| 1 | Construction Cows Shed, wall and drinking water Water — HISAR(DEPUTY COMMISSIONER HISSAR_IDA) - ₹2,089,839 against a ₹155,000 median for Water works in HISAR (1248% above, 347 peer works)
- 184 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| HISAR | ₹20.90 L | HIGH 76
cost 25delay 25duplication 20 | |
| 2 | Construction of Interlocking Tiles for cows in the Gaushala, Roads & Paving — HISAR(DEPUTY COMMISSIONER HISSAR_IDA) - ₹1,098,814 against a ₹199,276 median for Roads & Paving works in HISAR (451% above, 50 peer works)
- 203 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| HISAR | ₹10.99 L | HIGH 76
cost 25delay 25duplication 20 | |
| 3 | Construction of RO System (500-100 Lph) Including Water Cool Water — JIND(DEPUTY COMMISSIONER JIND) - ₹1,100,000 against a ₹175,000 median for Water works in JIND (529% above, 156 peer works)
- 210 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JIND | ₹11.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 4 | Construction Cows Shed, wall and drinking water Water — HISAR(DEPUTY COMMISSIONER HISSAR_IDA) - ₹2,089,839 against a ₹155,000 median for Water works in HISAR (1248% above, 347 peer works)
- 184 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| HISAR | ₹20.90 L | HIGH 76
cost 25delay 25duplication 20 | |
| 5 | Construction of Interlocking Tiles for cows in the Gaushala, Roads & Paving — HISAR(DEPUTY COMMISSIONER HISSAR_IDA) - ₹1,098,814 against a ₹199,276 median for Roads & Paving works in HISAR (451% above, 50 peer works)
- 203 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| HISAR | ₹10.99 L | HIGH 76
cost 25delay 25duplication 20 | |
| 6 | Construction of RO System (500-100 Lph) Including Water Cool Water — JIND(DEPUTY COMMISSIONER JIND) - ₹1,100,000 against a ₹175,000 median for Water works in JIND (529% above, 156 peer works)
- 210 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JIND | ₹11.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 7 | Pipeline and Public Stand Post (PSP) from Mundi Tal to Amarp Water — CHURU(DISTRICT COLLECTOR CHURU_IDA) - ₹2,149,000 against a ₹400,000 median for Water works in CHURU (437% above, 13 peer works)
- 267 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| CHURU | ₹21.49 L | HIGH 74
cost 25delay 25duplication 20 | |
| 8 | Pipeline and Public Stand Post (PSP) from Mundi Tal to Amarp Water — CHURU(DISTRICT COLLECTOR CHURU_IDA) - ₹2,149,000 against a ₹400,000 median for Water works in CHURU (437% above, 13 peer works)
- 267 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| CHURU | ₹21.49 L | HIGH 74
cost 25delay 25duplication 20 | |
| 9 | Construction of Cycle Stand, Painting of School, and Ro Wate Water — JIND(DEPUTY COMMISSIONER JIND) - ₹497,024 against a ₹175,000 median for Water works in JIND (184% above, 156 peer works)
- 119 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JIND | ₹4.97 L | MEDIUM 67
cost 25duplication 20delay 17 | |
| 10 | Construction of Cycle Stand, Painting of School, and Ro Wate Water — JIND(DEPUTY COMMISSIONER JIND) - ₹497,024 against a ₹175,000 median for Water works in JIND (184% above, 156 peer works)
- 119 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JIND | ₹4.97 L | MEDIUM 67
cost 25duplication 20delay 17 | |
| 11 | Construction of Shed for cows in the Gaushala, Village Balak Community Buildings — HISAR(DEPUTY COMMISSIONER HISSAR_IDA) - ₹1,100,000 against a ₹536,300 median for Community Buildings works in HISAR (105% above, 89 peer works)
- 110 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| HISAR | ₹11.00 L | MEDIUM 66
cost 25duplication 20delay 15 | |
| 12 | Construction of Shed for cows in the Gaushala, Village Balak Community Buildings — HISAR(DEPUTY COMMISSIONER HISSAR_IDA) - ₹1,100,000 against a ₹536,300 median for Community Buildings works in HISAR (105% above, 89 peer works)
- 110 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| HISAR | ₹11.00 L | MEDIUM 66
cost 25duplication 20delay 15 | |
