| 1 | Construction Of class Room For Gramanthar vidyavardhak Trust Education — VIJAYAPURA(DEPUTY COMMISSIONER BIJAPUR_IDA) - ₹495,000 against a ₹250,000 median for Education works in VIJAYAPURA (98% above, 146 peer works)
- 197 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 74% of this agency's ₹91,833,067 spend went to one vendor (Nirmithi kendra vijayapur), across 40 vendors and 130 transactions
| VIJAYAPURA | ₹4.95 L | HIGH 82
delay 25cost 25duplication 19 | |
| 2 | Construction Of class Room For Gramanthar vidyavardhak Trust Education — VIJAYAPURA(DEPUTY COMMISSIONER BIJAPUR_IDA) - ₹495,000 against a ₹250,000 median for Education works in VIJAYAPURA (98% above, 146 peer works)
- 197 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 74% of this agency's ₹91,833,067 spend went to one vendor (Nirmithi kendra vijayapur), across 40 vendors and 130 transactions
| VIJAYAPURA | ₹4.95 L | HIGH 82
delay 25cost 25duplication 19 | |
| 3 | Construction of community Hall Near Shri Kallameshwar Temple Community Buildings — VIJAYAPURA(DEPUTY COMMISSIONER BIJAPUR_IDA) - ₹495,000 against a ₹250,000 median for Community Buildings works in VIJAYAPURA (98% above, 629 peer works)
- 223 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 74% of this agency's ₹91,833,067 spend went to one vendor (Nirmithi kendra vijayapur), across 40 vendors and 130 transactions
| VIJAYAPURA | ₹4.95 L | HIGH 82
delay 25cost 25duplication 19 | |
| 4 | Construction of community Hall Near Shri Kallameshwar Temple Community Buildings — VIJAYAPURA(DEPUTY COMMISSIONER BIJAPUR_IDA) - ₹495,000 against a ₹250,000 median for Community Buildings works in VIJAYAPURA (98% above, 629 peer works)
- 223 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 74% of this agency's ₹91,833,067 spend went to one vendor (Nirmithi kendra vijayapur), across 40 vendors and 130 transactions
| VIJAYAPURA | ₹4.95 L | HIGH 82
delay 25cost 25duplication 19 | |
| 5 | Construction of community hall Near Ram Kshatriy Social Trus Community Buildings — VIJAYAPURA(DEPUTY COMMISSIONER BIJAPUR_IDA) - ₹495,000 against a ₹250,000 median for Community Buildings works in VIJAYAPURA (98% above, 629 peer works)
- 197 days beyond expected completion
Read more (2 more)Show less- 99% similarity with another nearby work
- 74% of this agency's ₹91,833,067 spend went to one vendor (Nirmithi kendra vijayapur), across 40 vendors and 130 transactions
| VIJAYAPURA | ₹4.95 L | HIGH 81
delay 25cost 25duplication 18 | |
| 6 | Construction of community hall Near Dr. BAbu Jagajeevan Rao Community Buildings — VIJAYAPURA(DEPUTY COMMISSIONER BIJAPUR_IDA) - ₹490,000 against a ₹250,000 median for Community Buildings works in VIJAYAPURA (96% above, 629 peer works)
- 197 days beyond expected completion
Read more (2 more)Show less- 99% similarity with another nearby work
- 74% of this agency's ₹91,833,067 spend went to one vendor (Nirmithi kendra vijayapur), across 40 vendors and 130 transactions
| VIJAYAPURA | ₹4.90 L | HIGH 79
delay 25cost 24duplication 16 | |
| 7 | Construction of community hall Near basaveshwar Temple Community Buildings — VIJAYAPURA(DEPUTY COMMISSIONER BIJAPUR_IDA) - ₹495,000 against a ₹250,000 median for Community Buildings works in VIJAYAPURA (98% above, 629 peer works)
- 656 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 53% delay rate across its projects
| VIJAYAPURA | ₹4.95 L | HIGH 77
delay 25cost 25duplication 20 | |
| 8 | Construction of community hall near Shri Lingeshwar Temple S Community Buildings — VIJAYAPURA(DEPUTY COMMISSIONER BIJAPUR_IDA) - ₹495,000 against a ₹250,000 median for Community Buildings works in VIJAYAPURA (98% above, 629 peer works)
- 654 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 53% delay rate across its projects
| VIJAYAPURA | ₹4.95 L | HIGH 77
delay 25cost 25duplication 20 | |
