| 1 | Construction of Community centres and Community Hall Community Buildings — SHIMLA(DEPUTY COMMISSIONER SHIMLA_IDA) - ₹500,000 against a ₹200,000 median for Community Buildings works in SHIMLA (150% above, 221 peer works)
- 284 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| SHIMLA | ₹5.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 2 | Construction of Link Road and pathways Roads & Paving — SHIMLA(DEPUTY COMMISSIONER SHIMLA_IDA) - ₹500,000 against a ₹200,000 median for Roads & Paving works in SHIMLA (150% above, 330 peer works)
- 284 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| SHIMLA | ₹5.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 3 | Construction of Community centres and Community Hall Community Buildings — SHIMLA(DEPUTY COMMISSIONER SHIMLA_IDA) - ₹500,000 against a ₹200,000 median for Community Buildings works in SHIMLA (150% above, 221 peer works)
- 284 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| SHIMLA | ₹5.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 4 | Construction of Link Road and pathways Roads & Paving — SHIMLA(DEPUTY COMMISSIONER SHIMLA_IDA) - ₹500,000 against a ₹200,000 median for Roads & Paving works in SHIMLA (150% above, 330 peer works)
- 284 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| SHIMLA | ₹5.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 5 | Construction of Concrete Road Adarsh Nagar Hardaspura Ward p Roads & Paving — CHAMBA(DEPUTY COMMISSIONER CHAMBA_IDA) - ₹500,000 against a ₹200,000 median for Roads & Paving works in CHAMBA (150% above, 339 peer works)
- 373 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 40% delay rate across its projects
| CHAMBA | ₹5.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 6 | Construction of ambulance road soling conc. With drain main Roads & Paving — CHAMBA(DEPUTY COMMISSIONER CHAMBA_IDA) - ₹400,000 against a ₹200,000 median for Roads & Paving works in CHAMBA (100% above, 339 peer works)
- 412 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 40% delay rate across its projects
| CHAMBA | ₹4.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 7 | Pucca path from Chalang to Shamshan Ghat GP Chil Bangla Dev. Religious & Cultural — CHAMBA(DEPUTY COMMISSIONER CHAMBA_IDA) - ₹400,000 against a ₹200,000 median for Religious & Cultural works in CHAMBA (100% above, 38 peer works)
- 413 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 40% delay rate across its projects
| CHAMBA | ₹4.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 8 | Jeep Road from Khalotu to Bairi GP Chil Bangla Dev. Block Ch Roads & Paving — CHAMBA(DEPUTY COMMISSIONER CHAMBA_IDA) - ₹400,000 against a ₹200,000 median for Roads & Paving works in CHAMBA (100% above, 339 peer works)
- 413 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 40% delay rate across its projects
| CHAMBA | ₹4.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 9 | Construction of Concrete Road Adarsh Nagar Hardaspura Ward p Roads & Paving — CHAMBA(DEPUTY COMMISSIONER CHAMBA_IDA) - ₹500,000 against a ₹200,000 median for Roads & Paving works in CHAMBA (150% above, 339 peer works)
- 373 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 40% delay rate across its projects
| CHAMBA | ₹5.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 10 | Construction of ambulance road soling conc. With drain main Roads & Paving — CHAMBA(DEPUTY COMMISSIONER CHAMBA_IDA) - ₹400,000 against a ₹200,000 median for Roads & Paving works in CHAMBA (100% above, 339 peer works)
- 412 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 40% delay rate across its projects
| CHAMBA | ₹4.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 11 | Pucca path from Chalang to Shamshan Ghat GP Chil Bangla Dev. Religious & Cultural — CHAMBA(DEPUTY COMMISSIONER CHAMBA_IDA) - ₹400,000 against a ₹200,000 median for Religious & Cultural works in CHAMBA (100% above, 38 peer works)
- 413 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 40% delay rate across its projects
| CHAMBA | ₹4.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 12 | Jeep Road from Khalotu to Bairi GP Chil Bangla Dev. Block Ch Roads & Paving — CHAMBA(DEPUTY COMMISSIONER CHAMBA_IDA) - ₹400,000 against a ₹200,000 median for Roads & Paving works in CHAMBA (100% above, 339 peer works)
- 413 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 40% delay rate across its projects
