| 26 | School bus for Harmal Panchakroshi High School, Harmal, Pern Education — NORTH GOA(DISTRICT COLLECTOR NORTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 127 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 62% delay rate across its projects
| NORTH GOA | ₹30.36 L | MEDIUM 63
duplication 20delay 18cost 16 | |
| 27 | School bus for Harmal Panchakroshi High School, Harmal, Pern Education — NORTH GOA(DISTRICT COLLECTOR NORTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 127 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 62% delay rate across its projects
| NORTH GOA | ₹30.36 L | MEDIUM 63
duplication 20delay 18cost 16 | |
| 28 | School Bus for Bal Bharti Vidhya Mandir, Ribandar, Tiswadi, Education — NORTH GOA(DISTRICT COLLECTOR NORTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 106 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 62% delay rate across its projects
| NORTH GOA | ₹31.68 L | MEDIUM 60
duplication 20cost 16delay 15 | |
| 29 | School Bus for Bal Bharti Vidhya Mandir, Ribandar, Tiswadi, Education — NORTH GOA(DISTRICT COLLECTOR NORTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 106 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 62% delay rate across its projects
| NORTH GOA | ₹31.68 L | MEDIUM 60
duplication 20cost 16delay 15 | |
| 30 | construction of community hall near Hanuman temple Nanoda V. Community Buildings — NORTH GOA(DISTRICT COLLECTOR NORTH GOA_IDA) - ₹7,888,373 against a ₹2,000,000 median for Community Buildings works in NORTH GOA (294% above, 25 peer works)
- 544 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 62% delay rate across its projects
| NORTH GOA | ₹78.88 L | MEDIUM 59 | |
| 31 | Construction of crematorium retaining wall compound wall and Community Buildings — NORTH GOA(DISTRICT COLLECTOR NORTH GOA_IDA) - ₹7,343,258 against a ₹2,000,000 median for Community Buildings works in NORTH GOA (267% above, 25 peer works)
- 544 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 62% delay rate across its projects
| NORTH GOA | ₹73.43 L | MEDIUM 59 | |
| 32 | Construction of community hall for karabhat gramsth madel ch Community Buildings — NORTH GOA(DISTRICT COLLECTOR NORTH GOA_IDA) - ₹14,525,234 against a ₹2,000,000 median for Community Buildings works in NORTH GOA (626% above, 25 peer works)
- 544 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 62% delay rate across its projects
| NORTH GOA | ₹1.45 Cr | MEDIUM 59 | |
| 33 | Providing garbage vehicle to V.P sodiem Siolim Bardez Goa Equipment & Vehicles — NORTH GOA(DISTRICT COLLECTOR NORTH GOA_IDA) - ₹2,500,000 against a ₹131,086 median for Equipment & Vehicles works in NORTH GOA (1807% above, 68 peer works)
- 544 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 62% delay rate across its projects
| NORTH GOA | ₹25.00 L | MEDIUM 59 | |
| 34 | Providing hearse van to V.P Penha-De- Franca Equipment & Vehicles — NORTH GOA(DISTRICT COLLECTOR NORTH GOA_IDA) - ₹2,600,000 against a ₹131,086 median for Equipment & Vehicles works in NORTH GOA (1883% above, 68 peer works)
- 544 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 62% delay rate across its projects
| NORTH GOA | ₹26.00 L | MEDIUM 59 | |
| 35 | Providing Hearse van to V.P Birondem Equipment & Vehicles — NORTH GOA(DISTRICT COLLECTOR NORTH GOA_IDA) - ₹2,600,000 against a ₹131,086 median for Equipment & Vehicles works in NORTH GOA (1883% above, 68 peer works)
- 544 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 62% delay rate across its projects
| NORTH GOA | ₹26.00 L | MEDIUM 59 | |
| 36 | construction of independent library blovk zantye brothers ed Education — NORTH GOA(DISTRICT COLLECTOR NORTH GOA_IDA) - ₹5,000,000 against a ₹2,485,613 median for Education works in NORTH GOA (101% above, 83 peer works)
- 544 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 62% delay rate across its projects
| NORTH GOA | ₹50.00 L | MEDIUM 59 | |
| 37 | Construction of community hall near sateri shantadurga devst Community Buildings — NORTH GOA(DISTRICT COLLECTOR NORTH GOA_IDA) - ₹8,493,404 against a ₹2,000,000 median for Community Buildings works in NORTH GOA (325% above, 25 peer works)
- 544 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 62% delay rate across its projects
| NORTH GOA | ₹84.93 L | MEDIUM 59 | |
| 38 | construction of agarshalka under MPLAD near shandurga devala Religious & Cultural — NORTH GOA(DISTRICT COLLECTOR NORTH GOA_IDA) - ₹5,000,000 against a ₹2,000,000 median for Religious & Cultural works in NORTH GOA (150% above, 11 peer works)
