| 1 | Laying of CC Road Roads & Paving — VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) - ₹500,000 against a ₹125,000 median for Roads & Paving works in VIKARABAD (300% above, 298 peer works)
- 548 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| VIKARABAD | ₹5.00 L | HIGH 73
cost 25delay 25duplication 20 | |
| 2 | Laying of CC Road Roads & Paving — VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) - ₹720,000 against a ₹125,000 median for Roads & Paving works in VIKARABAD (476% above, 298 peer works)
- 548 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| VIKARABAD | ₹7.20 L | HIGH 73
cost 25delay 25duplication 20 | |
| 3 | Laying of CC Road Roads & Paving — VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) - ₹500,000 against a ₹125,000 median for Roads & Paving works in VIKARABAD (300% above, 298 peer works)
- 552 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| VIKARABAD | ₹5.00 L | HIGH 73
cost 25delay 25duplication 20 | |
| 4 | Laying of CC Road Roads & Paving — VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) - ₹500,000 against a ₹125,000 median for Roads & Paving works in VIKARABAD (300% above, 298 peer works)
- 552 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| VIKARABAD | ₹5.00 L | HIGH 73
cost 25delay 25duplication 20 | |
| 5 | Laying of CC Road Roads & Paving — VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) - ₹1,000,000 against a ₹125,000 median for Roads & Paving works in VIKARABAD (700% above, 298 peer works)
- 552 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| VIKARABAD | ₹10.00 L | HIGH 73
cost 25delay 25duplication 20 | |
| 6 | Laying of CC Road From GP Building to KavaliBabu (H) at Ebba Roads & Paving — VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) - ₹500,000 against a ₹125,000 median for Roads & Paving works in VIKARABAD (300% above, 298 peer works)
- 552 days beyond expected completion
Read more (1 more)Show less- 98% similarity with another nearby work
| VIKARABAD | ₹5.00 L | MEDIUM 66
cost 25delay 25duplication 13 | |
| 7 | Laying of CC road from GP building to Kavalibabu (H) at Ebba Roads & Paving — VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) - ₹1,000,000 against a ₹125,000 median for Roads & Paving works in VIKARABAD (700% above, 298 peer works)
- 570 days beyond expected completion
Read more (1 more)Show less- 98% similarity with another nearby work
| VIKARABAD | ₹10.00 L | MEDIUM 66
cost 25delay 25duplication 13 | |
| 8 | Laying of CC Road Roads & Paving — VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) - ₹200,000 against a ₹125,000 median for Roads & Paving works in VIKARABAD (60% above, 298 peer works)
- 548 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| VIKARABAD | ₹2.00 L | MEDIUM 63
delay 25duplication 20cost 15 | |
| 9 | Providing of LED based Hi-Mast lights with Material Street Lighting — VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) - 547 days beyond expected completion
- 100% similarity with another nearby work
| VIKARABAD | ₹3.40 L | MEDIUM 57
delay 25duplication 20cost 9 | |
| 10 | Construction of Community Hall Community Buildings — VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) - 548 days beyond expected completion
- 100% similarity with another nearby work
| VIKARABAD | ₹5.00 L | MEDIUM 56
delay 25duplication 20cost 8 | |
| 11 | Providing of LED based Hi-mast lights with material Street Lighting — VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) - 547 days beyond expected completion
- 100% similarity with another nearby work
| VIKARABAD | ₹1.70 L | MEDIUM 56
delay 25duplication 20cost 8 | |
| 12 | Providing Hi-Mast Lights Street Lighting — VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) - 548 days beyond expected completion
- 100% similarity with another nearby work
| VIKARABAD | ₹3.00 L | MEDIUM 56
delay 25duplication 20cost 8 | |
| 13 | Laying of CC Road from Mangali Ramalingam (H) to Grampanchay Roads & Paving — VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) - 268 days beyond expected completion
- 100% similarity with another nearby work
| VIKARABAD | ₹1.25 L | MEDIUM 56
delay 25duplication 19cost 9 | |
