| 1 | SAMUDAYIK BHAWAN NIRMAN HETU Community Buildings — Narsimhapur(DISTRICT COLLECTOR NARSINGHPUR_IDA) - ₹1,200,000 against a ₹150,000 median for Community Buildings works in NARSIMHAPUR (700% above, 180 peer works)
- 645 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 49% delay rate across its projects
| NARSIMHAPUR | ₹12.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 2 | KHERAPATI MANDIR KE PAS SAMUDAYIK BHAWAN NIRMAN HETU Community Buildings — Narsimhapur(DISTRICT COLLECTOR NARSINGHPUR_IDA) - ₹1,200,000 against a ₹150,000 median for Community Buildings works in NARSIMHAPUR (700% above, 180 peer works)
- 645 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 49% delay rate across its projects
| NARSIMHAPUR | ₹12.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 3 | SAMUDAYIK BHAWAN NIRMAN HETU Community Buildings — Narsimhapur(DISTRICT COLLECTOR NARSINGHPUR_IDA) - ₹1,200,000 against a ₹150,000 median for Community Buildings works in NARSIMHAPUR (700% above, 180 peer works)
- 645 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 49% delay rate across its projects
| NARSIMHAPUR | ₹12.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 4 | SAMUDAYIK BHAWAN NIRMAN HETU Community Buildings — Narsimhapur(DISTRICT COLLECTOR NARSINGHPUR_IDA) - ₹1,000,000 against a ₹150,000 median for Community Buildings works in NARSIMHAPUR (567% above, 180 peer works)
- 713 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 49% delay rate across its projects
| NARSIMHAPUR | ₹10.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 5 | PARK NIRMAN HETU Sports — NARMADAPURAM(DISTRICT COLLECTOR NARMADAPURAM_IDA) - ₹200,000 against a ₹105,000 median for Sports works in NARMADAPURAM (90% above, 49 peer works)
- 714 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 10 payments still in progress, oldest 431 days
| NARMADAPURAM | ₹2.00 L | HIGH 76
delay 25cost 23duplication 20 | |
| 6 | PARK NIRMAN HETU Sports — NARMADAPURAM(DISTRICT COLLECTOR NARMADAPURAM_IDA) - ₹200,000 against a ₹105,000 median for Sports works in NARMADAPURAM (90% above, 49 peer works)
- 714 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 10 payments still in progress, oldest 431 days
| NARMADAPURAM | ₹2.00 L | HIGH 76
delay 25cost 23duplication 20 | |
| 7 | COMMON SITTING AREA Community Buildings — RAISEN(DISTRICT COLLECTOR RAISEN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 784 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 85% delay rate across its projects
| RAISEN | ₹25,000 | HIGH 72
delay 25duplication 20cost 15 | |
| 8 | COMMON SITTING AREA Community Buildings — RAISEN(DISTRICT COLLECTOR RAISEN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 784 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 85% delay rate across its projects
| RAISEN | ₹10,000 | HIGH 72
delay 25duplication 20cost 15 | |
| 9 | COMMON SITTING AREA Community Buildings — RAISEN(DISTRICT COLLECTOR RAISEN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 784 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 85% delay rate across its projects
| RAISEN | ₹10,000 | HIGH 72
delay 25duplication 20cost 15 | |
| 10 | COMMON SITTING AREA Community Buildings — RAISEN(DISTRICT COLLECTOR RAISEN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 784 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 85% delay rate across its projects
| RAISEN | ₹10,000 | HIGH 72
delay 25duplication 20cost 15 | |
| 11 | COMMON SITTING AREA Community Buildings — RAISEN(DISTRICT COLLECTOR RAISEN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 784 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 85% delay rate across its projects
| RAISEN | ₹40,000 | HIGH 72
delay 25duplication 20cost 14 | |
| 12 | COMMON SITTING AREA Community Buildings — RAISEN(DISTRICT COLLECTOR RAISEN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 784 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 85% delay rate across its projects