| 13 | Construction of Jat Community Center Community Buildings — GURUGRAM(DC CUM NODAL OFFICER MPLADS_5) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 309 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 56% delay rate across its projects
| GURUGRAM | ₹11.00 L | MEDIUM 65
delay 25duplication 20cost 12 | |
| 14 | Construction of Jat Community Center Community Buildings — GURUGRAM(DC CUM NODAL OFFICER MPLADS_5) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 309 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 56% delay rate across its projects
| GURUGRAM | ₹11.00 L | MEDIUM 65
delay 25duplication 20cost 12 | |
| 15 | Renovation Compilation of Library Sarv Jatiya Panchayat Bina Education — JIND(DEPUTY COMMISSIONER JIND) - ₹2,097,682 against a ₹392,564 median for Education works in JIND (434% above, 43 peer works)
- 100% similarity with another nearby work
| JIND | ₹20.98 L | MEDIUM 56
cost 25duplication 20delay 6 | |
| 16 | Renovation Compilation of Library Sarv Jatiya Panchayat Bina Education — JIND(DEPUTY COMMISSIONER JIND) - ₹2,097,682 against a ₹392,564 median for Education works in JIND (434% above, 43 peer works)
- 100% similarity with another nearby work
| JIND | ₹20.98 L | MEDIUM 56
cost 25duplication 20delay 6 | |
| 17 | Const. of IPB Rasta Fathepuri road to Dhani of Dr Devilal Roads & Paving — FATEHABAD(Deputy Commissioner Fatehabad) - ₹1,793,000 against a ₹492,500 median for Roads & Paving works in FATEHABAD (264% above, 52 peer works)
- 100% similarity with another nearby work
| FATEHABAD | ₹17.93 L | MEDIUM 55
cost 25duplication 20delay 8 | |
| 18 | Const. of IPB Rasta Fathepuri road to Dhani of Dr Devilal Roads & Paving — FATEHABAD(Deputy Commissioner Fatehabad) - ₹1,793,000 against a ₹492,500 median for Roads & Paving works in FATEHABAD (264% above, 52 peer works)
- 100% similarity with another nearby work
| FATEHABAD | ₹17.93 L | MEDIUM 55
cost 25duplication 20delay 8 | |
| 19 | Const. of Iron Shed at Both Shamshan Ghat Rasta Near Well Ne Roads & Paving — FATEHABAD(Deputy Commissioner Fatehabad) - ₹1,376,000 against a ₹492,500 median for Roads & Paving works in FATEHABAD (179% above, 52 peer works)
- 100% similarity with another nearby work
| FATEHABAD | ₹13.76 L | MEDIUM 55
cost 25duplication 20delay 8 | |
| 20 | Const. of B Wall of Community Center Community Buildings — FATEHABAD(Deputy Commissioner Fatehabad) - ₹2,978,000 against a ₹498,500 median for Community Buildings works in FATEHABAD (497% above, 76 peer works)
- 100% similarity with another nearby work
| FATEHABAD | ₹29.78 L | MEDIUM 55
cost 25duplication 20delay 8 | |
| 21 | Const. Track in Stadium Sports — FATEHABAD(Deputy Commissioner Fatehabad) - ₹2,030,000 against a ₹216,927 median for Sports works in FATEHABAD (836% above, 26 peer works)
- 100% similarity with another nearby work
| FATEHABAD | ₹20.30 L | MEDIUM 55
cost 25duplication 20delay 8 | |
| 22 | Const. of Drain from Shamshan Ghat to Pond Water — FATEHABAD(Deputy Commissioner Fatehabad) - ₹682,000 against a ₹175,000 median for Water works in FATEHABAD (290% above, 41 peer works)
- 100% similarity with another nearby work
| FATEHABAD | ₹6.82 L | MEDIUM 55
cost 25duplication 20delay 8 | |
| 23 | Const. of IPB Street from Main Road to Nagar Khera Roads & Paving — FATEHABAD(Deputy Commissioner Fatehabad) - ₹1,247,000 against a ₹492,500 median for Roads & Paving works in FATEHABAD (153% above, 52 peer works)
- 100% similarity with another nearby work
| FATEHABAD | ₹12.47 L | MEDIUM 55
cost 25duplication 20delay 8 | |
| 24 | Const. of Rasta From HO Chandu Lal Dalal to HO of Dalbir Ex Roads & Paving — FATEHABAD(Deputy Commissioner Fatehabad) - ₹1,193,000 against a ₹492,500 median for Roads & Paving works in FATEHABAD (142% above, 52 peer works)
- 100% similarity with another nearby work
| FATEHABAD | ₹11.93 L | MEDIUM 55
cost 25duplication 20delay 8 | |
| 25 | Const. of IPB Street Mochi Road to Bhala So Khayali Ram Roads & Paving — FATEHABAD(Deputy Commissioner Fatehabad) - ₹3,444,000 against a ₹492,500 median for Roads & Paving works in FATEHABAD (599% above, 52 peer works)
- 100% similarity with another nearby work
| FATEHABAD | ₹34.44 L | MEDIUM 55
cost 25duplication 20delay 8 | |