| 1 | Regarding the installation of High Mast light at Sita Kund D Street Lighting — SULTANPUR(DISTRICT MAGISTRATE SULTANPUR_IDA) - ₹1,296,194 against a ₹563,000 median for Street Lighting works in SULTANPUR (130% above, 44 peer works)
- 158 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| SULTANPUR | ₹12.96 L | HIGH 73
cost 25delay 22duplication 20 | |
| 2 | Regarding the installation of High Mast light at Sita Kund D Street Lighting — SULTANPUR(DISTRICT MAGISTRATE SULTANPUR_IDA) - ₹1,296,194 against a ₹563,000 median for Street Lighting works in SULTANPUR (130% above, 44 peer works)
- 158 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| SULTANPUR | ₹12.96 L | HIGH 73
cost 25delay 22duplication 20 | |
| 3 | Recommendation for Installation of Two Water Coolers at Pant Water — SULTANPUR(DISTRICT MAGISTRATE SULTANPUR_IDA) - ₹744,780 against a ₹372,390 median for Water works in SULTANPUR (100% above, 11 peer works)
- 78 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| SULTANPUR | ₹7.45 L | MEDIUM 62
cost 25duplication 20delay 11 | |
| 4 | Recommendation for Installation of Two Water Coolers at Pant Water — SULTANPUR(DISTRICT MAGISTRATE SULTANPUR_IDA) - ₹744,780 against a ₹372,390 median for Water works in SULTANPUR (100% above, 11 peer works)
- 78 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| SULTANPUR | ₹7.45 L | MEDIUM 62
cost 25duplication 20delay 11 | |
| 5 | Construction of a Cement Concrete CC Road at Vikas Khand Dub Roads & Paving — SULTANPUR(DISTRICT MAGISTRATE SULTANPUR_IDA) - ₹2,600,000 against a ₹820,890 median for Roads & Paving works in SULTANPUR (217% above, 60 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| SULTANPUR | ₹26.00 L | MEDIUM 51
cost 25duplication 20agency 6 | |
| 6 | Construction of a Cement Concrete CC Road at Vikas Khand Dub Roads & Paving — SULTANPUR(DISTRICT MAGISTRATE SULTANPUR_IDA) - ₹2,600,000 against a ₹820,890 median for Roads & Paving works in SULTANPUR (217% above, 60 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| SULTANPUR | ₹26.00 L | MEDIUM 51
cost 25duplication 20agency 6 | |
| 7 | Installation of two RO Water Coolers at Ward 7 Civil Lines D Water — SULTANPUR(DISTRICT MAGISTRATE SULTANPUR_IDA) - ₹700,000 against a ₹372,390 median for Water works in SULTANPUR (88% above, 11 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| SULTANPUR | ₹7.00 L | MEDIUM 48
cost 22duplication 20agency 6 | |
| 8 | Installation of two RO Water Coolers at Ward 7 Civil Lines D Water — SULTANPUR(DISTRICT MAGISTRATE SULTANPUR_IDA) - ₹700,000 against a ₹372,390 median for Water works in SULTANPUR (88% above, 11 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| SULTANPUR | ₹7.00 L | MEDIUM 48
cost 22duplication 20agency 6 | |
| 9 | Recommendation for Installation of Two High Mass light at Pa Sports — SULTANPUR(DISTRICT MAGISTRATE SULTANPUR_IDA) - 78 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| SULTANPUR | ₹13.00 L | MEDIUM 47
duplication 20delay 11cost 10 | |
| 10 | Recommendation for Installation of Two High Mass light at Pa Sports — SULTANPUR(DISTRICT MAGISTRATE SULTANPUR_IDA) - 78 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| SULTANPUR | ₹13.00 L | MEDIUM 47
duplication 20delay 11cost 10 | |
| 11 | I have received a request from Shri Mohammad Mustafa (Babu), Water — SULTANPUR(DISTRICT MAGISTRATE SULTANPUR_IDA) - 77 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| SULTANPUR | ₹3.72 L | MEDIUM 43
duplication 20delay 11agency 6 | |
| 12 | I have received a request from Shri Mohammad Mustafa (Babu), Water — SULTANPUR(DISTRICT MAGISTRATE SULTANPUR_IDA) - 77 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| SULTANPUR | ₹3.72 L | MEDIUM 43
duplication 20delay 11agency 6 | |