| 1 | Construction of three (3) classrooms. Education — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - ₹4,008,840 against a ₹1,090,000 median for Education works in SOUTH GOA (268% above, 96 peer works)
- 573 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SOUTH GOA | ₹40.09 L | HIGH 75
cost 25delay 25duplication 20 | |
| 2 | Construction of three (3) classrooms. Education — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - ₹4,008,840 against a ₹1,090,000 median for Education works in SOUTH GOA (268% above, 96 peer works)
- 573 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SOUTH GOA | ₹40.09 L | HIGH 72
cost 25delay 25duplication 20 | |
| 3 | Covering of roadside drainages by installing RCC Slabs. Drainage & Sanitation — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 757 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SOUTH GOA | ₹20.00 L | MEDIUM 66
delay 25duplication 20cost 18 | |
| 4 | Covering of roadside drainages by installing RCC Slabs. Drainage & Sanitation — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 757 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SOUTH GOA | ₹20.00 L | MEDIUM 66
delay 25duplication 20cost 18 | |
| 5 | Covering of roadside drainages by installing RCC Slabs. Drainage & Sanitation — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 757 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SOUTH GOA | ₹15.00 L | MEDIUM 65
delay 25duplication 20cost 17 | |
| 6 | Covering of roadside drainages by installing RCC Slabs. Drainage & Sanitation — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 757 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SOUTH GOA | ₹15.00 L | MEDIUM 65
delay 25duplication 20cost 17 | |
| 7 | Covering of roadside drainages by installing RCC Slabs. Drainage & Sanitation — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 757 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SOUTH GOA | ₹15.00 L | MEDIUM 65
delay 25duplication 20cost 17 | |
| 8 | Covering of roadside drainages by installing RCC Slabs. Drainage & Sanitation — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 757 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SOUTH GOA | ₹15.00 L | MEDIUM 65
delay 25duplication 20cost 17 | |
| 9 | Covering of roadside drainages by installing RCC Slabs. Drainage & Sanitation — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 757 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SOUTH GOA | ₹15.00 L | MEDIUM 65
delay 25duplication 20cost 17 | |
| 10 | School Bus for Balram Higher Secondary School, Ardhfond, Poi Education — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - Completed work has no photographic documentation on record
- ₹2,776,654 against a ₹1,090,000 median for Education works in SOUTH GOA (155% above, 96 peer works)
Read more (1 more)Show less- 100% similarity with another nearby work
| SOUTH GOA | ₹27.77 L | MEDIUM 55
cost 25duplication 20agency 5 | |
| 11 | School Bus for Shree Vishwanath Arlekar DADA Arlekar Memoria Education — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - Completed work has no photographic documentation on record
- ₹2,569,336 against a ₹1,090,000 median for Education works in SOUTH GOA (136% above, 96 peer works)
Read more (1 more)Show less- 100% similarity with another nearby work
| SOUTH GOA | ₹25.69 L | MEDIUM 55
cost 25duplication 20agency 5 | |
| 12 | School Bus for International Sadguru Gurukulum, Tapobhoomi, Education — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - Completed work has no photographic documentation on record
- ₹2,481,288 against a ₹1,090,000 median for Education works in SOUTH GOA (128% above, 96 peer works)
Read more (1 more)Show less- 100% similarity with another nearby work
| SOUTH GOA | ₹24.81 L | MEDIUM 55
cost 25duplication 20agency 5 | |
| 13 | Development of School payground of Regina Mundi High School, Education — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - ₹2,293,444 against a ₹1,090,000 median for Education works in SOUTH GOA (110% above, 96 peer works)
- 760 days beyond expected completion
| SOUTH GOA | ₹22.93 L | MEDIUM 52 | |
