Construction of PCC Road from Munda Masna to Fagun Bari in v

Roads & Paving

Jharkhand / KHUNTI — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) · Arjun Munda (KHUNTI)

Construction of PCC Road from Munda Masna to Fagun Bari in village katsimla

Overall risk score
48/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost51
Delay100
Duplication0
Agency68
Compliance0
Sanctioned
₹2.75 L
Delay
807d
Cost deviation
-31%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of rangeAI · Isolation Forest (scikit-learn)
  • 807 days beyond expected completionPublished dates
  • 51% of this agency's ₹24,475,000 spend went to one vendor (SAHYAK ABHIYANTA SANSAD MAD), across 3 vendors and 94 transactionsStatistics · Herfindahl-Hirschman index

Decision trail

Nobody has recorded a decision on this work yet.