| 1 | Const. of Community Hall Manchajyoti Club Community Buildings — KAMRUP METRO(DEPUTY COMMISSIONER KAMRUP METROPOLITAN_IDA) - ₹8,000,000 against a ₹600,000 median for Community Buildings works in KAMRUP METRO (1233% above, 47 peer works)
- 616 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| KAMRUP METRO | ₹80.00 L | MEDIUM 57 | |
| 2 | construction of Milan Sangha building at Sarpara, Palashbar Community Buildings — KAMRUP(DEPUTY COMMISSIONER KAMRUP_IDA) - ₹3,000,000 against a ₹300,000 median for Community Buildings works in KAMRUP (900% above, 67 peer works)
- 555 days beyond expected completion
| KAMRUP | ₹30.00 L | MEDIUM 56 | |
| 3 | Const. of Bonda Birkuchi main Road to Siva Path at
Bonda, Wa Roads & Paving — KAMRUP METRO(DEPUTY COMMISSIONER KAMRUP METROPOLITAN_IDA) - ₹2,900,000 against a ₹2,000,000 median for Roads & Paving works in KAMRUP METRO (45% above, 77 peer works)
- 609 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| KAMRUP METRO | ₹29.00 L | MEDIUM 50 | |
| 4 | Const. of Byelane no 2 (left side) Sarusajai Karbi Path, war Roads & Paving — KAMRUP METRO(DEPUTY COMMISSIONER KAMRUP METROPOLITAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 609 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| KAMRUP METRO | ₹25.50 L | MEDIUM 49 | |
| 5 | Const. of Sagalpara Aai than Path, Guwahati, Ward no- 24 Roads & Paving — KAMRUP METRO(DEPUTY COMMISSIONER KAMRUP METROPOLITAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 609 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| KAMRUP METRO | ₹24.80 L | MEDIUM 49 | |
| 6 | Const. of Gandhi Nagar Path at Mathgharia, ward no. 52 Roads & Paving — KAMRUP METRO(DEPUTY COMMISSIONER KAMRUP METROPOLITAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 609 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| KAMRUP METRO | ₹25.00 L | MEDIUM 49 | |
| 7 | Const. of road from Excel School road to Janmejoy Basumatary Roads & Paving — KAMRUP METRO(DEPUTY COMMISSIONER KAMRUP METROPOLITAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 603 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| KAMRUP METRO | ₹25.00 L | MEDIUM 49 | |
| 8 | Const. of Excel School Road to Subhas Rongpi House Road towa Roads & Paving — KAMRUP METRO(DEPUTY COMMISSIONER KAMRUP METROPOLITAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 603 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| KAMRUP METRO | ₹25.00 L | MEDIUM 49 | |
| 9 | Const. of Seuj Path at Saukuchi, ward no. 43 Roads & Paving — KAMRUP METRO(DEPUTY COMMISSIONER KAMRUP METROPOLITAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 609 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| KAMRUP METRO | ₹24.50 L | MEDIUM 49 | |
| 10 | Const. of Sagalpara Deosal Path at Sarusajai, Ward No- 24 Roads & Paving — KAMRUP METRO(DEPUTY COMMISSIONER KAMRUP METROPOLITAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 609 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| KAMRUP METRO | ₹24.50 L | MEDIUM 49 | |
| 11 | Const. of Bhupen Hazarika Path near CISF Office, Beharbari, Roads & Paving — KAMRUP METRO(DEPUTY COMMISSIONER KAMRUP METROPOLITAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 609 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| KAMRUP METRO | ₹24.16 L | MEDIUM 49 | |
| 12 | Const. of Munia Mikir Path, Thapana, Lokhra, Roads & Paving — KAMRUP METRO(DEPUTY COMMISSIONER KAMRUP METROPOLITAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 598 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| KAMRUP METRO | ₹24.50 L | MEDIUM 49 | |
| 13 | Const. of Bye Lane no. 3 at Barsapara Roads & Paving — KAMRUP METRO(DEPUTY COMMISSIONER KAMRUP METROPOLITAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 609 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| KAMRUP METRO | ₹23.50 L | MEDIUM 49 | |
| 14 | Const. of Lokhrakona Road & 3 other byelane at Lokhra, Guwah Roads & Paving — KAMRUP METRO(DEPUTY COMMISSIONER KAMRUP METROPOLITAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 609 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| KAMRUP METRO | ₹23.50 L | MEDIUM 49 | |
| 15 | Const. of Ramnagar Sonali Path, Noonmati, Ward No - 57 Roads & Paving — KAMRUP METRO(DEPUTY COMMISSIONER KAMRUP METROPOLITAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 609 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| KAMRUP METRO | ₹23.54 L | MEDIUM 49 | |
| 16 | Const. of Sankar Path at Sawkuchi, Ward No - 24 Roads & Paving — KAMRUP METRO(DEPUTY COMMISSIONER KAMRUP METROPOLITAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 609 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| KAMRUP METRO | ₹23.00 L | MEDIUM 49 | |
| 17 | Const. of Udenkona Path at Lokhra, Guwahati Roads & Paving — KAMRUP METRO(DEPUTY COMMISSIONER KAMRUP METROPOLITAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 555 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| KAMRUP METRO | ₹24.00 L | MEDIUM 49 | |
| 18 | Const. of Boundary Wall at Pragjyotish College, Santipur, Gu Education — KAMRUP METRO(DEPUTY COMMISSIONER KAMRUP METROPOLITAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 609 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| KAMRUP METRO | ₹20.00 L | MEDIUM 49 | |
| 19 | Const. of Minaram Boro Path at Sawkuchi, Guwahati, ward no. Roads & Paving — KAMRUP METRO(DEPUTY COMMISSIONER KAMRUP METROPOLITAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 598 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| KAMRUP METRO | ₹20.50 L | MEDIUM 49 | |
| 20 | Const. of Classroom at Jyoti Vidyapith LP School, Noonmati Education — KAMRUP METRO(DEPUTY COMMISSIONER KAMRUP METROPOLITAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 555 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| KAMRUP METRO | ₹10.00 L | MEDIUM 44 | |