| 1 | Works of Clean Drinking Water Plant near Inam Dattapeetha un Water — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - 682 days beyond expected completion
- 99% similarity with another nearby work
Read more (1 more)Show less- 71% of this agency's ₹103,430,115 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 38 vendors and 153 transactions
| CHIKKAMAGALURU | ₹5.00 L | MEDIUM 62
delay 25duplication 15agency 12 | |
| 2 | Construction of a barrier to the big ditch next to the farm Boundary & Protection — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - ₹1,000,000 against a ₹400,000 median for Boundary & Protection works in CHIKKAMAGALURU (150% above, 11 peer works)
- 604 days beyond expected completion
Read more (1 more)Show less- 71% of this agency's ₹103,430,115 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 38 vendors and 153 transactions
| CHIKKAMAGALURU | ₹10.00 L | MEDIUM 62 | |
| 3 | Development of Balekoppa, Maridibba main road to Guladamane Roads & Paving — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - ₹1,000,000 against a ₹500,000 median for Roads & Paving works in CHIKKAMAGALURU (100% above, 257 peer works)
- 608 days beyond expected completion
Read more (1 more)Show less- 71% of this agency's ₹103,430,115 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 38 vendors and 153 transactions
| CHIKKAMAGALURU | ₹10.00 L | MEDIUM 62 | |
| 4 | Makonahalli Late Huchchegowda Memorial Trust building work i Community Buildings — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in CHIKKAMAGALURU (100% above, 108 peer works)
- 763 days beyond expected completion
Read more (1 more)Show less- 71% of this agency's ₹103,430,115 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 38 vendors and 153 transactions
| CHIKKAMAGALURU | ₹10.00 L | MEDIUM 62 | |
| 5 | Works of Clean Drinking Water Plant near Inam Dattapeetha un Water — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - 601 days beyond expected completion
- 99% similarity with another nearby work
Read more (1 more)Show less- 71% of this agency's ₹103,430,115 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 38 vendors and 153 transactions
| CHIKKAMAGALURU | ₹5.00 L | MEDIUM 60
delay 25duplication 15agency 12 | |
| 6 | Computer room construction work for Kottigehara Government H Education — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 764 days beyond expected completion
Read more (1 more)Show less- 71% of this agency's ₹103,430,115 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 38 vendors and 153 transactions
| CHIKKAMAGALURU | ₹5.00 L | MEDIUM 49 | |
| 7 | Jannapura Girijan Colony Road Development in Gonibeedu Villa Roads & Paving — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 763 days beyond expected completion
Read more (1 more)Show less- 71% of this agency's ₹103,430,115 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 38 vendors and 153 transactions
| CHIKKAMAGALURU | ₹5.00 L | MEDIUM 49 | |
| 8 | Chinniga Government Higher Primary School development work i Education — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 763 days beyond expected completion
Read more (1 more)Show less- 71% of this agency's ₹103,430,115 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 38 vendors and 153 transactions
| CHIKKAMAGALURU | ₹5.00 L | MEDIUM 49 | |
| 9 | Kudure Bettalu Colony Road Development at G Hosalli in Gonib Roads & Paving — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 763 days beyond expected completion
Read more (1 more)Show less- 71% of this agency's ₹103,430,115 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 38 vendors and 153 transactions
| CHIKKAMAGALURU | ₹5.00 L | MEDIUM 49 | |
| 10 | Development of Cow Shed(Go-shale) in Melubilre Village of As Community Buildings — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 757 days beyond expected completion
Read more (1 more)Show less- 71% of this agency's ₹103,430,115 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 38 vendors and 153 transactions
| CHIKKAMAGALURU | ₹4.75 L | MEDIUM 49 | |
| 11 | Development of footpath connecting road from Suresh Angadi's Roads & Paving — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 757 days beyond expected completion
Read more (1 more)Show less- 71% of this agency's ₹103,430,115 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 38 vendors and 153 transactions
| CHIKKAMAGALURU | ₹4.00 L | MEDIUM 49 | |
| 12 | Bikkali road development from Bhagya's House to Krishna's h Roads & Paving — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 757 days beyond expected completion
Read more (1 more)Show less- 71% of this agency's ₹103,430,115 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 38 vendors and 153 transactions
