65 works across 1 implementing agency, recommended by 1 member of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | Maihar(District Collector Maihar_IDA) | 65 | 15 | ₹1.29 Cr | 10 | 33.4 | R M MP Agro Satna 49% of spend · 8 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Ganesh Singh SATNA | 65 | ₹1.29 Cr | 10 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Street Lighting | 36 | ₹31.39 L | 1 |
| Water | 13 | ₹21.19 L | 3 |
| Roads & Paving | 9 | ₹45.00 L | 6 |
| Other | 3 | ₹3.35 L | 0 |
| Religious & Cultural | 1 | ₹1.15 L | 0 |
| Community Buildings | 1 | ₹5.79 L | 0 |
| Sports | 1 | ₹10.00 L | 0 |
| Equipment & Vehicles | 1 | ₹11.44 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Gram panchayat me pani tankers hetu 132 days beyond expected completion | Maihar(District Collector Maihar_IDA) | Recommended | ₹1.63 L | 132 d | 0% | 55.0 | MEDIUM |
| Gram panchayat me pani tankers hetu 132 days beyond expected completion | Maihar(District Collector Maihar_IDA) | Recommended | ₹1.63 L | 132 d | 0% | 55.0 | MEDIUM |
| Gram panchayat me pani tankers hetu 130 days beyond expected completion | Maihar(District Collector Maihar_IDA) | Recommended | ₹1.63 L | 130 d | 0% | 54.7 | MEDIUM |
| Gram Panchayat me PCC Road Nirman hetu 94 days beyond expected completion | Maihar(District Collector Maihar_IDA) | Recommended | ₹5.00 L | 94 d | 0% | 49.7 | MEDIUM |
| Gram Panchayat me PCC Road Nirman hetu 94 days beyond expected completion | Maihar(District Collector Maihar_IDA) | Recommended | ₹5.00 L | 94 d | 0% | 49.7 | MEDIUM |
| Gram Panchayat Me PCC Road Nirman hetu 94 days beyond expected completion | Maihar(District Collector Maihar_IDA) | Recommended | ₹5.00 L | 94 d | 0% | 49.7 | MEDIUM |
| Gram Panchayat Me PCC Road Nirman hetu 94 days beyond expected completion | Maihar(District Collector Maihar_IDA) | Recommended | ₹5.00 L | 94 d | 0% | 49.7 | MEDIUM |
| Gram Panchayat Me PCC Road Nirman hetu 94 days beyond expected completion | Maihar(District Collector Maihar_IDA) | Recommended | ₹5.00 L | 94 d | 0% | 49.7 | MEDIUM |
| Gram Panchayat Me PCC Road Nirman hetu 94 days beyond expected completion | Maihar(District Collector Maihar_IDA) | Recommended | ₹5.00 L | 94 d | 0% | 49.7 | MEDIUM |
| Gram kharamseda meMunnibai Patel ke pump ke pass Viddutikara ₹140,000 against a ₹95,500 median for Street Lighting works in MAIHAR (47% above, 52 peer works) | Maihar(District Collector Maihar_IDA) | Recommended | ₹1.40 L | 94 d | +47% | 42.5 | MEDIUM |
| Gram Kharamseda me Dhooplal Dahayat ke pump ke pass Viddutik 94 days beyond expected completion | Maihar(District Collector Maihar_IDA) | Recommended | ₹1.19 L | 94 d | +25% | 39.5 | LOW |
| Gram kharamseda me Krushndatt Gautam ke pump ke pass Vidduti 94 days beyond expected completion | Maihar(District Collector Maihar_IDA) | Recommended | ₹1.18 L | 94 d | +24% | 39.5 | LOW |
| Gram Jariyari me Chandravati patel ke pump ke pas Viddutikar 94 days beyond expected completion | Maihar(District Collector Maihar_IDA) | Recommended | ₹47,000 | 94 d | -51% | 39.1 | LOW |
| Gram Jariyari me Dukhi bai patel ke pump ke pas Viddutikaran 94 days beyond expected completion | Maihar(District Collector Maihar_IDA) | Recommended | ₹69,000 | 94 d | -28% | 38.7 | LOW |
| Gram Chhairaha me Duvasiya patel ke pump ke pass Viddutikara ₹140,000 against a ₹95,500 median for Street Lighting works in MAIHAR (47% above, 52 peer works) | Maihar(District Collector Maihar_IDA) | Recommended | ₹1.40 L | 94 d | +47% | 37.5 | LOW |