| 1 | Covering of roadside drainages by installing RCC Slabs. Drainage & Sanitation — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 757 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SOUTH GOA | ₹20.00 L | MEDIUM 66
delay 25duplication 20cost 18 | |
| 2 | Covering of roadside drainages by installing RCC Slabs. Drainage & Sanitation — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 757 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SOUTH GOA | ₹20.00 L | MEDIUM 66
delay 25duplication 20cost 18 | |
| 3 | Covering of roadside drainages by installing RCC Slabs. Drainage & Sanitation — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 757 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SOUTH GOA | ₹15.00 L | MEDIUM 65
delay 25duplication 20cost 17 | |
| 4 | Covering of roadside drainages by installing RCC Slabs. Drainage & Sanitation — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 757 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SOUTH GOA | ₹15.00 L | MEDIUM 65
delay 25duplication 20cost 17 | |
| 5 | Covering of roadside drainages by installing RCC Slabs. Drainage & Sanitation — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 757 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SOUTH GOA | ₹15.00 L | MEDIUM 65
delay 25duplication 20cost 17 | |
| 6 | Covering of roadside drainages by installing RCC Slabs. Drainage & Sanitation — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 757 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SOUTH GOA | ₹15.00 L | MEDIUM 65
delay 25duplication 20cost 17 | |
| 7 | Covering of roadside drainages by installing RCC Slabs. Drainage & Sanitation — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 757 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SOUTH GOA | ₹15.00 L | MEDIUM 65
delay 25duplication 20cost 17 | |
| 8 | Development of School payground of Regina Mundi High School, Education — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - ₹2,293,444 against a ₹1,090,000 median for Education works in SOUTH GOA (110% above, 96 peer works)
- 760 days beyond expected completion
| SOUTH GOA | ₹22.93 L | MEDIUM 52 | |
| 9 | Supply and Installation of Gym Equipment at Cuncolim Muncipa Sports — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - ₹2,910,682 against a ₹150,000 median for Sports works in SOUTH GOA (1840% above, 14 peer works)
- 760 days beyond expected completion
| SOUTH GOA | ₹29.11 L | MEDIUM 52 | |
| 10 | Construction of compound wall for community hall and a memor Community Buildings — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 757 days beyond expected completion
| SOUTH GOA | ₹35.00 L | MEDIUM 48 | |
| 11 | Extension of Cemetery of Sacred Heart of Jesus, Sanguem (Old Religious & Cultural — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 729 days beyond expected completion
| SOUTH GOA | ₹29.21 L | MEDIUM 47 | |
| 12 | Supply of slabs at VP Davorlim, Dicarpali, Salcette-Goa Drainage & Sanitation — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - ₹2,650,000 against a ₹1,500,000 median for Drainage & Sanitation works in SOUTH GOA (77% above, 17 peer works)
- 704 days beyond expected completion
| SOUTH GOA | ₹26.50 L | MEDIUM 46 | |
| 13 | Tarring/Asphalting for internal road Roads & Paving — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 690 days beyond expected completion
| SOUTH GOA | ₹25.00 L | MEDIUM 45 | |
| 14 | Upgradation of Govt. Village School playgroung, jogging trac Education — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 760 days beyond expected completion
| SOUTH GOA | ₹14.28 L | MEDIUM 44 | |
| 15 | Upgradation of Govt. Village School Playground, jogging Trac Education — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 760 days beyond expected completion
| SOUTH GOA | ₹11.15 L | MEDIUM 43 | |
| 16 | Supply of slabs at Curti Khandepar, Ponda Drainage & Sanitation — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 704 days beyond expected completion
| SOUTH GOA | ₹15.00 L | MEDIUM 43 | |
| 17 | Development of playground at Regina Mundi High School (Phase Education — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 599 days beyond expected completion
| SOUTH GOA | ₹15.00 L | MEDIUM 42 | |
| 18 | To provide and to install High
Mast 3- Arms Lights at
vari Street Lighting — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - ₹800,000 against a ₹550,000 median for Street Lighting works in SOUTH GOA (45% above, 10 peer works)
- 725 days beyond expected completion
| SOUTH GOA | ₹8.00 L | MEDIUM 41 | |