| 14 | Laying of CC Road from Mangali Ramalingam (H) to Grampanchay Roads & Paving — VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) - 268 days beyond expected completion
- 100% similarity with another nearby work
| VIKARABAD | ₹1.25 L | MEDIUM 56
delay 25duplication 19cost 9 | |
| 15 | Construction of C C Road from Majid to P Balappa (H) at Chow Roads & Paving — VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) - ₹500,000 against a ₹125,000 median for Roads & Paving works in VIKARABAD (300% above, 298 peer works)
- 577 days beyond expected completion
| VIKARABAD | ₹5.00 L | MEDIUM 53 | |
| 16 | CONSTRUCTION OF CULTURAL CENTER ATB WATER TANK, KAREEMPUR VI Water — VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) - ₹500,000 against a ₹200,000 median for Water works in VIKARABAD (150% above, 69 peer works)
- 990 days beyond expected completion
| VIKARABAD | ₹5.00 L | MEDIUM 53 | |
| 17 | Construction of Cultural Centre at Balajinagar Colony Parig Religious & Cultural — VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) - ₹1,000,000 against a ₹500,000 median for Religious & Cultural works in VIKARABAD (100% above, 8 peer works)
- 1270 days beyond expected completion
| VIKARABAD | ₹10.00 L | MEDIUM 53 | |
| 18 | Augmentation to PWS Scheme at Kothapally Village of Kotepall Water — VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) - ₹500,000 against a ₹200,000 median for Water works in VIKARABAD (150% above, 69 peer works)
- 223 days beyond expected completion
| VIKARABAD | ₹5.00 L | MEDIUM 53 | |
| 19 | Laying of CC Road from Venu Pantulu House to Vadla Brahmaiah Roads & Paving — VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) - ₹500,000 against a ₹125,000 median for Roads & Paving works in VIKARABAD (300% above, 298 peer works)
- 290 days beyond expected completion
| VIKARABAD | ₹5.00 L | MEDIUM 53 | |
| 20 | Laying of CC Road in front of Police Station Premises at Dha Roads & Paving — VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) - ₹1,300,000 against a ₹125,000 median for Roads & Paving works in VIKARABAD (940% above, 298 peer works)
- 317 days beyond expected completion
| VIKARABAD | ₹13.00 L | MEDIUM 53 | |
| 21 | Providing of LED based High Mast lights with material Street Lighting — VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) - Completed work has no photographic documentation on record
- ₹500,000 against a ₹250,000 median for Street Lighting works in VIKARABAD (100% above, 52 peer works)
Read more (1 more)Show less- 100% similarity with another nearby work
| VIKARABAD | ₹5.00 L | MEDIUM 53
cost 25duplication 20compliance 5 | |
| 22 | Providing of LED based High Mast lights with material Street Lighting — VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) - Completed work has no photographic documentation on record
- ₹500,000 against a ₹250,000 median for Street Lighting works in VIKARABAD (100% above, 52 peer works)
Read more (1 more)Show less- 100% similarity with another nearby work
| VIKARABAD | ₹5.00 L | MEDIUM 53
cost 25duplication 20compliance 5 | |
| 23 | Laying of CC Road Roads & Paving — VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) - Completed work has no photographic documentation on record
- ₹493,447 against a ₹125,000 median for Roads & Paving works in VIKARABAD (295% above, 298 peer works)
Read more (1 more)Show less- 100% similarity with another nearby work
| VIKARABAD | ₹4.93 L | MEDIUM 53
cost 25duplication 20compliance 5 | |
| 24 | Laying of CC Road Roads & Paving — VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) - Completed work has no photographic documentation on record
- ₹385,414 against a ₹125,000 median for Roads & Paving works in VIKARABAD (208% above, 298 peer works)
Read more (1 more)Show less- 100% similarity with another nearby work
| VIKARABAD | ₹3.85 L | MEDIUM 53
cost 25duplication 20compliance 5 | |
| 25 | Laying of CC Road Roads & Paving — VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) - Completed work has no photographic documentation on record
- ₹500,000 against a ₹125,000 median for Roads & Paving works in VIKARABAD (300% above, 298 peer works)
Read more (1 more)Show less- 100% similarity with another nearby work
| VIKARABAD | ₹5.00 L | MEDIUM 53
cost 25duplication 20compliance 5 | |