| 26 | Construction of Prasanta Bordoloi Path Chiring Chapori Roads & Paving — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 720 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹10.00 L | MEDIUM 51 | |
| 27 | Infrastructure development of Tea Tribes Girls Hostel at Tin Education — TINSUKIA(DC Tinsukia) - ₹800,000 against a ₹500,000 median for Education works in TINSUKIA (60% above, 19 peer works)
- 635 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 71% delay rate across its projects
| TINSUKIA | ₹8.00 L | MEDIUM 51 | |
| 28 | Development and Beautification of Community Hall near Bor Na Community Buildings — TINSUKIA(DC Tinsukia) - ₹800,000 against a ₹500,000 median for Community Buildings works in TINSUKIA (60% above, 61 peer works)
- 636 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 71% delay rate across its projects
| TINSUKIA | ₹8.00 L | MEDIUM 51 | |
| 29 | Construction of Rajhuwa Rangamancha at Ninggam Tai Phake Religious & Cultural — TINSUKIA(DC Tinsukia) - ₹800,000 against a ₹500,000 median for Religious & Cultural works in TINSUKIA (60% above, 26 peer works)
- 636 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 71% delay rate across its projects
| TINSUKIA | ₹8.00 L | MEDIUM 51 | |
| 30 | Construction of Tirap Anchalik Jestha Nagorik Sammelan Bhawa Community Buildings — TINSUKIA(DC Tinsukia) - ₹800,000 against a ₹500,000 median for Community Buildings works in TINSUKIA (60% above, 61 peer works)
- 636 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 71% delay rate across its projects
| TINSUKIA | ₹8.00 L | MEDIUM 51 | |
| 31 | Construction of M.N. Bordoloi Path Roads & Paving — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 720 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹8.00 L | MEDIUM 50 | |
| 32 | Construction of class room of Lahoal High School Education — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 633 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹10.00 L | MEDIUM 50 | |
| 33 | Construction of Community Hall at Rangsali Nepali Gaon Community Buildings — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 635 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹10.00 L | MEDIUM 50 | |
| 34 | Infrastructure Development of Joypur auditorium Community Buildings — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 635 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹10.00 L | MEDIUM 50 | |
| 35 | Infrastructure development of Sonowal Kachari Gate, Sasoni P Boundary & Protection — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 635 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹10.00 L | MEDIUM 50 | |
| 36 | Infrastructure development of Rajgarh Rangoli High School Education — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 635 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹10.00 L | MEDIUM 50 | |
| 37 | Upgradation of Atal Bhawan at Naoholia Community Buildings — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 551 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹10.00 L | MEDIUM 49 | |
| 38 | Construction of Atal Bhawan at Oil Town (Daily Bazar), Dulia Community Buildings — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 551 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹10.00 L | MEDIUM 49 | |
| 39 | Development of Atal Bhawan at Panimudi (Tengakhat) Community Buildings — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 551 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹10.00 L | MEDIUM 49 | |
| 40 | Construction of side drain of Jugesh Borgohain path, at Chak Drainage & Sanitation — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 551 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹10.00 L | MEDIUM 49 | |
| 41 | Construction of Lengeri HS School Main Gate Ph-II, Lengeri Education — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 551 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹10.00 L | MEDIUM 49 | |
| 42 | Construction of Public Auditorium at Moran Natun Nagar Community Buildings — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 618 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹10.00 L | MEDIUM 49 | |
| 43 | Construction of Public Auditorium at Haladhibari Konwar Gaon Community Buildings — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 618 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹10.00 L | MEDIUM 49 | |
| 44 | Construction of Public Auditorium at Bhogamur Tiniali Community Buildings — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 618 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹10.00 L | MEDIUM 49 | |
| 45 | Construction of Cultural Centre near Lakhi Mandir, Dillibari Religious & Cultural — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - ₹750,000 against a ₹500,000 median for Religious & Cultural works in DIBRUGARH (50% above, 41 peer works)
- 551 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹7.50 L | MEDIUM 49 | |
| 46 | Development of Kololwlowa Sr. Basic School, Khowang Kolowlow Education — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 551 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹8.00 L | MEDIUM 48 | |
| 47 | Development of Cultural Centre of Jokai Jeoti Sangha Religious & Cultural — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 624 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹7.00 L | MEDIUM 47 | |
| 48 | Development of Cultural Centre near Ouphulia Baptish Church, Religious & Cultural — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 551 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹7.00 L | MEDIUM 47 | |
| 49 | Construction of Open Shed of Sashan at Mancotta TE Community Buildings — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - 624 days beyond expected completion
- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹6.00 L | MEDIUM 46 | |
| 50 | Construction of Ledo Bazar Community I-Tall near Sri Ram Man Religious & Cultural — TINSUKIA(DC Tinsukia) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 636 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 71% delay rate across its projects
| TINSUKIA | ₹6.00 L | MEDIUM 46 | |