| 1 | Construction of pathways, concreting with drainage Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 237 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹25.00 L | MEDIUM 70
delay 25duplication 20cost 16 | |
| 2 | construction of pathways with drainage Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 237 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹25.00 L | MEDIUM 70
delay 25duplication 20cost 16 | |
| 3 | Construction of pathways with drainage Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 237 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹25.00 L | MEDIUM 70
delay 25duplication 20cost 16 | |
| 4 | Construction of pathways with drainage Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 237 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹20.00 L | MEDIUM 69
delay 25duplication 20cost 15 | |
| 5 | construction of pathways, concreting with drainage Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 237 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹20.00 L | MEDIUM 69
delay 25duplication 20cost 15 | |
| 6 | Construction of pathways, concreting with drainage Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 237 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹20.00 L | MEDIUM 69
delay 25duplication 20cost 15 | |
| 7 | Construction of pathways, concreting with drainage Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 237 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹15.00 L | MEDIUM 67
delay 25duplication 20cost 13 | |
| 8 | construction of pathways with drainage Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 237 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹15.00 L | MEDIUM 67
delay 25duplication 20cost 13 | |
| 9 | Construction of Pathways and drainage Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 237 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹10.00 L | MEDIUM 65
delay 25duplication 20cost 10 | |
| 10 | Construction of Pathways with drainage Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 237 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹10.00 L | MEDIUM 65
delay 25duplication 20cost 10 | |
| 11 | Construction of Pathways with drainage Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 237 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹10.00 L | MEDIUM 65
delay 25duplication 20cost 10 | |
| 12 | Construction of pathways and drainage Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 237 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹10.00 L | MEDIUM 65
delay 25duplication 20cost 10 | |
| 13 | Construction of roads, link roads, pathways or any other roa Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 237 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹10.00 L | MEDIUM 65
delay 25duplication 20cost 10 | |
| 14 | Construction of roads, link roads, pathways or any other roa Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 237 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹10.00 L | MEDIUM 65
delay 25duplication 20cost 10 | |
| 15 | Construction of roads, link roads, pathways or any other roa Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 237 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹10.00 L | MEDIUM 65
delay 25duplication 20cost 10 | |
| 16 | Construction of pathways or any other road with drainage sy Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 237 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹10.00 L | MEDIUM 65
delay 25duplication 20cost 10 | |
| 17 | Construction of pathways or any other road with drainage sy Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 237 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹10.00 L | MEDIUM 65
delay 25duplication 20cost 10 | |
| 18 | Construction of roads, link roads, pathways or any other roa Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 237 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹10.00 L | MEDIUM 65
delay 25duplication 20cost 10 | |
| 19 | Construction of roads, link roads, pathways or any other roa Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 237 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹10.00 L | MEDIUM 65
delay 25duplication 20cost 10 | |
| 20 | Construction of roads, link roads, pathways or any other roa Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 237 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹10.00 L | MEDIUM 65
delay 25duplication 20cost 10 | |
| 21 | Construction of roads, link roads, pathways or any other roa Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 237 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹10.00 L | MEDIUM 65
delay 25duplication 20cost 10 | |
| 22 | Construction of pathways with drainage system and concret Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 237 days beyond expected completion
Read more (2 more)Show less- 98% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹25.00 L | MEDIUM 63
delay 25cost 16duplication 14 | |
| 23 | construction of pathways with drainage, and concreting Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 237 days beyond expected completion
Read more (2 more)Show less- 99% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹15.00 L | MEDIUM 63
delay 25duplication 16cost 13 | |
| 24 | Construction of pathways or any other road with drainage sy Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 237 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹25.00 L | MEDIUM 54 | |
| 25 | Construction of link roads, pathways or any other road with Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 237 days beyond expected completion
Read more (2 more)Show less- 96% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹10.00 L | MEDIUM 53 | |