| RAISEN | ₹50,000 | HIGH 72
delay 25duplication 20cost 14 | |
| 13 | COMMON SITTING AREA Community Buildings — RAISEN(DISTRICT COLLECTOR RAISEN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 784 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 85% delay rate across its projects
| RAISEN | ₹50,000 | HIGH 72
delay 25duplication 20cost 14 | |
| 14 | COMMUNITY HALL Community Buildings — RAISEN(DISTRICT COLLECTOR RAISEN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 784 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 85% delay rate across its projects
| RAISEN | ₹75,000 | HIGH 71
delay 25duplication 20cost 14 | |
| 15 | SAMUDAYIK BHAWAN NIRMAN HETU Community Buildings — Narsimhapur(DISTRICT COLLECTOR NARSINGHPUR_IDA) - ₹250,000 against a ₹150,000 median for Community Buildings works in NARSIMHAPUR (67% above, 180 peer works)
- 713 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 49% delay rate across its projects
| NARSIMHAPUR | ₹2.50 L | MEDIUM 69
delay 25duplication 20cost 17 | |
| 16 | WATER TAINKAR Water — RAISEN(DISTRICT COLLECTOR RAISEN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 716 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 85% delay rate across its projects
| RAISEN | ₹1.00 L | MEDIUM 68
delay 25duplication 20agency 13 | |
| 17 | WATER TAINKAR Water — RAISEN(DISTRICT COLLECTOR RAISEN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 716 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 85% delay rate across its projects
| RAISEN | ₹1.00 L | MEDIUM 68
delay 25duplication 20agency 13 | |
| 18 | WATER TAINKAR Water — RAISEN(DISTRICT COLLECTOR RAISEN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 716 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 85% delay rate across its projects
| RAISEN | ₹1.00 L | MEDIUM 68
delay 25duplication 20agency 13 | |
| 19 | WATER TAINKAR Water — RAISEN(DISTRICT COLLECTOR RAISEN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 716 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 85% delay rate across its projects
| RAISEN | ₹1.00 L | MEDIUM 68
delay 25duplication 20agency 13 | |
| 20 | GRAM SE SHANTIDHAM KI OR CC ROAD NIRMAN Roads & Paving — RAISEN(DISTRICT COLLECTOR RAISEN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 716 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 85% delay rate across its projects
| RAISEN | ₹1.50 L | MEDIUM 68
delay 25duplication 20agency 13 | |
| 21 | GRAM SE SHANTIDHAM KI OR CC ROAD NIRMAN Roads & Paving — RAISEN(DISTRICT COLLECTOR RAISEN_IDA) - 716 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 85% delay rate across its projects
| RAISEN | ₹2.00 L | MEDIUM 67
delay 25duplication 20agency 13 | |
| 22 | SARVJANIK CC CHABUTARA NIRMAN Community Buildings — Narsimhapur(DISTRICT COLLECTOR NARSINGHPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 717 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 49% delay rate across its projects
| NARSIMHAPUR | ₹50,000 | MEDIUM 64
delay 25duplication 20cost 12 | |
| 23 | SARVJANIK CC CHABUTARA NIRMAN Community Buildings — Narsimhapur(DISTRICT COLLECTOR NARSINGHPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 716 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 49% delay rate across its projects
| NARSIMHAPUR | ₹50,000 | MEDIUM 64
delay 25duplication 20cost 12 | |
| 24 | SARVJANIK CC CHABUTARA NIRMAN Community Buildings — Narsimhapur(DISTRICT COLLECTOR NARSINGHPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 716 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 49% delay rate across its projects
| NARSIMHAPUR | ₹50,000 | MEDIUM 64
delay 25duplication 20cost 12 | |
| 25 | KHERAPATI MANDIR KE PAS CC CHABUTARA NIRMAN Religious & Cultural — Narsimhapur(DISTRICT COLLECTOR NARSINGHPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 716 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 49% delay rate across its projects
| NARSIMHAPUR | ₹50,000 | MEDIUM 64
delay 25duplication 20cost 12 | |