| 1 | Ramnarayan singh ke pump ke pas Ati. transfarmar evm viddut Street Lighting — SATNA(DISTRICT COLLECTOR SATNA_IDA) - ₹549,000 against a ₹180,000 median for Street Lighting works in SATNA (205% above, 278 peer works)
- 610 days beyond expected completion
Read more (2 more)Show less- 97% similarity with another nearby work
- Implementing agency has a 76% delay rate across its projects
| SATNA | ₹5.49 L | HIGH 70 | |
| 2 | Rambali patel ke pump ke pas Ati. transfarmar & viddutikaran Street Lighting — Maihar(District Collector Maihar_IDA) - ₹245,000 against a ₹95,500 median for Street Lighting works in MAIHAR (157% above, 52 peer works)
- 581 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 73% delay rate across its projects
| MAIHAR | ₹2.45 L | MEDIUM 66 | |
| 3 | Chhedilal patel ke pump ke pas Ati. transfarmar & viddutikar Street Lighting — Maihar(District Collector Maihar_IDA) - ₹200,000 against a ₹95,500 median for Street Lighting works in MAIHAR (109% above, 52 peer works)
- 581 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 73% delay rate across its projects
| MAIHAR | ₹2.00 L | MEDIUM 66 | |
| 4 | Pcc Road Nirman Kary hetu Roads & Paving — SATNA(DISTRICT COLLECTOR SATNA_IDA) - 587 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 76% delay rate across its projects
| SATNA | ₹5.00 L | MEDIUM 64
delay 25duplication 20agency 11 | |
| 5 | Pcc Road Nirman Kary hetu Roads & Paving — SATNA(DISTRICT COLLECTOR SATNA_IDA) - 587 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 76% delay rate across its projects
| SATNA | ₹5.00 L | MEDIUM 64
delay 25duplication 20agency 11 | |
| 6 | Pcc Road Nirman Kary hetu Roads & Paving — SATNA(DISTRICT COLLECTOR SATNA_IDA) - 587 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 76% delay rate across its projects
| SATNA | ₹5.00 L | MEDIUM 64
delay 25duplication 20agency 11 | |
| 7 | Pcc Road Nirman Kary hetu Roads & Paving — Maihar(District Collector Maihar_IDA) - 587 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 73% delay rate across its projects
| MAIHAR | ₹5.00 L | MEDIUM 64
delay 25duplication 20agency 11 | |
| 8 | Pcc Road Nirman Kary hetu Roads & Paving — Maihar(District Collector Maihar_IDA) - 587 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 73% delay rate across its projects
| MAIHAR | ₹5.00 L | MEDIUM 64
delay 25duplication 20agency 11 | |
| 9 | Pcc Road Nirman Kary hetu Roads & Paving — Maihar(District Collector Maihar_IDA) - 587 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 73% delay rate across its projects
| MAIHAR | ₹5.00 L | MEDIUM 64
delay 25duplication 20agency 11 | |
| 10 | Pcc Road Nirman Kary hetu Roads & Paving — Maihar(District Collector Maihar_IDA) - 587 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 73% delay rate across its projects
| MAIHAR | ₹5.00 L | MEDIUM 64
delay 25duplication 20agency 11 | |
| 11 | Pcc Road Nirman Kary hetu Roads & Paving — Maihar(District Collector Maihar_IDA) - 587 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 73% delay rate across its projects
| MAIHAR | ₹5.00 L | MEDIUM 64
delay 25duplication 20agency 11 | |
| 12 | Sarswati shishu mandir Atirict kaksha nirman Religious & Cultural — SATNA(DISTRICT COLLECTOR SATNA_IDA) - 554 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 76% delay rate across its projects
| SATNA | ₹3.00 L | MEDIUM 64
delay 25duplication 20agency 11 | |
| 13 | Sarswati shishu mandir Atirict kaksha nirman Religious & Cultural — SATNA(DISTRICT COLLECTOR SATNA_IDA) - 554 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 76% delay rate across its projects
| SATNA | ₹3.00 L | MEDIUM 64
delay 25duplication 20agency 11 | |
| 14 | Sarswati shishu mandir Atirict kaksha nirman Religious & Cultural — Maihar(District Collector Maihar_IDA) - 554 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 73% delay rate across its projects
