| 26 | 31 ?? 06 ?? 170-200 ?? Other — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - ₹6,520,794 against a ₹2,480,022 median for Other works in HARDOI (163% above, 10 peer works)
- 385 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹65.21 L | MEDIUM 56 | |
| 27 | Lighting of public spaces Street Lighting — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - ₹6,968,560 against a ₹174,214 median for Street Lighting works in HARDOI (3900% above, 82 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹69.69 L | MEDIUM 56
cost 25duplication 20agency 6 | |
| 28 | Lighting of public spaces Street Lighting — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - ₹6,097,477 against a ₹174,214 median for Street Lighting works in HARDOI (3400% above, 82 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹60.97 L | MEDIUM 56
cost 25duplication 20agency 6 | |
| 29 | Lighting of public spaces Street Lighting — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - ₹9,581,750 against a ₹174,214 median for Street Lighting works in HARDOI (5400% above, 82 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹95.82 L | MEDIUM 56
cost 25duplication 20agency 6 | |
| 30 | Lighting of public spaces Street Lighting — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - ₹2,787,424 against a ₹174,214 median for Street Lighting works in HARDOI (1500% above, 82 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹27.87 L | MEDIUM 56
cost 25duplication 20agency 6 | |
| 31 | Lighting of public spaces Street Lighting — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - ₹8,710,700 against a ₹174,214 median for Street Lighting works in HARDOI (4900% above, 82 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹87.11 L | MEDIUM 56
cost 25duplication 20agency 6 | |
| 32 | construction of 06 comunity center Community Buildings — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 567 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹98.70 L | MEDIUM 54 | |
| 33 | Lighting of public spaces Street Lighting — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - ₹9,227,740 against a ₹174,214 median for Street Lighting works in HARDOI (5197% above, 82 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹92.28 L | MEDIUM 51
cost 25duplication 20agency 6 | |
| 34 | 30 ?? 6?? 170 ?? 200 Other — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - ₹4,022,832 against a ₹2,480,022 median for Other works in HARDOI (62% above, 10 peer works)
- 365 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹40.23 L | MEDIUM 51 | |
| 35 | 19 ?? 6?? 170 ?? 200 Other — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - ₹3,959,045 against a ₹2,480,022 median for Other works in HARDOI (60% above, 10 peer works)
- 365 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹39.59 L | MEDIUM 50 | |
| 36 | purchanging of bera machine Equipment & Vehicles — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 763 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹16.66 L | MEDIUM 49 | |
| 37 | ?? Other — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 760 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹5.99 L | MEDIUM 45 | |
| 38 | Room And Toilet Drainage & Sanitation — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 589 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹10.00 L | MEDIUM 44 | |
| 39 | Construction of Interlocking Road Roads & Paving — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 589 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹8.66 L | MEDIUM 43 | |
| 40 | WS/MP792/2023-2024/9105-Construction of rooms and halls in s Education — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - ₹999,983 against a ₹580,000 median for Education works in HARDOI (72% above, 14 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹10.00 L | MEDIUM 43
duplication 18cost 18agency 6 | |
| 41 | Purchase of furniture Equipment & Vehicles — HARDOI(DISTRICT MAGISTRATE HARDOI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 548 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| HARDOI | ₹6.00 L | MEDIUM 41 | |