| 1 | CONSTRUTION OF COMUNNITY HALL AT ANTARDA UNDER TARBHA NAC Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - ₹600,000 against a ₹200,000 median for Community Buildings works in SUBARNAPUR (200% above, 139 peer works)
- 548 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹6.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 2 | CONSTRUTION OF COMUNNITY HALL AT ANTARDA UNDER TARBHA NAC Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - ₹600,000 against a ₹200,000 median for Community Buildings works in SUBARNAPUR (200% above, 139 peer works)
- 548 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹6.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 3 | Construction of Community Center in Alisibindha Village, Blo Community Buildings — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in KHORDHA (100% above, 144 peer works)
- 342 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 4 | Construction of Community Center in Chakeisihani Village, Wa Community Buildings — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in KHORDHA (100% above, 144 peer works)
- 350 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 5 | Construction of Community Center in Salapadihi village under Community Buildings — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in KHORDHA (100% above, 144 peer works)
- 405 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 6 | Construction of Additional Building and Renovation in Odisha Community Buildings — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in KHORDHA (100% above, 144 peer works)
- 419 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 7 | CONSTRUTION OF COMMUNITY CENTRE AT BANPUR NAC WARD NO. 02 FO Community Buildings — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in KHORDHA (100% above, 144 peer works)
- 548 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 8 | Construction of Community Center in Alisibindha Village, Blo Community Buildings — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in KHORDHA (100% above, 144 peer works)
- 342 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 9 | Construction of Community Center in Chakeisihani Village, Wa Community Buildings — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in KHORDHA (100% above, 144 peer works)
- 350 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 10 | Construction of Community Center in Salapadihi village under Community Buildings — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in KHORDHA (100% above, 144 peer works)
- 405 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 11 | Construction of Additional Building and Renovation in Odisha Community Buildings — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in KHORDHA (100% above, 144 peer works)
- 419 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 12 | CONSTRUTION OF COMMUNITY CENTRE AT BANPUR NAC WARD NO. 02 FO Community Buildings — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in KHORDHA (100% above, 144 peer works)
- 548 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 13 | Renovation of Bounsa Pokhari near Balipadar crematorium. GP- Religious & Cultural — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹600,000 against a ₹250,000 median for Religious & Cultural works in KHORDHA (140% above, 128 peer works)
- 139 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹6.00 L | HIGH 70
cost 25duplication 20delay 19 | |
| 14 | Renovation of Bounsa Pokhari near Balipadar crematorium. GP- Religious & Cultural — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹600,000 against a ₹250,000 median for Religious & Cultural works in KHORDHA (140% above, 128 peer works)
- 139 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹6.00 L | HIGH 70
cost 25duplication 20delay 19 | |
| 15 | Renovation of Pond near Kapileswar Temple in Dia village. Water — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹500,000 against a ₹100,000 median for Water works in KHORDHA (400% above, 382 peer works)
- 119 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹5.00 L | MEDIUM 68
cost 25duplication 20delay 17 | |
| 16 | Renovation of Pond near Kapileswar Temple in Dia village. Water — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹500,000 against a ₹100,000 median for Water works in KHORDHA (400% above, 382 peer works)
- 119 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹5.00 L | MEDIUM 68
cost 25duplication 20delay 17 | |
| 17 | Construction of Guard Wall and Culvert in Singarajkhunta vil Roads & Paving — MALKANGIRI(District Collector Malkangiri_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 422 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 53% delay rate across its projects
| MALKANGIRI | ₹10.00 L | MEDIUM 65
delay 25duplication 20cost 12 | |
| 18 | Construction of Guard Wall and Culvert in Singarajkhunta vil Roads & Paving — MALKANGIRI(District Collector Malkangiri_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 422 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 53% delay rate across its projects
| MALKANGIRI | ₹10.00 L | MEDIUM 65
delay 25duplication 20cost 12 | |
| 19 | Construction of road from Main road to Jagannath Temple (Lab Roads & Paving — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,000,000 against a ₹400,000 median for Roads & Paving works in KHORDHA (150% above, 165 peer works)
- 94 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹10.00 L | MEDIUM 64
cost 25duplication 20delay 13 | |
| 20 | Construction of road from Main road to Jagannath Temple (Lab Roads & Paving — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,000,000 against a ₹400,000 median for Roads & Paving works in KHORDHA (150% above, 165 peer works)
- 94 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹10.00 L | MEDIUM 64
cost 25duplication 20delay 13 | |
| 21 | Construction of Class rooms and hall in Saraswati Sishu Vidy Community Buildings — Kataka(DISTRICT COLLECTOR CUTTACK_IDA) - ₹500,000 against a ₹350,000 median for Community Buildings works in KATAKA (43% above, 273 peer works)
- 387 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KATAKA | ₹5.00 L | MEDIUM 60
delay 25duplication 20cost 11 | |
| 22 | Construction of Class rooms and hall in Saraswati Sishu Vidy Community Buildings — Kataka(DISTRICT COLLECTOR CUTTACK_IDA) - ₹500,000 against a ₹350,000 median for Community Buildings works in KATAKA (43% above, 273 peer works)
- 387 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KATAKA | ₹5.00 L | MEDIUM 60
delay 25duplication 20cost 11 | |
| 23 | Construction of society house of Sambit Villa residential we Community Buildings — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - 293 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹5.00 L | MEDIUM 59
delay 25duplication 20cost 8 | |
| 24 | Construction of society house of Sambit Villa residential we Community Buildings — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - 293 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹5.00 L | MEDIUM 59
delay 25duplication 20cost 8 | |
| 25 | Construction of Culvert with Guard Wall in front of Ajay Bal Roads & Paving — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - 232 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹2.50 L | MEDIUM 58
delay 25duplication 20cost 7 | |