| 9 | Construction of community hall near Shri Lingeshwar Temple S Community Buildings — VIJAYAPURA(DEPUTY COMMISSIONER BIJAPUR_IDA) - ₹495,000 against a ₹250,000 median for Community Buildings works in VIJAYAPURA (98% above, 629 peer works)
- 654 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 53% delay rate across its projects
| VIJAYAPURA | ₹4.95 L | HIGH 77
delay 25cost 25duplication 20 | |
| 10 | Construction of Class room For Manniranjan Yallandur Yoga In Education — VIJAYAPURA(DEPUTY COMMISSIONER BIJAPUR_IDA) - ₹495,000 against a ₹250,000 median for Education works in VIJAYAPURA (98% above, 146 peer works)
- 654 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 53% delay rate across its projects
| VIJAYAPURA | ₹4.95 L | HIGH 77
delay 25cost 25duplication 20 | |
| 11 | Construction of Class room For Manniranjan Yallandur Yoga In Education — VIJAYAPURA(DEPUTY COMMISSIONER BIJAPUR_IDA) - ₹495,000 against a ₹250,000 median for Education works in VIJAYAPURA (98% above, 146 peer works)
- 654 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 53% delay rate across its projects
| VIJAYAPURA | ₹4.95 L | HIGH 77
delay 25cost 25duplication 20 | |
| 12 | Construction of Class room For Manniranjan Yallandur Yoga In Education — VIJAYAPURA(DEPUTY COMMISSIONER BIJAPUR_IDA) - ₹495,000 against a ₹250,000 median for Education works in VIJAYAPURA (98% above, 146 peer works)
- 654 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 53% delay rate across its projects
| VIJAYAPURA | ₹4.95 L | HIGH 77
delay 25cost 25duplication 20 | |
| 13 | Construction of community Hall Near Shivayogeshwar Temple at Community Buildings — VIJAYAPURA(DEPUTY COMMISSIONER BIJAPUR_IDA) - ₹495,000 against a ₹250,000 median for Community Buildings works in VIJAYAPURA (98% above, 629 peer works)
- 223 days beyond expected completion
Read more (2 more)Show less- 98% similarity with another nearby work
- 74% of this agency's ₹91,833,067 spend went to one vendor (Nirmithi kendra vijayapur), across 40 vendors and 130 transactions
| VIJAYAPURA | ₹4.95 L | HIGH 77
delay 25cost 25duplication 14 | |
| 14 | Construction of community hall Near Revannasiddeshwar Temple Community Buildings — VIJAYAPURA(DEPUTY COMMISSIONER BIJAPUR_IDA) - ₹495,000 against a ₹250,000 median for Community Buildings works in VIJAYAPURA (98% above, 629 peer works)
- 649 days beyond expected completion
Read more (2 more)Show less- 99% similarity with another nearby work
- Implementing agency has a 53% delay rate across its projects
| VIJAYAPURA | ₹4.95 L | HIGH 76
delay 25cost 25duplication 18 | |
| 15 | Construction of community hall Near Revannasiddeshwar Temple Community Buildings — VIJAYAPURA(DEPUTY COMMISSIONER BIJAPUR_IDA) - ₹495,000 against a ₹250,000 median for Community Buildings works in VIJAYAPURA (98% above, 629 peer works)
- 649 days beyond expected completion
Read more (2 more)Show less- 99% similarity with another nearby work
- Implementing agency has a 53% delay rate across its projects
| VIJAYAPURA | ₹4.95 L | HIGH 76
delay 25cost 25duplication 18 | |
| 16 | Construction of community Hall Near Merchandise Association Community Buildings — VIJAYAPURA(DEPUTY COMMISSIONER BIJAPUR_IDA) - ₹495,000 against a ₹250,000 median for Community Buildings works in VIJAYAPURA (98% above, 629 peer works)
- 656 days beyond expected completion
Read more (2 more)Show less- 99% similarity with another nearby work
- Implementing agency has a 53% delay rate across its projects
| VIJAYAPURA | ₹4.95 L | HIGH 75
delay 25cost 25duplication 18 | |
| 17 | Construction of community Hall Near Merchandise Association Community Buildings — VIJAYAPURA(DEPUTY COMMISSIONER BIJAPUR_IDA) - ₹495,000 against a ₹250,000 median for Community Buildings works in VIJAYAPURA (98% above, 629 peer works)
- 656 days beyond expected completion
Read more (2 more)Show less- 99% similarity with another nearby work
- Implementing agency has a 53% delay rate across its projects
| VIJAYAPURA | ₹4.95 L | HIGH 75
delay 25cost 25duplication 18 | |
