| 1 | ADDITIONAL CLASS ROOM Education — PURULIA(DISTRICT MAGISTRATE PURULIA_IDA) - ₹2,338,000 against a ₹1,200,000 median for Education works in PURULIA (95% above, 13 peer works)
- 573 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| PURULIA | ₹23.38 L | HIGH 73
delay 25cost 24duplication 20 | |
| 2 | A.C.R
Sector Name-
Other
Sector-02 Scheme-999 Education — PURULIA(DISTRICT MAGISTRATE PURULIA_IDA) - ₹2,000,000 against a ₹1,200,000 median for Education works in PURULIA (67% above, 13 peer works)
- 568 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| PURULIA | ₹20.00 L | MEDIUM 66
delay 25duplication 20cost 17 | |
| 3 | Boundary Wall Boundary & Protection — PURULIA(DISTRICT MAGISTRATE PURULIA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 568 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| PURULIA | ₹20.00 L | MEDIUM 65
delay 25duplication 20cost 16 | |
| 4 | Community Hall Community Buildings — PURULIA(DISTRICT MAGISTRATE PURULIA_IDA) - ₹1,500,000 against a ₹1,000,000 median for Community Buildings works in PURULIA (50% above, 27 peer works)
- 566 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| PURULIA | ₹15.00 L | MEDIUM 64
delay 25duplication 20cost 15 | |
| 5 | Community Hall Community Buildings — PURULIA(DISTRICT MAGISTRATE PURULIA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 559 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| PURULIA | ₹12.00 L | MEDIUM 62
delay 25duplication 20cost 13 | |
| 6 | Hostel Education — PURULIA(DISTRICT MAGISTRATE PURULIA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 570 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| PURULIA | ₹12.00 L | MEDIUM 62
delay 25duplication 20cost 13 | |
| 7 | Hostel Education — PURULIA(DISTRICT MAGISTRATE PURULIA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 570 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| PURULIA | ₹12.00 L | MEDIUM 62
delay 25duplication 20cost 13 | |
| 8 | Community Hall Community Buildings — PURULIA(DISTRICT MAGISTRATE PURULIA_IDA) - ₹2,500,000 against a ₹1,000,000 median for Community Buildings works in PURULIA (150% above, 27 peer works)
- 77 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 42% of this agency's ₹36,305,010 spend went to one vendor (GOPAL CHANDRA CHOWDHURY), across 5 vendors and 50 transactions
| PURULIA | ₹25.00 L | MEDIUM 62
cost 25duplication 20delay 11 | |
| 9 | BOUNDARY WALL Boundary & Protection — PURULIA(DISTRICT MAGISTRATE PURULIA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 573 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| PURULIA | ₹10.00 L | MEDIUM 61
delay 25duplication 20cost 13 | |
| 10 | AUDITORIUM HALL Community Buildings — PURULIA(DISTRICT MAGISTRATE PURULIA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 570 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| PURULIA | ₹10.00 L | MEDIUM 61
delay 25duplication 20cost 12 | |
| 11 | Solar water Treatment Plant and Drinking water:1 HP Solar Wa Water — PURULIA(DISTRICT MAGISTRATE PURULIA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 566 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| PURULIA | ₹8.01 L | MEDIUM 60
delay 25duplication 20cost 11 | |
| 12 | Solar water Treatment Plant and Drinking water:1 HP Solar Wa Water — PURULIA(DISTRICT MAGISTRATE PURULIA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 566 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| PURULIA | ₹8.01 L | MEDIUM 60
delay 25duplication 20cost 11 | |
| 13 | Solar water Treatment Plant and Drinking water:1 HP Solar Wa Water — PURULIA(DISTRICT MAGISTRATE PURULIA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 566 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| PURULIA | ₹8.01 L | MEDIUM 60
delay 25duplication 20cost 11 | |
| 14 | Solar water Treatment Plant and Drinking water:1 HP Solar Wa Water — PURULIA(DISTRICT MAGISTRATE PURULIA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 566 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| PURULIA | ₹8.01 L | MEDIUM 60
delay 25duplication 20cost 11 | |
| 15 | Solar water Treatment Plant and Drinking water:1 HP Solar Wa Water — PURULIA(DISTRICT MAGISTRATE PURULIA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 566 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| PURULIA | ₹8.01 L | MEDIUM 60
delay 25duplication 20cost 11 | |
| 16 | Solar water Treatment Plant and Drinking water:1 HP Solar Wa Water — PURULIA(DISTRICT MAGISTRATE PURULIA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 566 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| PURULIA | ₹8.01 L | MEDIUM 60
delay 25duplication 20cost 11 | |
| 17 | Solar water Treatment Plant and Drinking water:1 HP Solar Wa Water — PURULIA(DISTRICT MAGISTRATE PURULIA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 566 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| PURULIA | ₹8.01 L | MEDIUM 60
delay 25duplication 20cost 11 | |
| 18 | Solar water Treatment Plant and Drinking water:1 HP Solar Wa Water — PURULIA(DISTRICT MAGISTRATE PURULIA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 566 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| PURULIA | ₹8.01 L | MEDIUM 60
delay 25duplication 20cost 11 | |
| 19 | Solar water Treatment Plant and Drinking water:1 HP Solar Wa Water — PURULIA(DISTRICT MAGISTRATE PURULIA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 566 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| PURULIA | ₹8.01 L | MEDIUM 60
delay 25duplication 20cost 11 | |
| 20 | Solar water Treatment Plant and Drinking water:1 HP Solar Wa Water — PURULIA(DISTRICT MAGISTRATE PURULIA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 567 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| PURULIA | ₹8.01 L | MEDIUM 60
delay 25duplication 20cost 11 | |
| 21 | Solar water Treatment Plant and Drinking water:1 HP Solar Wa Water — PURULIA(DISTRICT MAGISTRATE PURULIA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 567 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| PURULIA | ₹8.01 L | MEDIUM 60
delay 25duplication 20cost 11 | |
| 22 | Solar water Treatment Plant and Drinking water:1 HP Solar Wa Water — PURULIA(DISTRICT MAGISTRATE PURULIA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 567 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| PURULIA | ₹8.01 L | MEDIUM 60
delay 25duplication 20cost 11 | |
| 23 | Solar water Treatment Plant and Drinking water:1 HP Solar Wa Water — PURULIA(DISTRICT MAGISTRATE PURULIA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 567 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| PURULIA | ₹8.01 L | MEDIUM 60
delay 25duplication 20cost 11 | |
| 24 | Solar water Treatment Plant and Drinking water:1 HP Solar Wa Water — PURULIA(DISTRICT MAGISTRATE PURULIA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 567 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| PURULIA | ₹8.01 L | MEDIUM 60
delay 25duplication 20cost 11 | |
| 25 | Solar water Treatment Plant and Drinking water:1 HP Solar Wa Water — PURULIA(DISTRICT MAGISTRATE PURULIA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 567 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| PURULIA | ₹8.01 L | MEDIUM 60
delay 25duplication 20cost 11 | |