- 544 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 62% delay rate across its projects
| NORTH GOA | ₹50.00 L | MEDIUM 59 | |
| 39 | Proposal to purchase hearse van for the benfit of Village PA Equipment & Vehicles — NORTH GOA(DISTRICT COLLECTOR NORTH GOA_IDA) - ₹1,662,700 against a ₹131,086 median for Equipment & Vehicles works in NORTH GOA (1168% above, 68 peer works)
- 204 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 62% delay rate across its projects
| NORTH GOA | ₹16.63 L | MEDIUM 59 | |
| 40 | to provide Jumbo size photocopier machine , mini printer,pro Equipment & Vehicles — NORTH GOA(DISTRICT COLLECTOR NORTH GOA_IDA) - ₹574,640 against a ₹131,086 median for Equipment & Vehicles works in NORTH GOA (338% above, 68 peer works)
- 225 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 62% delay rate across its projects
| NORTH GOA | ₹5.75 L | MEDIUM 59 | |
| 41 | Providing bigger garbage truck for collection of door to doo Equipment & Vehicles — NORTH GOA(DISTRICT COLLECTOR NORTH GOA_IDA) - ₹1,327,771 against a ₹131,086 median for Equipment & Vehicles works in NORTH GOA (913% above, 68 peer works)
- 272 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 62% delay rate across its projects
| NORTH GOA | ₹13.28 L | MEDIUM 59 | |
| 42 | Providing Garbage Van to Village Panchayat Torxem, Pernem Go Equipment & Vehicles — NORTH GOA(DISTRICT COLLECTOR NORTH GOA_IDA) - ₹1,689,000 against a ₹131,086 median for Equipment & Vehicles works in NORTH GOA (1188% above, 68 peer works)
- 279 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 62% delay rate across its projects
| NORTH GOA | ₹16.89 L | MEDIUM 59 | |
| 43 | Request to sanction garbage van Tata 407 Gold SFC DCR 33 ca Equipment & Vehicles — NORTH GOA(DISTRICT COLLECTOR NORTH GOA_IDA) - ₹1,689,000 against a ₹131,086 median for Equipment & Vehicles works in NORTH GOA (1188% above, 68 peer works)
- 279 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 62% delay rate across its projects
| NORTH GOA | ₹16.89 L | MEDIUM 59 | |
| 44 | garbage collection vehicle to V.P Nachinola Equipment & Vehicles — NORTH GOA(DISTRICT COLLECTOR NORTH GOA_IDA) - ₹1,689,000 against a ₹131,086 median for Equipment & Vehicles works in NORTH GOA (1188% above, 68 peer works)
- 279 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 62% delay rate across its projects
| NORTH GOA | ₹16.89 L | MEDIUM 59 | |
| 45 | Garbage van to V.P Moira Equipment & Vehicles — NORTH GOA(DISTRICT COLLECTOR NORTH GOA_IDA) - ₹1,689,000 against a ₹131,086 median for Equipment & Vehicles works in NORTH GOA (1188% above, 68 peer works)
- 279 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 62% delay rate across its projects
| NORTH GOA | ₹16.89 L | MEDIUM 59 | |
| 46 | Providing Hearse van to Mapusa Municipal Council Equipment & Vehicles — NORTH GOA(DISTRICT COLLECTOR NORTH GOA_IDA) - ₹1,662,700 against a ₹131,086 median for Equipment & Vehicles works in NORTH GOA (1168% above, 68 peer works)
- 279 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 62% delay rate across its projects
| NORTH GOA | ₹16.63 L | MEDIUM 59 | |
| 47 | providing hearse van to V.P Harvalem, Bicholim Model : E6C Equipment & Vehicles — NORTH GOA(DISTRICT COLLECTOR NORTH GOA_IDA) - ₹606,181 against a ₹131,086 median for Equipment & Vehicles works in NORTH GOA (362% above, 68 peer works)
- 279 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 62% delay rate across its projects
| NORTH GOA | ₹6.06 L | MEDIUM 59 | |
| 48 | Providing Hearse Van and Mortuary Freezer Box to Valpoi Mun Equipment & Vehicles — NORTH GOA(DISTRICT COLLECTOR NORTH GOA_IDA) - ₹1,662,700 against a ₹131,086 median for Equipment & Vehicles works in NORTH GOA (1168% above, 68 peer works)
- 279 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 62% delay rate across its projects
| NORTH GOA | ₹16.63 L | MEDIUM 59 | |
| 49 | Providing Hearse Van ( Four Wheeler) to V.P Honda Equipment & Vehicles — NORTH GOA(DISTRICT COLLECTOR NORTH GOA_IDA) - ₹1,662,700 against a ₹131,086 median for Equipment & Vehicles works in NORTH GOA (1168% above, 68 peer works)
- 279 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 62% delay rate across its projects
| NORTH GOA | ₹16.63 L | MEDIUM 59 | |
| 50 | Provide artificial limb left and right side to Fulrani Shank Equipment & Vehicles — NORTH GOA(DISTRICT COLLECTOR NORTH GOA_IDA) - ₹260,650 against a ₹131,086 median for Equipment & Vehicles works in NORTH GOA (99% above, 68 peer works)
- 279 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 62% delay rate across its projects
| NORTH GOA | ₹2.61 L | MEDIUM 59 | |