| 18 | Construction of community hall Near Revannasiddeshwar Temple Community Buildings — VIJAYAPURA(DEPUTY COMMISSIONER BIJAPUR_IDA) - ₹495,000 against a ₹250,000 median for Community Buildings works in VIJAYAPURA (98% above, 629 peer works)
- 649 days beyond expected completion
Read more (2 more)Show less- 99% similarity with another nearby work
- Implementing agency has a 53% delay rate across its projects
| VIJAYAPURA | ₹4.95 L | HIGH 74
delay 25cost 25duplication 17 | |
| 19 | Construction of community hall Near Revannasiddeshwar Temple Community Buildings — VIJAYAPURA(DEPUTY COMMISSIONER BIJAPUR_IDA) - ₹495,000 against a ₹250,000 median for Community Buildings works in VIJAYAPURA (98% above, 629 peer works)
- 649 days beyond expected completion
Read more (2 more)Show less- 99% similarity with another nearby work
- Implementing agency has a 53% delay rate across its projects
| VIJAYAPURA | ₹4.95 L | HIGH 74
delay 25cost 25duplication 17 | |
| 20 | Construction of community Hall Near Merchandise Association Community Buildings — VIJAYAPURA(DEPUTY COMMISSIONER BIJAPUR_IDA) - ₹495,000 against a ₹250,000 median for Community Buildings works in VIJAYAPURA (98% above, 629 peer works)
- 656 days beyond expected completion
Read more (2 more)Show less- 99% similarity with another nearby work
- Implementing agency has a 53% delay rate across its projects
| VIJAYAPURA | ₹4.95 L | HIGH 74
delay 25cost 25duplication 17 | |
| 21 | Construction of Class room For Shivayogeshwar Kannada Primar Education — VIJAYAPURA(DEPUTY COMMISSIONER BIJAPUR_IDA) - ₹400,000 against a ₹250,000 median for Education works in VIJAYAPURA (60% above, 146 peer works)
- 223 days beyond expected completion
Read more (2 more)Show less- 99% similarity with another nearby work
- 74% of this agency's ₹91,833,067 spend went to one vendor (Nirmithi kendra vijayapur), across 40 vendors and 130 transactions
| VIJAYAPURA | ₹4.00 L | HIGH 71
delay 25duplication 18cost 15 | |
| 22 | Construction Of comminuty hall near Ramalingadev Choudeshwar Community Buildings — VIJAYAPURA(DEPUTY COMMISSIONER BIJAPUR_IDA) - ₹495,000 against a ₹250,000 median for Community Buildings works in VIJAYAPURA (98% above, 629 peer works)
- 76 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 74% of this agency's ₹91,833,067 spend went to one vendor (Nirmithi kendra vijayapur), across 40 vendors and 130 transactions
| VIJAYAPURA | ₹4.95 L | MEDIUM 68
cost 25duplication 20agency 13 | |
| 23 | Construction Of comminuty hall near Ramalingadev Choudeshwar Community Buildings — VIJAYAPURA(DEPUTY COMMISSIONER BIJAPUR_IDA) - ₹495,000 against a ₹250,000 median for Community Buildings works in VIJAYAPURA (98% above, 629 peer works)
- 76 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 74% of this agency's ₹91,833,067 spend went to one vendor (Nirmithi kendra vijayapur), across 40 vendors and 130 transactions
| VIJAYAPURA | ₹4.95 L | MEDIUM 68
cost 25duplication 20agency 13 | |
| 24 | Construction Of Class room for Sangameshwar Educational Trus Education — VIJAYAPURA(DEPUTY COMMISSIONER BIJAPUR_IDA) - ₹495,000 against a ₹250,000 median for Education works in VIJAYAPURA (98% above, 146 peer works)
- 76 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 74% of this agency's ₹91,833,067 spend went to one vendor (Nirmithi kendra vijayapur), across 40 vendors and 130 transactions
| VIJAYAPURA | ₹4.95 L | MEDIUM 68
cost 25duplication 20agency 13 | |
| 25 | Construction Of Class room for Sangameshwar Educational Trus Education — VIJAYAPURA(DEPUTY COMMISSIONER BIJAPUR_IDA) - ₹495,000 against a ₹250,000 median for Education works in VIJAYAPURA (98% above, 146 peer works)
- 76 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 74% of this agency's ₹91,833,067 spend went to one vendor (Nirmithi kendra vijayapur), across 40 vendors and 130 transactions
| VIJAYAPURA | ₹4.95 L | MEDIUM 68
cost 25duplication 20agency 13 | |