Augmentation to PWS Scheme at Kothapally Village of Kotepall
Water
Telangana / VIKARABAD — VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) · Konda Vishweshwar Reddy (CHELVELLA)
Augmentation to PWS Scheme at Kothapally Village of Kotepally Mandal
Overall risk score
53/100
Blended from the five components below, each weighted as shown.
Risk components
Cost100
Delay100
Duplication0
Agency21
Compliance0
Sanctioned
₹5.00 L
Delay
223d
Cost deviation
150%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- ₹500,000 against a ₹200,000 median for Water works in VIKARABAD (150% above, 69 peer works)Peer comparison · sector labelled by Gemini Flash Lite
- 223 days beyond expected completionPublished dates
Decision trail
Nobody has recorded a decision on this work yet.