| 1 | Construction of two class rooms in Bhagwat Jha Azad Degree C Education — JAMTARA(Deputy Commissioner Jamtara_IDA) - ₹1,000,000 against a ₹249,745 median for Education works in JAMTARA (300% above, 46 peer works)
- 430 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 97% of this agency's ₹28,850,000 spend went to one vendor (PRAHLAD MANDAL), across 2 vendors and 108 transactions
| JAMTARA | ₹10.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 2 | Construction of Guest House at Radha Krishan Thakur Bari Sev Community Buildings — GIRIDIH(Deputy Commissioner Giridh_IDA) - ₹1,000,000 against a ₹300,000 median for Community Buildings works in GIRIDIH (233% above, 90 peer works)
- 562 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 65% of this agency's ₹110,464,562 spend went to one vendor (Executive engineer), across 2 vendors and 335 transactions
| GIRIDIH | ₹10.00 L | HIGH 83
cost 25delay 25duplication 20 | |
| 3 | Construction of Guest House at Radha Krishan Thakur Bari Sev Community Buildings — GIRIDIH(Deputy Commissioner Giridh_IDA) - ₹1,000,000 against a ₹300,000 median for Community Buildings works in GIRIDIH (233% above, 90 peer works)
- 562 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 57% of this agency's ₹126,197,671 spend went to one vendor (Executive engineer), across 2 vendors and 380 transactions
| GIRIDIH | ₹10.00 L | HIGH 82
cost 25delay 25duplication 20 | |
| 4 | Construction of two class rooms in Bhagwat Jha Azad Degree C Education — JAMTARA(Deputy Commissioner Jamtara_IDA) - ₹1,000,000 against a ₹249,745 median for Education works in JAMTARA (300% above, 46 peer works)
- 430 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 46% of this agency's ₹28,689,800 spend went to one vendor (SANTOSH KUMAR MONDAL), across 3 vendors and 104 transactions
| JAMTARA | ₹10.00 L | HIGH 78
cost 25delay 25duplication 20 | |
| 5 | Construction of Shed near Holy Cross School in ward no-11 at Education — RANCHI(DEPUTY COMMISSIONER RANCHI_IDA) - ₹465,000 against a ₹100,000 median for Education works in RANCHI (365% above, 433 peer works)
- 142 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| RANCHI | ₹4.65 L | MEDIUM 68
cost 25duplication 20delay 20 | |
| 6 | Installation of Boring, Tank and Tower Near Loyla Hostel war Education — RANCHI(DEPUTY COMMISSIONER RANCHI_IDA) - ₹660,000 against a ₹100,000 median for Education works in RANCHI (560% above, 433 peer works)
- 142 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| RANCHI | ₹6.60 L | MEDIUM 68
cost 25duplication 20delay 20 | |
| 7 | Construction of shed and platform near Gossner Middle School Education — RANCHI(DEPUTY COMMISSIONER RANCHI_IDA) - ₹580,000 against a ₹100,000 median for Education works in RANCHI (480% above, 433 peer works)
- 142 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| RANCHI | ₹5.80 L | MEDIUM 68
cost 25duplication 20delay 20 | |
| 8 | Construction of Shed near Holy Cross School in ward no-11 at Education — RANCHI(DEPUTY COMMISSIONER RANCHI_IDA) - ₹465,000 against a ₹100,000 median for Education works in RANCHI (365% above, 433 peer works)
- 142 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| RANCHI | ₹4.65 L | MEDIUM 68
cost 25duplication 20delay 20 | |
| 9 | Installation of Boring, Tank and Tower Near Loyla Hostel war Education — RANCHI(DEPUTY COMMISSIONER RANCHI_IDA) - ₹660,000 against a ₹100,000 median for Education works in RANCHI (560% above, 433 peer works)
- 142 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| RANCHI | ₹6.60 L | MEDIUM 68
cost 25duplication 20delay 20 | |
| 10 | Construction of shed and platform near Gossner Middle School Education — RANCHI(DEPUTY COMMISSIONER RANCHI_IDA) - ₹580,000 against a ₹100,000 median for Education works in RANCHI (480% above, 433 peer works)
- 142 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| RANCHI | ₹5.80 L | MEDIUM 68
cost 25duplication 20delay 20 | |
| 11 | Construction of community halls for Social work Momi , Karha Community Buildings — GIRIDIH(Deputy Commissioner Giridh_IDA) - Completed work has no photographic documentation on record
- ₹1,149,644 against a ₹300,000 median for Community Buildings works in GIRIDIH (283% above, 90 peer works)
Read more (2 more)Show less- 100% similarity with another nearby work
