| 1 | Construction of Box Culvert on Vadakkekatt Colony-Punnakkal Roads & Paving — ALAPPUZHA(DISTRICT COLLECTOR ALAPPUZHA_IDA) - ₹2,000,000 against a ₹972,457 median for Roads & Paving works in ALAPPUZHA (106% above, 132 peer works)
- 546 days beyond expected completion
| ALAPPUZHA | ₹20.00 L | MEDIUM 54 | |
| 2 | Construction of Drainage for Avoiding Water logging beside A Roads & Paving — ALAPPUZHA(DISTRICT COLLECTOR ALAPPUZHA_IDA) - ₹4,000,000 against a ₹972,457 median for Roads & Paving works in ALAPPUZHA (311% above, 132 peer works)
- 1349 days beyond expected completion
| ALAPPUZHA | ₹40.00 L | MEDIUM 54 | |
| 3 | Construction of Building for C R Madhu Sabdika Grandhasala, Community Buildings — KOLLAM(DISTRICT COLLECTOR KOLLAM_IDA) - ₹1,500,000 against a ₹521,500 median for Community Buildings works in KOLLAM (188% above, 14 peer works)
- 546 days beyond expected completion
| KOLLAM | ₹15.00 L | MEDIUM 53 | |
| 4 | Development of Public Park in Arthunkal Beach in Cherthala S Sports — ALAPPUZHA(DISTRICT COLLECTOR ALAPPUZHA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 546 days beyond expected completion
| ALAPPUZHA | ₹52.75 L | MEDIUM 50 | |
| 5 | Construction of Sub-Centre for PHC in Thodiyoor Gram Panchay Health — KOLLAM(DISTRICT COLLECTOR KOLLAM_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 546 days beyond expected completion
| KOLLAM | ₹40.00 L | MEDIUM 47 | |
| 6 | Construction of First Floor Building for Mortury at THQ Hosp Health — ALAPPUZHA(DISTRICT COLLECTOR ALAPPUZHA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 546 days beyond expected completion
| ALAPPUZHA | ₹26.00 L | MEDIUM 47 | |
| 7 | Purchase of 36+D School Bus for Govt. UPS Karthikappalli (Ta Education — ALAPPUZHA(DISTRICT COLLECTOR ALAPPUZHA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 546 days beyond expected completion
| ALAPPUZHA | ₹26.00 L | MEDIUM 47 | |
| 8 | Purchase of 25+D School Bus for VHSS Kanichukulangara Education — ALAPPUZHA(DISTRICT COLLECTOR ALAPPUZHA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 545 days beyond expected completion
| ALAPPUZHA | ₹23.00 L | MEDIUM 46 | |
| 9 | Purchase of 25+D School Bus for Govt. Town LPS Cherthala Education — ALAPPUZHA(DISTRICT COLLECTOR ALAPPUZHA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 545 days beyond expected completion
| ALAPPUZHA | ₹22.00 L | MEDIUM 46 | |
| 10 | Purchase of 25 + D School Bus for SCU Govt. VHSS Pattanakkad Education — ALAPPUZHA(DISTRICT COLLECTOR ALAPPUZHA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 546 days beyond expected completion
| ALAPPUZHA | ₹22.25 L | MEDIUM 46 | |
| 11 | Purchase of 25+D School Bus for Govt. HSLPS Kalavoor (Tata S Education — ALAPPUZHA(DISTRICT COLLECTOR ALAPPUZHA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 546 days beyond expected completion
| ALAPPUZHA | ₹22.50 L | MEDIUM 46 | |
| 12 | Purchase of 21+D School Bus for Govt. Muslim LPS Punnapra (T Education — ALAPPUZHA(DISTRICT COLLECTOR ALAPPUZHA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 546 days beyond expected completion
| ALAPPUZHA | ₹19.00 L | MEDIUM 46 | |
| 13 | Installation of Mini Mast Lights (8 Meter height and 5 led f Street Lighting — ALAPPUZHA(DISTRICT COLLECTOR ALAPPUZHA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 1303 days beyond expected completion
| ALAPPUZHA | ₹2.17 L | MEDIUM 45 | |
| 14 | Purchase of 18+D School Bus for Govt. Muslim LPS, Memana Oac Education — KOLLAM(DISTRICT COLLECTOR KOLLAM_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 545 days beyond expected completion
| KOLLAM | ₹18.00 L | MEDIUM 44 | |
| 15 | Construction of Building for Thandantayyath Adv V Ahammedkut Education — KOLLAM(DISTRICT COLLECTOR KOLLAM_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 545 days beyond expected completion
| KOLLAM | ₹15.00 L | MEDIUM 43 | |
| 16 | Purchase and Installation of Laptop/Desktop Computers/ Proje Education — ALAPPUZHA(DISTRICT COLLECTOR ALAPPUZHA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 546 days beyond expected completion
| ALAPPUZHA | ₹7.90 L | MEDIUM 41 | |
| 17 | Erection of Tube Well in Play Ground Pump House in Cheruthan Water — ALAPPUZHA(DISTRICT COLLECTOR ALAPPUZHA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 550 days beyond expected completion
| ALAPPUZHA | ₹8.00 L | MEDIUM 41 | |