Construction of Tirap Anchalik Jestha Nagorik Sammelan Bhawa
Community Buildings
Assam / TINSUKIA — TINSUKIA(DC Tinsukia) · Rameswar Teli (DIBRUGARH)
Construction of Tirap Anchalik Jestha Nagorik Sammelan Bhawan at Jagun Ph-II
Overall risk score
51/100
Blended from the five components below, each weighted as shown.
Risk components
Cost60
Delay100
Duplication0
Agency71
Compliance0
Sanctioned
₹8.00 L
Delay
636d
Cost deviation
60%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- ₹800,000 against a ₹500,000 median for Community Buildings works in TINSUKIA (60% above, 61 peer works)Peer comparison · sector labelled by Gemini Flash Lite
- 636 days beyond expected completionPublished dates
- Implementing agency has a 71% delay rate across its projectsStated compliance rule
Decision trail
Nobody has recorded a decision on this work yet.