| CHAMBA | ₹4.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 13 | Construction of Road, approach roads, link roads and pathway Roads & Paving — KANGRA(DEPUTY COMMISSIONER KANGRA_IDA) - ₹800,000 against a ₹200,000 median for Roads & Paving works in KANGRA (300% above, 501 peer works)
- 284 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KANGRA | ₹8.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 14 | Construction of Road, approach roads, link roads and pathway Roads & Paving — KANGRA(DEPUTY COMMISSIONER KANGRA_IDA) - ₹800,000 against a ₹200,000 median for Roads & Paving works in KANGRA (300% above, 501 peer works)
- 284 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KANGRA | ₹8.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 15 | Construction of Link Road from Post office-Bhulsway to SC Ba Roads & Paving — BILASPUR(DEPUTY COMMISSIONER, BILASPUR) - ₹500,000 against a ₹200,000 median for Roads & Paving works in BILASPUR (150% above, 157 peer works)
- 394 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BILASPUR | ₹5.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 16 | Construction of Link Road from Post office-Bhulsway to SC Ba Roads & Paving — BILASPUR(DEPUTY COMMISSIONER, BILASPUR) - ₹500,000 against a ₹200,000 median for Roads & Paving works in BILASPUR (150% above, 157 peer works)
- 394 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BILASPUR | ₹5.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 17 | Construction of Prathmik Pathshala (retaining wall at gps ka Boundary & Protection — SHIMLA(DEPUTY COMMISSIONER SHIMLA_IDA) - ₹500,000 against a ₹200,000 median for Boundary & Protection works in SHIMLA (150% above, 39 peer works)
- 153 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| SHIMLA | ₹5.00 L | HIGH 75
cost 25delay 21duplication 20 | |
| 18 | Construction of Prathmik Pathshala (retaining wall at gps ka Boundary & Protection — SHIMLA(DEPUTY COMMISSIONER SHIMLA_IDA) - ₹500,000 against a ₹200,000 median for Boundary & Protection works in SHIMLA (150% above, 39 peer works)
- 153 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| SHIMLA | ₹5.00 L | HIGH 75
cost 25delay 21duplication 20 | |
| 19 | Construction of Contact paved road main road Padar to kavant Roads & Paving — SHIMLA(DEPUTY COMMISSIONER SHIMLA_IDA) - ₹500,000 against a ₹200,000 median for Roads & Paving works in SHIMLA (150% above, 330 peer works)
- 133 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| SHIMLA | ₹5.00 L | HIGH 73
cost 25duplication 20delay 18 | |
| 20 | Construction of Contact paved road main road Padar to kavant Roads & Paving — SHIMLA(DEPUTY COMMISSIONER SHIMLA_IDA) - ₹500,000 against a ₹200,000 median for Roads & Paving works in SHIMLA (150% above, 330 peer works)
- 133 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| SHIMLA | ₹5.00 L | HIGH 73
cost 25duplication 20delay 18 | |
| 21 | Construction of community hall Shri Vaishya Sabha Nahan Community Buildings — SIRMAUR(DEPUTY COMMISSIONER SIRMOUR_IDA) - ₹500,000 against a ₹250,000 median for Community Buildings works in SIRMAUR (100% above, 86 peer works)
- 153 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| SIRMAUR | ₹5.00 L | HIGH 73
cost 25delay 21duplication 20 | |
| 22 | Construction of community hall Shri Vaishya Sabha Nahan Community Buildings — SIRMAUR(DEPUTY COMMISSIONER SIRMOUR_IDA) - ₹500,000 against a ₹250,000 median for Community Buildings works in SIRMAUR (100% above, 86 peer works)
- 153 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| SIRMAUR | ₹5.00 L | HIGH 73
cost 25delay 21duplication 20 | |
| 23 | Construction of room Saraswati Vidya Mandir Religious & Cultural — MANDI(DEPUTY COMMISSIONER MANDI_IDA) - ₹300,000 against a ₹150,000 median for Religious & Cultural works in MANDI (100% above, 33 peer works)
- 153 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MANDI | ₹3.00 L | HIGH 72
cost 25delay 21duplication 20 | |
| 24 | Construction of room Saraswati Vidya Mandir Religious & Cultural — MANDI(DEPUTY COMMISSIONER MANDI_IDA) - ₹300,000 against a ₹150,000 median for Religious & Cultural works in MANDI (100% above, 33 peer works)
- 153 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MANDI | ₹3.00 L | HIGH 72
cost 25delay 21duplication 20 | |
| 25 | Construction of Road, Mehli Shoghi Junga Sadhupul Road Roads & Paving — SHIMLA(DEPUTY COMMISSIONER SHIMLA_IDA) - ₹2,500,000 against a ₹200,000 median for Roads & Paving works in SHIMLA (1150% above, 330 peer works)
- 111 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| SHIMLA | ₹25.00 L | MEDIUM 70
cost 25duplication 20delay 15 | |