- 65% of this agency's ₹110,464,562 spend went to one vendor (Executive engineer), across 2 vendors and 335 transactions
| GIRIDIH | ₹11.50 L | MEDIUM 63
cost 25duplication 20agency 13 | |
| 12 | Construction of community halls for Social work Momi , Karha Community Buildings — GIRIDIH(Deputy Commissioner Giridh_IDA) - Completed work has no photographic documentation on record
- ₹1,149,644 against a ₹300,000 median for Community Buildings works in GIRIDIH (283% above, 90 peer works)
Read more (2 more)Show less- 100% similarity with another nearby work
- 57% of this agency's ₹126,197,671 spend went to one vendor (Executive engineer), across 2 vendors and 380 transactions
| GIRIDIH | ₹11.50 L | MEDIUM 62
cost 25duplication 20agency 12 | |
| 13 | Additonal and Extra Work for Renovation of Minority School o Education — RANCHI(DEPUTY COMMISSIONER RANCHI_IDA) - ₹166,950 against a ₹100,000 median for Education works in RANCHI (67% above, 433 peer works)
- 142 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| RANCHI | ₹1.67 L | MEDIUM 59
duplication 20delay 20cost 17 | |
| 14 | Additonal and Extra Work for Renovation of Minority School o Education — RANCHI(DEPUTY COMMISSIONER RANCHI_IDA) - ₹166,950 against a ₹100,000 median for Education works in RANCHI (67% above, 433 peer works)
- 142 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| RANCHI | ₹1.67 L | MEDIUM 59
duplication 20delay 20cost 17 | |
| 15 | Boring , Construction of Platform , Installation of Water Ta Roads & Paving — RANCHI(DEPUTY COMMISSIONER RANCHI_IDA) - 676 days beyond expected completion
- 100% similarity with another nearby work
| RANCHI | ₹4.61 L | MEDIUM 58
delay 25duplication 20cost 10 | |
| 16 | Boring , Construction of Platform , Installation of Water Ta Roads & Paving — RANCHI(DEPUTY COMMISSIONER RANCHI_IDA) - 676 days beyond expected completion
- 100% similarity with another nearby work
| RANCHI | ₹4.61 L | MEDIUM 58
delay 25duplication 20cost 10 | |
| 17 | Boring , Construction of Platform , Installation of Water Ta Water — RANCHI(DEPUTY COMMISSIONER RANCHI_IDA) - 430 days beyond expected completion
- 100% similarity with another nearby work
| RANCHI | ₹4.84 L | MEDIUM 57
delay 25duplication 20cost 9 | |
| 18 | Boring , Construction of Platform , Installation of Water Ta Water — RANCHI(DEPUTY COMMISSIONER RANCHI_IDA) - 430 days beyond expected completion
- 100% similarity with another nearby work
| RANCHI | ₹4.84 L | MEDIUM 57
delay 25duplication 20cost 9 | |
| 19 | Boring , Construction of Platform , Installation of Water Ta Water — RANCHI(DEPUTY COMMISSIONER RANCHI_IDA) - 430 days beyond expected completion
- 100% similarity with another nearby work
| RANCHI | ₹4.84 L | MEDIUM 57
delay 25duplication 20cost 9 | |
| 20 | Boring , Construction of Platform , Installation of Water Ta Water — RANCHI(DEPUTY COMMISSIONER RANCHI_IDA) - 430 days beyond expected completion
- 100% similarity with another nearby work
| RANCHI | ₹4.84 L | MEDIUM 57
delay 25duplication 20cost 9 | |
| 21 | Boring , Construction of Platform , Installation of Water Ta Water — RANCHI(DEPUTY COMMISSIONER RANCHI_IDA) - 430 days beyond expected completion
- 100% similarity with another nearby work
| RANCHI | ₹4.84 L | MEDIUM 57
delay 25duplication 20cost 9 | |
| 22 | Boring , Construction of Platform , Installation of Water Ta Water — RANCHI(DEPUTY COMMISSIONER RANCHI_IDA) - 430 days beyond expected completion
- 100% similarity with another nearby work
| RANCHI | ₹4.84 L | MEDIUM 57
delay 25duplication 20cost 9 | |
| 23 | Boring , Construction of Platform , Installation of Water Ta Roads & Paving — RANCHI(DEPUTY COMMISSIONER RANCHI_IDA) - 426 days beyond expected completion
- 100% similarity with another nearby work
| RANCHI | ₹4.84 L | MEDIUM 57
delay 25duplication 20cost 9 | |
| 24 | Boring , Construction of Platform , Installation of Water Ta Water — RANCHI(DEPUTY COMMISSIONER RANCHI_IDA) - 426 days beyond expected completion
- 100% similarity with another nearby work
| RANCHI | ₹4.84 L | MEDIUM 57
delay 25duplication 20cost 9 | |
| 25 | Boring , Construction of Platform , Installation of Water Ta Water — RANCHI(DEPUTY COMMISSIONER RANCHI_IDA) - 426 days beyond expected completion
- 100% similarity with another nearby work
| RANCHI | ₹4.84 L | MEDIUM 57
delay 25duplication 20cost 9 | |