| 14 | Supply and Installation of Gym Equipment at Cuncolim Muncipa Sports — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - ₹2,910,682 against a ₹150,000 median for Sports works in SOUTH GOA (1840% above, 14 peer works)
- 760 days beyond expected completion
| SOUTH GOA | ₹29.11 L | MEDIUM 52 | |
| 15 | School Bus for Balram Higher Secondary School, Ardhfond, Poi Education — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - Completed work has no photographic documentation on record
- ₹2,776,654 against a ₹1,090,000 median for Education works in SOUTH GOA (155% above, 96 peer works)
Read more (1 more)Show less- 100% similarity with another nearby work
| SOUTH GOA | ₹27.77 L | MEDIUM 52
cost 25duplication 20compliance 5 | |
| 16 | School Bus for Shree Vishwanath Arlekar DADA Arlekar Memoria Education — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - Completed work has no photographic documentation on record
- ₹2,569,336 against a ₹1,090,000 median for Education works in SOUTH GOA (136% above, 96 peer works)
Read more (1 more)Show less- 100% similarity with another nearby work
| SOUTH GOA | ₹25.69 L | MEDIUM 52
cost 25duplication 20compliance 5 | |
| 17 | School Bus for International Sadguru Gurukulum, Tapobhoomi, Education — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - Completed work has no photographic documentation on record
- ₹2,481,288 against a ₹1,090,000 median for Education works in SOUTH GOA (128% above, 96 peer works)
Read more (1 more)Show less- 100% similarity with another nearby work
| SOUTH GOA | ₹24.81 L | MEDIUM 52
cost 25duplication 20compliance 5 | |
| 18 | School Bus for Late Shri Vinayak Gopal Shenvi Vidyalaya, Raw Education — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - ₹2,485,613 against a ₹1,090,000 median for Education works in SOUTH GOA (128% above, 96 peer works)
- 100% similarity with another nearby work
| SOUTH GOA | ₹24.86 L | MEDIUM 50
cost 25duplication 20agency 5 | |
| 19 | School Bus for Sarvodaya High School, Usgaon, Ponda, North G Education — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - ₹2,424,897 against a ₹1,090,000 median for Education works in SOUTH GOA (122% above, 96 peer works)
- 100% similarity with another nearby work
| SOUTH GOA | ₹24.25 L | MEDIUM 50
cost 25duplication 20agency 5 | |
| 20 | School Bus for Shiksha Sadan High School, Pirol, Mardol, Pon Education — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - ₹2,424,897 against a ₹1,090,000 median for Education works in SOUTH GOA (122% above, 96 peer works)
- 100% similarity with another nearby work
| SOUTH GOA | ₹24.25 L | MEDIUM 50
cost 25duplication 20agency 5 | |
| 21 | PUCHASE OF SCHOOL BUS for SARVODAYA EDUCATIONAL SOCIETY’S HI Education — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - ₹2,767,057 against a ₹1,090,000 median for Education works in SOUTH GOA (154% above, 96 peer works)
- 100% similarity with another nearby work
| SOUTH GOA | ₹27.67 L | MEDIUM 50
cost 25duplication 20agency 5 | |
| 22 | SCHOOL BUS for Popular High School, Margao, Salcete, South G Education — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - ₹2,484,987 against a ₹1,090,000 median for Education works in SOUTH GOA (128% above, 96 peer works)
- 100% similarity with another nearby work
| SOUTH GOA | ₹24.85 L | MEDIUM 50
cost 25duplication 20agency 5 | |
| 23 | School Bus for Keshav Smruti Higher Secondary School, Alto D Education — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - ₹2,400,201 against a ₹1,090,000 median for Education works in SOUTH GOA (120% above, 96 peer works)
- 100% similarity with another nearby work
| SOUTH GOA | ₹24.00 L | MEDIUM 50
cost 25duplication 20agency 5 | |
| 24 | To provide roofing sheets for the school building under MPLA Education — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - ₹4,357,756 against a ₹1,090,000 median for Education works in SOUTH GOA (300% above, 96 peer works)
- 139 days beyond expected completion
| SOUTH GOA | ₹43.58 L | MEDIUM 50 | |
| 25 | Development of Government Village School Plyground t New Vad Education — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - ₹3,500,000 against a ₹1,090,000 median for Education works in SOUTH GOA (221% above, 96 peer works)
- 139 days beyond expected completion
| SOUTH GOA | ₹35.00 L | MEDIUM 50 | |