| 1 | Construction of Dharamshala Religious & Cultural — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - ₹500,000 against a ₹200,000 median for Religious & Cultural works in KAPURTHALA (150% above, 17 peer works)
- 804 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹5.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 2 | Construction of sports stadium Sports — HOSHIARPUR(DEPUTY COMMISSIONER HOSHIARPUR_IDA) - ₹500,000 against a ₹200,000 median for Sports works in HOSHIARPUR (150% above, 116 peer works)
- 792 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| HOSHIARPUR | ₹5.00 L | HIGH 72
cost 25delay 25duplication 20 | |
| 3 | Construction of Shamshanghat Religious & Cultural — HOSHIARPUR(DEPUTY COMMISSIONER HOSHIARPUR_IDA) - ₹400,000 against a ₹200,000 median for Religious & Cultural works in HOSHIARPUR (100% above, 81 peer works)
- 797 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| HOSHIARPUR | ₹4.00 L | HIGH 72
cost 25delay 25duplication 20 | |
| 4 | Development of sports stadium Sports — HOSHIARPUR(DEPUTY COMMISSIONER HOSHIARPUR_IDA) - ₹500,000 against a ₹200,000 median for Sports works in HOSHIARPUR (150% above, 116 peer works)
- 804 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| HOSHIARPUR | ₹5.00 L | HIGH 72
cost 25delay 25duplication 20 | |
| 5 | Construction of street Roads & Paving — HOSHIARPUR(DEPUTY COMMISSIONER HOSHIARPUR_IDA) - ₹350,000 against a ₹200,000 median for Roads & Paving works in HOSHIARPUR (75% above, 146 peer works)
- 804 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| HOSHIARPUR | ₹3.50 L | MEDIUM 65
delay 25duplication 20cost 19 | |
| 6 | Construction of drainage system Drainage & Sanitation — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 797 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹1.50 L | MEDIUM 64
delay 25duplication 20cost 13 | |
| 7 | Construction of shamshan ghat Religious & Cultural — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 792 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹1.50 L | MEDIUM 64
delay 25duplication 20cost 13 | |
| 8 | Construction of water drainage system Water — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 797 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹5.00 L | MEDIUM 63
delay 25duplication 20cost 13 | |
| 9 | Construction of street, drains are also to be constructed al Drainage & Sanitation — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 800 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹2.00 L | MEDIUM 63
delay 25duplication 20cost 13 | |
| 10 | Construction of street, drains are also to be constructed al Drainage & Sanitation — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 800 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹2.00 L | MEDIUM 63
delay 25duplication 20cost 13 | |
| 11 | Construction of street, drains are also to be constructed al Drainage & Sanitation — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 800 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹2.00 L | MEDIUM 63
delay 25duplication 20cost 13 | |
| 12 | Construction of community hall Community Buildings — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 797 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹2.50 L | MEDIUM 63
delay 25duplication 20cost 13 | |
| 13 | Construction of drainage system Drainage & Sanitation — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 792 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹2.00 L | MEDIUM 63
delay 25duplication 20cost 13 | |
| 14 | Construction of shamshan ghat Religious & Cultural — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 792 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹2.00 L | MEDIUM 63
delay 25duplication 20cost 13 | |
| 15 | Construction of Community Hall Community Buildings — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 804 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹3.00 L | MEDIUM 63
delay 25duplication 20cost 13 | |
| 16 | Construction of SC Dharmshala Community Buildings — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 769 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹2.50 L | MEDIUM 62
delay 25duplication 20cost 12 | |
| 17 | Construction of Street, drains also to be constructed alongw Drainage & Sanitation — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 804 days beyond expected completion
Read more (1 more)Show less- 99% similarity with another nearby work
| KAPURTHALA | ₹2.00 L | MEDIUM 62
delay 25duplication 18cost 13 | |
| 18 | Construction of street, drains are also to be constructed al Drainage & Sanitation — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 800 days beyond expected completion
Read more (1 more)Show less- 99% similarity with another nearby work
| KAPURTHALA | ₹2.00 L | MEDIUM 60
delay 25duplication 16cost 13 | |
| 19 | Installation of solar lights Street Lighting — HOSHIARPUR(DEPUTY COMMISSIONER HOSHIARPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 792 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| HOSHIARPUR | ₹1.50 L | MEDIUM 60
delay 25duplication 20cost 13 | |
| 20 | Construction of Harijan Dharamshala Religious & Cultural — HOSHIARPUR(DEPUTY COMMISSIONER HOSHIARPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 797 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| HOSHIARPUR | ₹2.00 L | MEDIUM 59
delay 25duplication 20cost 13 | |
| 21 | Construction of Dr BR Ambedkar Bhawan Community Buildings — HOSHIARPUR(DEPUTY COMMISSIONER HOSHIARPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 769 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| HOSHIARPUR | ₹1.50 L | MEDIUM 59
delay 25duplication 20cost 13 | |
| 22 | Installation of Solar Lights Street Lighting — HOSHIARPUR(DEPUTY COMMISSIONER HOSHIARPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 749 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| HOSHIARPUR | ₹1.00 L | MEDIUM 59
delay 25duplication 20cost 12 | |
| 23 | Construction of Street, drains are also to be constructed al Drainage & Sanitation — HOSHIARPUR(DEPUTY COMMISSIONER HOSHIARPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 813 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| HOSHIARPUR | ₹2.00 L | MEDIUM 58
delay 25duplication 19cost 13 | |
| 24 | Construction of rooms & halls (completion of the building), Community Buildings — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - ₹1,000,000 against a ₹250,000 median for Community Buildings works in KAPURTHALA (300% above, 56 peer works)
- 609 days beyond expected completion
| KAPURTHALA | ₹10.00 L | MEDIUM 55 | |
| 25 | Construction of Dr. B.R. Ambedkar Bhawan, village Nangal, Ph Community Buildings — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - ₹500,000 against a ₹250,000 median for Community Buildings works in KAPURTHALA (100% above, 56 peer works)
- 665 days beyond expected completion
| KAPURTHALA | ₹5.00 L | MEDIUM 55 | |