| CHIKKAMAGALURU | ₹4.00 L | MEDIUM 49 | |
| 13 | Construction of Sringeri Journalist's Community Hall Community Buildings — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 763 days beyond expected completion
Read more (1 more)Show less- 71% of this agency's ₹103,430,115 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 38 vendors and 153 transactions
| CHIKKAMAGALURU | ₹4.00 L | MEDIUM 49 | |
| 14 | Development of Melgat-Magodu Road in Markal Village Panchaya Roads & Paving — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 763 days beyond expected completion
Read more (1 more)Show less- 71% of this agency's ₹103,430,115 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 38 vendors and 153 transactions
| CHIKKAMAGALURU | ₹4.00 L | MEDIUM 49 | |
| 15 | CC road work in Karehalli Vaddarahatti Colony, Cheeranahalli Roads & Paving — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - 653 days beyond expected completion
- 71% of this agency's ₹103,430,115 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 38 vendors and 153 transactions
| CHIKKAMAGALURU | ₹5.00 L | MEDIUM 49 | |
| 16 | CC road work in Gollarhatti Colony, Cheeranahalli Village P Roads & Paving — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - 653 days beyond expected completion
- 71% of this agency's ₹103,430,115 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 38 vendors and 153 transactions
| CHIKKAMAGALURU | ₹4.00 L | MEDIUM 48 | |
| 17 | Development of Lower Kunjavalli Road of Aduvalli Gram Pancha Roads & Paving — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 608 days beyond expected completion
Read more (1 more)Show less- 71% of this agency's ₹103,430,115 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 38 vendors and 153 transactions
| CHIKKAMAGALURU | ₹7.00 L | MEDIUM 48 | |
| 18 | Development of Basarikatte Meruti Colony Road in Atthikodug Roads & Paving — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 608 days beyond expected completion
Read more (1 more)Show less- 71% of this agency's ₹103,430,115 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 38 vendors and 153 transactions
| CHIKKAMAGALURU | ₹7.00 L | MEDIUM 48 | |
| 19 | Honnalli road development work from Darekoppa to Gulle Kodi Roads & Paving — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 608 days beyond expected completion
Read more (1 more)Show less- 71% of this agency's ₹103,430,115 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 38 vendors and 153 transactions
| CHIKKAMAGALURU | ₹7.00 L | MEDIUM 48 | |
| 20 | Kondi Bailu Colony to Jogin Hittalu Colony road development Roads & Paving — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 608 days beyond expected completion
Read more (1 more)Show less- 71% of this agency's ₹103,430,115 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 38 vendors and 153 transactions
| CHIKKAMAGALURU | ₹7.00 L | MEDIUM 48 | |
| 21 | Development work of Vidyabharati Primary School in Banakal V Education — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - 694 days beyond expected completion
- 71% of this agency's ₹103,430,115 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 38 vendors and 153 transactions
| CHIKKAMAGALURU | ₹5.00 L | MEDIUM 47 | |
| 22 | Development work of District Kannada Sahitya Parishad, Chikk Community Buildings — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - 696 days beyond expected completion
- 71% of this agency's ₹103,430,115 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 38 vendors and 153 transactions
| CHIKKAMAGALURU | ₹5.00 L | MEDIUM 47 | |
| 23 | Development of Udbhava Ganapati High School in Belawadi Vill Education — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - 694 days beyond expected completion
- 71% of this agency's ₹103,430,115 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 38 vendors and 153 transactions
| CHIKKAMAGALURU | ₹4.50 L | MEDIUM 47 | |
| 24 | Community building work for Hallada Rameshwar temple in Rame Religious & Cultural — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - 696 days beyond expected completion
- 71% of this agency's ₹103,430,115 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 38 vendors and 153 transactions
| CHIKKAMAGALURU | ₹4.50 L | MEDIUM 47 | |
| 25 | CC Road Works in Scheduled Caste Colony of Lakya Hobli Iswar Roads & Paving — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - 653 days beyond expected completion
- 71% of this agency's ₹103,430,115 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 38 vendors and 153 transactions
| CHIKKAMAGALURU | ₹5.00 L | MEDIUM 46 | |