| 1 | MPLADS - 162
Construction work of a hall in Khasra No. 62/1 Community Buildings — JODHPUR(DISTRICT COLLECTOR JODHPUR IDA) - ₹1,600,000 against a ₹541,167 median for Community Buildings works in JODHPUR (196% above, 55 peer works)
- 605 days beyond expected completion
| JODHPUR | ₹16.00 L | MEDIUM 54 | |
| 2 | MPLADS - 372
Construction work of public library in populate Education — Phalodi(DISTRICT COLLECTOR PHALODI_IDA) - ₹1,000,000 against a ₹500,000 median for Education works in PHALODI (100% above, 63 peer works)
- 573 days beyond expected completion
| PHALODI | ₹10.00 L | MEDIUM 53 | |
| 3 | MPLADS - 86
Development work including construction of hall Community Buildings — JODHPUR(DISTRICT COLLECTOR JODHPUR IDA) - ₹1,000,000 against a ₹541,167 median for Community Buildings works in JODHPUR (85% above, 55 peer works)
- 734 days beyond expected completion
| JODHPUR | ₹10.00 L | MEDIUM 50 | |
| 4 | MPLADS - 146
Construction work of hall in Rajput Seva Samiti Community Buildings — JAISALMER(DISTRICT COLLECTOR JAISLAMER_IDA) - ₹1,700,000 against a ₹984,268 median for Community Buildings works in JAISALMER (73% above, 98 peer works)
- 717 days beyond expected completion
| JAISALMER | ₹17.00 L | MEDIUM 48 | |
| 5 | MPLADS - 245
Work of construction of a class room in Governm Education — JODHPUR(DISTRICT COLLECTOR JODHPUR IDA) - ₹1,000,000 against a ₹599,278 median for Education works in JODHPUR (67% above, 56 peer works)
- 717 days beyond expected completion
| JODHPUR | ₹10.00 L | MEDIUM 46 | |
| 6 | MPLADS - 234
Work of construction of reading room in public Community Buildings — JAISALMER(DISTRICT COLLECTOR JAISLAMER_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 717 days beyond expected completion
| JAISALMER | ₹10.00 L | MEDIUM 44 | |
| 7 | MPLADS - 218
Construction work of reading room at Khartaram Community Buildings — JAISALMER(DISTRICT COLLECTOR JAISLAMER_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 714 days beyond expected completion
| JAISALMER | ₹10.00 L | MEDIUM 44 | |
| 8 | MPLADS - 178
Work of construction of reading room on public Religious & Cultural — JODHPUR(DISTRICT COLLECTOR JODHPUR IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 732 days beyond expected completion
| JODHPUR | ₹10.00 L | MEDIUM 44 | |
| 9 | MPLADS - 158
Development construction work like boundary wal Water — JODHPUR(DISTRICT COLLECTOR JODHPUR IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 733 days beyond expected completion
| JODHPUR | ₹10.00 L | MEDIUM 44 | |
| 10 | MPLADS - 164
Work of construction of a class room in Govern Education — JODHPUR(DISTRICT COLLECTOR JODHPUR IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 733 days beyond expected completion
| JODHPUR | ₹6.00 L | MEDIUM 43 | |
| 11 | MPLADS - 177
Work of construction of a ward at Primary Heal Health — JODHPUR(DISTRICT COLLECTOR JODHPUR IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 733 days beyond expected completion
| JODHPUR | ₹8.00 L | MEDIUM 43 | |
| 12 | MPLADS - 385
Construction work of public reading room near R Religious & Cultural — Jodhpur Gramin(DISTRICT COLLECTOR JODHPUR RURAL_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 549 days beyond expected completion
| JODHPUR GRAMIN | ₹10.00 L | MEDIUM 43 | |
| 13 | MPLADS - 207
Construction work of public Pyau at Khasra No. Community Buildings — JODHPUR(DISTRICT COLLECTOR JODHPUR IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 733 days beyond expected completion
| JODHPUR | ₹7.50 L | MEDIUM 43 | |
| 14 | MPLADS - 174
Work of procurement of Kabaddi mats and materia Education — JAISALMER(DISTRICT COLLECTOR JAISLAMER_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 718 days beyond expected completion
| JAISALMER | ₹7.00 L | MEDIUM 42 | |
| 15 | MPLADS - 259
Construction work of hall and toilet near Balin Drainage & Sanitation — JAISALMER(DISTRICT COLLECTOR JAISLAMER_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 604 days beyond expected completion
| JAISALMER | ₹11.00 L | MEDIUM 42 | |
| 16 | MPLADS - 255
Work of construction of reading room on public Community Buildings — JAISALMER(DISTRICT COLLECTOR JAISLAMER_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 717 days beyond expected completion
| JAISALMER | ₹7.00 L | MEDIUM 42 | |
| 17 | MPLADS - 155 The work of construction of a hall in the Bhani Education — JAISALMER(DISTRICT COLLECTOR JAISLAMER_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 549 days beyond expected completion
| JAISALMER | ₹10.00 L | MEDIUM 42 | |
| 18 | MPLADS - 344
Construction work of e-library in Shri Hanwant Roads & Paving — JODHPUR(DISTRICT COLLECTOR JODHPUR IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 581 days beyond expected completion
| JODHPUR | ₹11.00 L | MEDIUM 42 | |
| 19 | MPLADS - 240
Construction work of Pyau with Tanka on public Water — JODHPUR(DISTRICT COLLECTOR JODHPUR IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 717 days beyond expected completion
| JODHPUR | ₹7.50 L | MEDIUM 42 | |
| 20 | MPLADS - 370
Construction work of public toilet along with r Drainage & Sanitation — JAISALMER(DISTRICT COLLECTOR JAISLAMER_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 573 days beyond expected completion
| JAISALMER | ₹10.00 L | MEDIUM 42 | |
| 21 | MPLADS - 298
Construction work of library in Government High Education — JAISALMER(DISTRICT COLLECTOR JAISLAMER_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 596 days beyond expected completion
| JAISALMER | ₹10.00 L | MEDIUM 42 | |
| 22 | MPLADS - 221
Construction work of main gate, four walls and Boundary & Protection — JAISALMER(DISTRICT COLLECTOR JAISLAMER_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 605 days beyond expected completion
| JAISALMER | ₹10.00 L | MEDIUM 42 | |
| 23 | MPLADS - 278
Construction work of reading room in Khasra No. Religious & Cultural — JAISALMER(DISTRICT COLLECTOR JAISLAMER_IDA) - 604 days beyond expected completion
| JAISALMER | ₹4.00 L | MEDIUM 42
delay 25cost 8duplication 5 | |
| 24 | MPLADS - 183
Work of construction of boundary wall and gate Boundary & Protection — JODHPUR(DISTRICT COLLECTOR JODHPUR IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 732 days beyond expected completion
| JODHPUR | ₹6.00 L | MEDIUM 41 | |
| 25 | MPLADS - 171
Work of construction of a class room in Govern Education — JODHPUR(DISTRICT COLLECTOR JODHPUR IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 733 days beyond expected completion
| JODHPUR | ₹6.00 L | MEDIUM 41 | |