond located in Panchayat Water — GIRIDIH(Deputy Commissioner Giridh_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 757 days beyond expected completion
Read more (1 more)Show less- 57% of this agency's ₹126,197,671 spend went to one vendor (Executive engineer), across 2 vendors and 380 transactions
| GIRIDIH | ₹2.50 L | MEDIUM 49 | |