| 51 | Construction of paver block path from Ganesh Manjhi's house Roads & Paving — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - 364 days beyond expected completion
- 74% of this agency's ₹40,768,520 spend went to one vendor (ASSISTANT ENGINEER ZILA PARISHAD KHUNTI), across 3 vendors and 103 transactions
| KHUNTI | ₹2.00 L | MEDIUM 48 | |
| 52 | Upgradation of Platform and shed in Kansari Mohalla, Village Community Buildings — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 807 days beyond expected completion
Read more (1 more)Show less- 51% of this agency's ₹24,475,000 spend went to one vendor (SAHYAK ABHIYANTA SANSAD MAD), across 3 vendors and 94 transactions
| KHUNTI | ₹3.25 L | MEDIUM 48 | |
| 53 | Construction of PCC Road from Munda Masna to Fagun Bari in v Roads & Paving — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 807 days beyond expected completion
Read more (1 more)Show less- 51% of this agency's ₹24,475,000 spend went to one vendor (SAHYAK ABHIYANTA SANSAD MAD), across 3 vendors and 94 transactions
| KHUNTI | ₹2.75 L | MEDIUM 48 | |
| 54 | Construction of shed in dadul ghat podan crematorium, villag Community Buildings — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 806 days beyond expected completion
Read more (1 more)Show less- 51% of this agency's ₹24,475,000 spend went to one vendor (SAHYAK ABHIYANTA SANSAD MAD), across 3 vendors and 94 transactions
| KHUNTI | ₹3.00 L | MEDIUM 48 | |
| 55 | Construction of PCC Road in village Dorya, Blcok Arki Roads & Paving — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 806 days beyond expected completion
Read more (1 more)Show less- 51% of this agency's ₹24,475,000 spend went to one vendor (SAHYAK ABHIYANTA SANSAD MAD), across 3 vendors and 94 transactions
| KHUNTI | ₹3.00 L | MEDIUM 48 | |
| 56 | Construction of PCC road from Kochang Toli to Narsing Munda Roads & Paving — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 806 days beyond expected completion
Read more (1 more)Show less- 51% of this agency's ₹24,475,000 spend went to one vendor (SAHYAK ABHIYANTA SANSAD MAD), across 3 vendors and 94 transactions
| KHUNTI | ₹3.00 L | MEDIUM 48 | |
| 57 | Construction of Shed in ganaloya village crematorium Community Buildings — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 807 days beyond expected completion
Read more (1 more)Show less- 51% of this agency's ₹24,475,000 spend went to one vendor (SAHYAK ABHIYANTA SANSAD MAD), across 3 vendors and 94 transactions
| KHUNTI | ₹3.00 L | MEDIUM 48 | |
| 58 | Construction of Shed in Belwadag village crematorium Community Buildings — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 807 days beyond expected completion
Read more (1 more)Show less- 51% of this agency's ₹24,475,000 spend went to one vendor (SAHYAK ABHIYANTA SANSAD MAD), across 3 vendors and 94 transactions
| KHUNTI | ₹3.00 L | MEDIUM 48 | |
| 59 | Construction of Passenger Shed in Main Road Jojohatu Roads & Paving — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 807 days beyond expected completion
Read more (1 more)Show less- 51% of this agency's ₹24,475,000 spend went to one vendor (SAHYAK ABHIYANTA SANSAD MAD), across 3 vendors and 94 transactions
| KHUNTI | ₹3.00 L | MEDIUM 48 | |
| 60 | Construction of Graveyard in Teli Tola, Village Ghunsuli Religious & Cultural — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 807 days beyond expected completion
Read more (1 more)Show less- 51% of this agency's ₹24,475,000 spend went to one vendor (SAHYAK ABHIYANTA SANSAD MAD), across 3 vendors and 94 transactions
| KHUNTI | ₹3.00 L | MEDIUM 48 | |
| 61 | Construction of Bathrooms and toilet in Maliyada Ashram Drainage & Sanitation — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 807 days beyond expected completion
Read more (1 more)Show less- 51% of this agency's ₹24,475,000 spend went to one vendor (SAHYAK ABHIYANTA SANSAD MAD), across 3 vendors and 94 transactions
| KHUNTI | ₹4.00 L | MEDIUM 48 | |
| 62 | Construction of ghat in Bargarha pond of village Belangi of Water — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - ₹500,000 against a ₹300,000 median for Water works in KHUNTI (67% above, 9 peer works)
- 107 days beyond expected completion
Read more (1 more)Show less- 74% of this agency's ₹40,768,520 spend went to one vendor (ASSISTANT ENGINEER ZILA PARISHAD KHUNTI), across 3 vendors and 103 transactions
| KHUNTI | ₹5.00 L | MEDIUM 46 | |
| 63 | Construction work of PCC road and drain from Tapkara Main Ro Roads & Paving — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - ₹741,900 against a ₹400,000 median for Roads & Paving works in KHUNTI (85% above, 113 peer works)
- 74% of this agency's ₹40,768,520 spend went to one vendor (ASSISTANT ENGINEER ZILA PARISHAD KHUNTI), across 3 vendors and 103 transactions
| KHUNTI | ₹7.42 L | MEDIUM 45 | |
| 64 | Construction of Public library building in Village Ganaloya, Education — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - 584 days beyond expected completion
- 51% of this agency's ₹24,475,000 spend went to one vendor (SAHYAK ABHIYANTA SANSAD MAD), across 3 vendors and 94 transactions
| KHUNTI | ₹5.00 L | MEDIUM 43 | |
| 65 | Construction of Paver Block Road from Main Road to Bajar Tan Roads & Paving — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - 584 days beyond expected completion
- 51% of this agency's ₹24,475,000 spend went to one vendor (SAHYAK ABHIYANTA SANSAD MAD), across 3 vendors and 94 transactions
| KHUNTI | ₹5.00 L | MEDIUM 43 | |
| 66 | Construction of new Building Hall near Hanuman Mandir, Torpa Community Buildings — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - 584 days beyond expected completion
- 51% of this agency's ₹24,475,000 spend went to one vendor (SAHYAK ABHIYANTA SANSAD MAD), across 3 vendors and 94 transactions
| KHUNTI | ₹4.00 L | MEDIUM 43 | |
| 67 | Construction of PCC Road in Village Gidwa, Block: Arki, Dist Roads & Paving — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - 593 days beyond expected completion
- 51% of this agency's ₹24,475,000 spend went to one vendor (SAHYAK ABHIYANTA SANSAD MAD), across 3 vendors and 94 transactions
| KHUNTI | ₹4.00 L | MEDIUM 43 | |
| 68 | Construction of drain in village Taro near Sri Bhim Singh Mu Drainage & Sanitation — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - 593 days beyond expected completion
- 51% of this agency's ₹24,475,000 spend went to one vendor (SAHYAK ABHIYANTA SANSAD MAD), across 3 vendors and 94 transactions
| KHUNTI | ₹3.00 L | MEDIUM 42 | |
| 69 | Construction of PCC road on the road going from Khunti Mahil Roads & Paving — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - ₹600,000 against a ₹400,000 median for Roads & Paving works in KHUNTI (50% above, 113 peer works)
- 107 days beyond expected completion
Read more (1 more)Show less- 74% of this agency's ₹40,768,520 spend went to one vendor (ASSISTANT ENGINEER ZILA PARISHAD KHUNTI), across 3 vendors and 103 transactions
| KHUNTI | ₹6.00 L | MEDIUM 42 | |