| 1 | Ballari city Dr. Joladarashi Doddangouda Rangamandir Stage a Community Buildings — BALLARI(DEPUTY COMMISSIONER BELLARY_IDA) - ₹2,000,000 against a ₹1,000,000 median for Community Buildings works in BALLARI (100% above, 30 peer works)
- 546 days beyond expected completion
Read more (1 more)Show less- 49% of this agency's ₹96,130,423 spend went to one vendor (Bellary Nirmithi Kendra Bellary), across 4 vendors and 83 transactions
| BALLARI | ₹20.00 L | MEDIUM 59 | |
| 2 | Construction of Rooms and halls in Chitiginahalu village Gov Education — BALLARI(DEPUTY COMMISSIONER BELLARY_IDA) - ₹3,250,000 against a ₹1,000,000 median for Education works in BALLARI (225% above, 19 peer works)
- 546 days beyond expected completion
Read more (1 more)Show less- 49% of this agency's ₹96,130,423 spend went to one vendor (Bellary Nirmithi Kendra Bellary), across 4 vendors and 83 transactions
| BALLARI | ₹32.50 L | MEDIUM 59 | |
| 3 | Construction of rooms and halls in SM Boys Junior college Ka Education — BALLARI(DEPUTY COMMISSIONER BELLARY_IDA) - ₹3,250,000 against a ₹1,000,000 median for Education works in BALLARI (225% above, 19 peer works)
- 546 days beyond expected completion
Read more (1 more)Show less- 49% of this agency's ₹96,130,423 spend went to one vendor (Bellary Nirmithi Kendra Bellary), across 4 vendors and 83 transactions
| BALLARI | ₹32.50 L | MEDIUM 59 | |
| 4 | Construction work of CC Road from KC Link Road to Donnappa R Roads & Paving — BALLARI(DEPUTY COMMISSIONER BELLARY_IDA) - ₹20,000,000 against a ₹1,000,000 median for Roads & Paving works in BALLARI (1900% above, 51 peer works)
- 546 days beyond expected completion
Read more (1 more)Show less- 49% of this agency's ₹96,130,423 spend went to one vendor (Bellary Nirmithi Kendra Bellary), across 4 vendors and 83 transactions
| BALLARI | ₹2.00 Cr | MEDIUM 59 | |
| 5 | Udasalamma Check dam lake development work under Kudligi Tow Water — Vijayanagara(DEPUTY COMMISSIONER VIJAYANAGARA_IDA) - ₹10,000,000 against a ₹900,000 median for Water works in VIJAYANAGARA (1011% above, 9 peer works)
- 544 days beyond expected completion
| VIJAYANAGARA | ₹1.00 Cr | MEDIUM 55 | |
| 6 | Development of Footpath Pedestrian from Moorangadi cricle vi Roads & Paving — Vijayanagara(DEPUTY COMMISSIONER VIJAYANAGARA_IDA) - ₹7,800,000 against a ₹500,000 median for Roads & Paving works in VIJAYANAGARA (1460% above, 8 peer works)
- 544 days beyond expected completion
| VIJAYANAGARA | ₹78.00 L | MEDIUM 55 | |
| 7 | Development of Park At 01 st Main Road, 3rd and 04th Cross i Roads & Paving — Vijayanagara(DEPUTY COMMISSIONER VIJAYANAGARA_IDA) - ₹5,200,000 against a ₹500,000 median for Roads & Paving works in VIJAYANAGARA (940% above, 8 peer works)
- 544 days beyond expected completion
| VIJAYANAGARA | ₹52.00 L | MEDIUM 55 | |
| 8 | Development of public parks in Basaveshwara Badavane at Hosa Sports — Vijayanagara(DEPUTY COMMISSIONER VIJAYANAGARA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 544 days beyond expected completion
| VIJAYANAGARA | ₹65.00 L | MEDIUM 51 | |
| 9 | Park development work in MP Prakash Nagar Shankara Gowda Col Street Lighting — Vijayanagara(DEPUTY COMMISSIONER VIJAYANAGARA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 544 days beyond expected completion
| VIJAYANAGARA | ₹65.00 L | MEDIUM 51 | |
| 10 | Development of public park in JP Nagar Hosapete Town limit Sports — Vijayanagara(DEPUTY COMMISSIONER VIJAYANAGARA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 544 days beyond expected completion
| VIJAYANAGARA | ₹50.00 L | MEDIUM 50 | |
| 11 | Develpoment of Park at Rajaginagar Area in Hosapete City Sports — Vijayanagara(DEPUTY COMMISSIONER VIJAYANAGARA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 544 days beyond expected completion
| VIJAYANAGARA | ₹50.00 L | MEDIUM 50 | |