| MAIHAR | ₹3.00 L | MEDIUM 63
delay 25duplication 20agency 11 | |
| 15 | Sarswati shishu mandir Atirict kaksha nirman Religious & Cultural — Maihar(District Collector Maihar_IDA) - 554 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 73% delay rate across its projects
| MAIHAR | ₹3.00 L | MEDIUM 63
delay 25duplication 20agency 11 | |
| 16 | KASHaudhan Samaj Hetu Samudayik bhawan nirman Community Buildings — SATNA(DISTRICT COLLECTOR SATNA_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in SATNA (100% above, 24 peer works)
- 562 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 76% delay rate across its projects
| SATNA | ₹10.00 L | MEDIUM 61 | |
| 17 | mahurachh kandaila talab me sidhi nirman Water — SATNA(DISTRICT COLLECTOR SATNA_IDA) - ₹363,000 against a ₹163,424 median for Water works in SATNA (122% above, 55 peer works)
- 581 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 76% delay rate across its projects
| SATNA | ₹3.63 L | MEDIUM 61 | |
| 18 | Kali mandir ke pass teen sed nirman Religious & Cultural — SATNA(DISTRICT COLLECTOR SATNA_IDA) - ₹500,000 against a ₹241,000 median for Religious & Cultural works in SATNA (107% above, 14 peer works)
- 581 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 76% delay rate across its projects
| SATNA | ₹5.00 L | MEDIUM 61 | |
| 19 | Sangram Colony School ke peeche Chabutra & shed nirman Education — SATNA(DISTRICT COLLECTOR SATNA_IDA) - ₹500,000 against a ₹230,500 median for Education works in SATNA (117% above, 10 peer works)
- 581 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 76% delay rate across its projects
| SATNA | ₹5.00 L | MEDIUM 61 | |
| 20 | Nyayalay parishar me ati. kaksh nirman hetu Community Buildings — SATNA(DISTRICT COLLECTOR SATNA_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in SATNA (100% above, 24 peer works)
- 586 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 76% delay rate across its projects
| SATNA | ₹10.00 L | MEDIUM 61 | |
| 21 | Electric poles and cables will be installed in Nishant Vihar Street Lighting — SATNA(DISTRICT COLLECTOR SATNA_IDA) - ₹500,000 against a ₹180,000 median for Street Lighting works in SATNA (178% above, 278 peer works)
- 602 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 76% delay rate across its projects
| SATNA | ₹5.00 L | MEDIUM 61 | |
| 22 | Lalita gupta ke pump ke pas ati. transfarmar evm viddutikara Street Lighting — SATNA(DISTRICT COLLECTOR SATNA_IDA) - ₹576,000 against a ₹180,000 median for Street Lighting works in SATNA (220% above, 278 peer works)
- 609 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 76% delay rate across its projects
| SATNA | ₹5.76 L | MEDIUM 61 | |
| 23 | Shri Loknath Singh ke pump ke pas Ati. Transfarmar Evm viddu Street Lighting — Maihar(District Collector Maihar_IDA) - ₹300,000 against a ₹95,500 median for Street Lighting works in MAIHAR (214% above, 52 peer works)
- 545 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 73% delay rate across its projects
| MAIHAR | ₹3.00 L | MEDIUM 61 | |
| 24 | Ramsharan Dwivedi ke pump ke pas viddutikaran Street Lighting — Maihar(District Collector Maihar_IDA) - ₹216,000 against a ₹95,500 median for Street Lighting works in MAIHAR (126% above, 52 peer works)
- 581 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 73% delay rate across its projects
| MAIHAR | ₹2.16 L | MEDIUM 61 | |
| 25 | Shankar singh ke pump ke pas Ati. transfarmar & viddutikaran Street Lighting — Maihar(District Collector Maihar_IDA) - ₹240,000 against a ₹95,500 median for Street Lighting works in MAIHAR (151% above, 52 peer works)
- 581 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 73% delay rate across its projects
| MAIHAR | ₹2.40 L | MEDIUM 61 | |